Prima Comm Guide Line (Ignore CCTV)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 30

PR1MA DEVELOPMENT ICT

INFRA DESIGN GUIDELINES


FOR DEVELOPERS
VERSION 2
PERBADANAN PR1MA MALAYSIA
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

Table of Contents
1.1 INTRODUCTION.......................................................................................................................... 2
1.1 GENERAL ............................................................................................................................ 2
1.2 OBJECTIVES ........................................................................................................................ 2
1.3 SCOPE ................................................................................................................................ 3
2 OWNERSHIP AND RESPONSIBILITY .............................................................................................. 5
2.1 Ownership .......................................................................................................................... 5
2.2 Responsibility Matrix .......................................................................................................... 5
2.2.1 Broadband and Telephony Services ..............................................................................................5
2.2.2 CCTV Surveillance and SMATV ......................................................................................................7
2.3 Scope of Work Demarcation between PR1MA Communications and Developer .................... 8
2.3.1 Scope of Work Demarcation for Multi-Dwelling Units (MDU) .....................................................8
2.3.2 Scope of Work Demarcation for Singe-Dwelling Units (SDU) ......................................................8
3 SCOPE OF WORK FOR DIFFERENT PR1MA DEVELOPMENT MODELS ............................................... 9
3.1 Broadband and Telephony Services ..................................................................................... 9
3.1.1 For all PR1MA Developments: PR1MA Own, Joint Venture (JV) and MEPBA .............................9
3.1.2 Exception........................................................................................................................................9
3.2 CCTV Surveillance System ................................................................................................. 10
3.2.1 PR1MA Own, Joint Venture (JV) and MEPBA (EN-BLOCK) .........................................................10
3.2.2 Exception......................................................................................................................................10
4 BASIS OF DESIGN ...................................................................................................................... 11
5 DESIGN GUIDELINES .................................................................................................................. 12
5.1 GENERAL GUIDELINE ......................................................................................................... 12
5.2 GUIDELINE FOR MULTI-DWELLING UNITS (MDU) ................................................................ 15
5.2.1 NETWORK DESIGN ......................................................................................................................15
5.2.2 OSP PLANNING REQUIREMENTS ................................................................................................16
5.3 GUIDELINE FOR SINGLE-DWELLING UNITS (SDU) ............................................................... 21
5.3.1 NETWORK DESIGN ......................................................................................................................21
5.3.2 OSP PLANNING REQUIREMENTS ................................................................................................22
5.4 GUIDELINE FOR CCTV ....................................................................................................... 27
5.5 SMATV GUIDELINES ......................................................................................................... 28
6 CCC SUBMISSION PROCEDURE................................................................................................... 29

____________________________________________________________________________________________________
October, 2014 Page 1 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

1. INTRODUCTION
1.1 GENERAL

PR1MA Communications Sdn Bhd (“PR1MA Comm”), a wholly owned subsidiary or Perbadanan
PR1MA Malaysia will undertake the design, build, operate and maintain the IT and
Telecommunication infrastructure in all PR1MA developments.
This document serves as a General Design Guideline for PR1MA development areas specifically to
facilitate the deployment of ICT related infrastructure and services.
This document must be read in conjunction with the PR1MA Planning & Development Guideline and
the guidelines set-forth by Malaysian Communications and Multimedia Commission (MCMC) in the
Malaysian Technical Standards Forum Berhad (MTSFB) publications; Technical Standards &
Infrastructure Requirements – Fixed Network Infrastructure & Technical Standard of In-building Fibre
Cabling for Fibre-to-the-Premise.
The deployment of the ICT infrastructure and network is not limited to this guideline only and
therefore the M&E consultant should explore suitable or better alternatives without deviating from
the principles as stated in this document to ascertain that the objectives as stated below are met.

1.2 OBJECTIVES

1. To provide Fibre-to-the–home (FTTH) and Fibre-to-the-office (FTTO) cable network using the
GPON (Gigabit Passive Optical Network) technology as specified by ITU (International
Telecommunications Union) and MEF (Metro-E Forum) necessary for housing units and related
commercial areas.

2. To provide robust and future-proof GPON and AE (Active Ethernet) fibre optic network
infrastructure to cater for Triple/Quad Play and IP-based services for residential and commercial
buildings of PR1MA.

3. To provide IP-based infrastructure to be 4G-ready suitable for bandwidths and backhaul services
for cellular service providers within PR1MA development areas.

4. To facilitate the design of a cable network infrastructure which is capable of providing ‘equal
access’ enabling the entry of multiple service providers using a single network architecture owned
by PR1MA.

____________________________________________________________________________________________________
October, 2014 Page 2 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

1.3 SCOPE

1. The guideline covers the following:

OUTSIDE PLANT/INSIDE PLANT • Manholes and ducting and related accessories

PASSIVE NETWORKS • External Cabling network design and specifications


(FIBRE, SPLITTERS, ETC.) inclusive of the related materials and accessories.
• Internal cabling network design and specifications
inclusive of the related materials and accessories.

VOIP PHONES - CABLING • Internal (within house units) cabling design and
specifications inclusive of the related materials and
accessories.

CCTV SURVEILLANCE – CABLING • External cabling design and specifications inclusive of


the related materials and accessories.
• Internal (within house units) cabling design and
specifications inclusive of the related materials and
accessories.

2. The guideline DOES NOT cover the following:

TELECOMMUNICATION SERVICES PR1MA Communications is to install, operate, manage &


maintain all IT and Telecommunication services, e.g.
Broadband, VoIP, IPTV, etc.

ACTIVE NETWORK EQUIPMENT To be provided by PR1MA Communications

CCTV SURVEILLANCE – SERVICE & PR1MA Communications is to install, operate, manage &
MAINTENANCE maintain

PHYSICAL ACCESS Physical access such as:


• Vehicle access to the development area
• Access to the block/units
shall be managed by the Facility Management company
(either a subsidiary company of PR1MA or a Joint-Venture
company between PR1MA and other parties, or an
outsourced facility management company appointed by
PR1MA)

____________________________________________________________________________________________________
October, 2014 Page 3 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

PHYSICAL SECURITY Physical security is provided by PR1MA in PR1MA


Development via outsourcing model to security service
providers

PA SYSTEM PA System shall be part and parcel of the design concept by


the M&E Consultant in accordance to the Uniform Building
By-Law. The provision of PA System is subject to
requirements by the Local Authority as per approved
Development Order and Building Plan

CENTRAL CONTROL ROOM (CCR) The provision of CCR is part of the design concept by the
M&E Consultant and the Project Architect in accordance to
requirements for each development.

OPTICAL FIBRE DISTRIBUTION FRAME • Not required.


(ODF/OFDF) ROOM • Splitters are to be installed in the riser or ceiling.
Cabling and systems up to the individual house units to be
MASTER ANTENNA TV/SMATV/DIGITAL
TV provided by PR1MA Communications

____________________________________________________________________________________________________
October, 2014 Page 4 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

2 OWNERSHIP AND RESPONSIBILITY


2.1 Ownership
1. PR1MA will own the network infrastructure in all developments for all Passive (cable access) and
Active (Optical Line Terminal and Optical Network Terminal) networks including Outside Plant
(OSP).

2. PR1MA will own all ICT related services including the equipment/system to support those services.

2.2 Responsibility Matrix

2.2.1 Broadband and Telephony Services


Elements Developer/Main Contractor PR1MA Communications
OSP 1. To design, deliver, install, test and 1. To provide design guidelines and
commission the following OSP items: specification.
- Manholes
- Ducts
- Plinth 2. To review and approve drawing and
- Telecommunication room and other design.
facilities according to PR1MA Comm
design guidelines and specifications.
3. To provide Support Letter for DO
2. To coordinate with PR1MA approval (Development Order) and
Comm during implementation. CCC submission.

3. 3. To provide access to site for 4. To provide maintenance and


PR1MA Comm and its support as the Telecommunication
subcontractors. Provider.
ISP To provide: 1. To provide design guidelines and
specification.
- Conduit
- Back box for FTB,
- Cable tray 2. To review and approve drawing and
- FWS design.
- Trunking
3. To provide maintenance and
Developer to provide the above
support as Telecommunication
according to PR1MA Comm design
Provider
for High-rise and Landed
development.

____________________________________________________________________________________________________
October, 2014 Page 5 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

Cabling and 1. To provide indoor drop cable from 1. To design, deliver and install, test
Accessories FTB point up to FWS for High-rise & and commission end to end FTTH
(Drop fibre, Splitter, Landed development passive elements.
FTB, etc.) - Splitters
2. To perform indoor drop cable - FTB
labelling and testing
- ODF (Optical Distribution Frame)
- Closures
- Feeder Fiber Cables
- Fiber cables management cabinet

2. To provide maintenance and


support as Telecommunication
Provider
Active Elements and Not Applicable 1. To design, deliver, install, test and
Telecommunication commission all active equipment
Services required to provide the
telecommunication services.

2. To provide maintenance and support


as Telecommunication Provider

Land 1. To allocate a reserve land for 1. To install, operate, manage &


telecommunication for both High maintain all IT and Telecommunication
rise (MDU) and landed (SDU) services on the reserved land

2. The reserved land shall be titled


under Perbadanan PR1MA
Malaysia

____________________________________________________________________________________________________
October, 2014 Page 6 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

2.2.2 CCTV Surveillance and SMATV

Elements Developer/Main Contractor PR1MA Communications


CCTV Surveillance 1. To design and provide dedicated 1. To provide design guidelines and
conduit or trunking, network points specification.
(camera to be installed by PR1MA
Comm) and power termination points
according to PR1MA Comm design 2. To review, approve drawing and
guidelines. design of the infrastructure

2.To provide CCR (subject to the size 3. To design, deliver, cabling, install,
of the development & to be test, commission and hand over
confirmed by Facilities Management) complete CCTV system.
with following requirements:

3. Commercial (TNB, Malakof etc) &


Essential (gen-set) power supply
- Air Cond
- Lighting
- Earth bar for grounding

SMATV 1. To allocate space and power supply 1. To provide design guidelines and
at the rooftop to install the central specification.
Satellite Dish System.

2. To review, approve drawing and


design of the infrastructure

3. To design, deliver, install, test,


commission and hand over SMATV
systems

4. To provide service, maintenance


and support as Telecommunication
Provider

____________________________________________________________________________________________________
October, 2014 Page 7 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

2.3 Scope of Work Demarcation between PR1MA Communications and


Developer

2.3.1 Scope of Work Demarcation for Multi-Dwelling Units (MDU)


The scope of work demarcation for multi-dwelling units is illustrated in below diagram

HOUSE UNIT CORRIDOR RISER


LEGEND:
RED COLOUR - BY PR1MA COMM
GREEN COLOUR - BY DEVELOPER
PC – BY PR1MA COMM TRUNKING (D)
D – BY DEVELOPER
DROP CABLE (D)

FTB (PC)

CONCEALED CONDUIT (D) FIBER CABBLE (PC)

VERTICAL CABLE TRAY (D)

HDPE DUCT (D) TELCO


ROOM (D)

FIBER PIT (D)

MANHOLE (D)

FIBER CABLE (PC)


HDPE DUCT INSIDE SLAB (D)

2.3.2 Scope of Work Demarcation for Singe-Dwelling Units (SDU)


The scope of work demarcation for single-dwelling units is illustrated in below diagram

LEGEND:
RED COLOUR - BY PR1MA COMM
GREEN COLOUR - BY DEVELOPER
PC – BY PR1MA COMM
D – BY DEVELOPER
DROP CABLE (D)
FTB (PC) BACK BOX (D)

CONCEALED CONDUIT (D)


1500mm

FWS IN MAIN LIVING


ROOM (D)
300mm

DRAIN
25mmØ UPVC CONDUIT (D)
JUNCTION BOX (D)

FIBER CABLE (PC)

HDPE DUCT (D)

____________________________________________________________________________________________________
October, 2014 Page 8 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

3 SCOPE OF WORK FOR DIFFERENT PR1MA DEVELOPMENT


MODELS

3.1 Broadband and Telephony Services

3.1.1 For all PR1MA Developments: PR1MA Own, Joint Venture (JV) and MEPBA
Dev. Model Stage Developer/Main Contractor PR1MA Comm
PR1MA Own All • To provide Telecommunication • Design
Room with facilities • No Objection Letter
• To provide conduit, cable tray, • Implementation
FWS, back box, Indoor drop • Operation
cable • Maintenance & Support
• To provide power termination
• To provide plinth
Joint Venture All • To provide Telecommunication • Design
Room with facility • No Objection Letter
• To provide conduit, cable tray, • Implementation
FWS, back box, Indoor drop • Operation
cable • Maintenance & Support
• To provide power termination
• To provide plinth
MEBPA All • To provide Telecommunication • Design or redesign (depending on
Room facility development stage)
• To provide conduit, cable tray, • No Objection Letter
FWS ,back box, Indoor drop • Implementation
cable • Operation
• To provide power termination • Maintenance & Support
• To provide plinth

3.1.2 Exception

There is no exception, all PR1MA developments will follow the model in section 3.1.1 above.
For MEBPA projects that already have DO and/or BP approval, PR1MA Communications will review the
design and recommend possible omissions from the developer’s scope to make sure the project is aligned
with PR1MA overall IT and Telecommunication strategy.

____________________________________________________________________________________________________
October, 2014 Page 9 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

3.2 CCTV Surveillance System

3.2.1 PR1MA Own, Joint Venture (JV) and MEPBA (EN-BLOCK)


Dev. Model Stage Developer/Main Contractor PR1MA
PR1MA Own All • CCC Room with facility • Design
• To provide conduit • Implementation
• To provide power termination • Support & Maintenance

Joint Venture All • CCC Room with facility • Design


• To provide conduit • Implementation
• To provide power termination • Support & Maintenance
ME All • CCC Room with facility • Design or redesign (depending on
• To provide conduit development stage)
• To provide power termination • Implementation
• Support & Maintenance

3.2.2 Exception

There is no exception, all PR1MA developments will follow the model in section 3.2.1 above.
CCTV will not be part of the Developer/Main Contractor scope of work.

____________________________________________________________________________________________________
October, 2014 Page 10 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

4 BASIS OF DESIGN

1. The following MTSFB (Malaysian Technical Standards Forum Berhad) publications provide the
general guide for the design of the infrastructure & network:
a) Technical Standards & Infrastructure Requirements – Fixed Network Infrastructure
b) Technical Standard of In-building Fibre Cabling for Fibre-to-the-Premise

2. Enabling the Convergence of Network for Quad/Triple Play and Smart Services suitable for Fixed-
Mobile Convergence (FMC).

3. FTTH and FTTO transport network based on GPON and AE technology for all dwellings.

4. Proposed FTTx design offers complete flexibility to support open system architecture which can
cater for future passive or active network upgrades.

5. Network design to be able to cater for “Open-Access” for multiple service providers.

6. Wireless Hotspots to be made available with the capability to provide 3G/4G WiFi offloads in
common and public areas for both indoor and outdoor locations.

7. Centralised UPS in Telecommunication Room.

8. The FTTH infrastructure is designed to be able to support triple play services (High speed
broadband, Voice and media content)

9. The developer must provide a separate electrical meter and electricity wiring for the
telecommunications services.

10. The Consultant/Developer is to provide cable trunking, conduits, FWS, back box, Indoor drop cable
and related facilities within the buildings, and ducts & manholes within the development area.

11. Actual cable network designs may differ at different sites depending on the network topology and
the nature of the dwellings

____________________________________________________________________________________________________
October, 2014 Page 11 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

5 DESIGN GUIDELINES

5.1 GENERAL GUIDELINE

1. Manhole
Outside
• Common Manhole
Plant
• To have a Common Manhole for Telco’s to access to the PR1MA development
• Telco’s to provide connectivity from their manhole to the Common Manhole.
• To be located at the border between the public area and the developer’s area,
closest to the main road.
• Common Manhole to be type JRC7.
• Manhole type JRC7 or JB30 may be deployed beyond the Common Manhole point.

Size(mm)
Manhole
No Type Length Width Depth
1 JRC7 1280 975 1100
2 JB30 950 650 630

JRC7 Manhole

JB30 Manhole

2. Ducting
• Deployment of Smoothwall HDPE duct as below. The requirements is not only limited to
these particular size since it is based on PR1MA Communications request during design
proposal

____________________________________________________________________________________________________
October, 2014 Page 12 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

Smoothwall Duct Layer Remark


type

32mm Feeder To be used from common manhole to


JB30 and telco room/outdoor cabinet to
the first JB30 serving the units and/or to
be used between each and every JB30

PR1MA shall advice the number of


ducting per-project basis

25mm Distribution To be used from JB30 to each units and


from JB30 to the selected street light
poles

• The type of the duct usage is based on the volume of units and will be advice further by
PR1MA Communications during the design review stage by PR1MA Communications

3. Fibre Connection Between Building (For High Rise) – Campus Backbone Cabling

• For High Rise Building development that has more than 1 tower block, the fibre cabling
from main telco room needs to be connected to the telco room of each towers
(Secondary telco rooms).

• Each tower must have its own telco room (If required by PR1MA Communications during
design proposal)

4. Fibre Connection Between Phases

• In developments where there are multiple phases (whereby each phase is within
different area), each phase must have fibre connection to the other phases.
• The connection will be between the Main MDF of each phase.

• The Optical fibre cable shall be fully compliant to ITU-T G.652D specification for GPON
FTTH/O deployment.
Cabling • 1-Core SM (single mode) ITU G.652 Fibre cable extends from splitter to each housing
unit.
• Split ratios 1:2, 1:4, 1:8, 1:16, 1:32 and 1:64 may be used depending on building design
and network topology.
• Cat 5 or Cat 6 UTP cable shall connect to IP network from ONU/ONT.
• 2- core Indoor drop cable referred to the in-building cabling from FTB to FWS and shall
meet all applicable requirement stated in ANSI/ICEA S-104-696, ITU-T, IEC 60794-2
(2002-12) or JIS Standard for Optical Fibre Outside Plant Communication Cable

• To provide concealed conduit with fibre cabling for FTTH/O termination from corridor (for
MDU) and from Fiber Termination Box (FTB) (for SDU) to Fibre Wall Socket (FWS) within the
following units

____________________________________________________________________________________________________
October, 2014 Page 13 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

Conduit
within the
Item Location
house unit

1 House Units

2 Shop and Commercial Units

3 Management Office

4 Tadika and Taska

5 Control Room

6. Guard House

• Conduit shall be of uPVC type with the size of 25mm or more depending on number of cable
fill.
• M&E Consultant to recommend location of FTTH/O termination point within the house unit.
Land • To reserve a land for both High rise (MDU) and landed (SDU) development, the
telecommunication reserved land shall be titled under Perbadanan PR1MA Malaysia
Street Light
• The street light layout by the developer will be based on the requirements as per landscape
guideline
• To provide 25mm duct from the selected street light to the nearest manhole
• PR1MA will advise which street light poles that are required to be connected to the
manhole

CCTV • Monitoring of CCTV will be at the Guard House or control room depending on requirement.
Surveillance
• Storage of CCTV will be kept up to 30 days unless they are required in relation to the
System investigation of crime or for evidentiary proceedings, for which identified images and or
footage will be saved to CD or other appropriate storage medium.

____________________________________________________________________________________________________
October, 2014 Page 14 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

5.2 GUIDELINE FOR MULTI-DWELLING UNITS (MDU)

1. Must follow the General Guideline in Section 5.1.

2. Additionally, must follow the guidelines specific to MDU (please refer to the table below).

3. The network design and OSP planning requirements for MDU is illustrated below:

5.2.1 NETWORK DESIGN

____________________________________________________________________________________________________
October, 2014 Page 15 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

5.2.2 OSP PLANNING REQUIREMENTS

PODIUM A PODIUM B

TOWER A TOWER B TOWER C

ELV RISER ELV RISER ELV RISER

TELECOM RISER TELECOM RISER TELECOM RISER

TELCO TELCO
ROOM ROOM
GUARD
HOUSE

LEGEND
JRC7 MANHOLE c/w HEAVY DUTY COVER
JB30 MANHOLE c/w HEAVY DUTY COVER
FIBER PIT 600mm(L) x 600mm(W) x 750mm (D)
2 WAY 32mmØ HDPE DUCT (TYPICAL DESIGN)*
300mm CABLE TRAY

* PR1MA shall advice the number of ducting


per-project basis

Planning Requirement for High Rise Development (for illustration purposes only)

Land To allocate a reserved land for telecommunication, with minimum size 10m x
10m. The telecommunication reserved land shall be titled under Perbadanan
PR1MA Malaysia

Primary Room
Telco Room  One (1) Primary room per development area

 Room size minimum of 5mtr x 4mtr X 3mtr (W x D x H) useable


space
 The telco room is generally located in the basement or bottom
floor of a building
 Independent power meter
 Electrical DB with minimum two (2) 30 Amp isolators, and two
(2) 13 Amp power points from normal power supply
 2 x 28Watt-T5 bare channel
 2 x Ventilation/exhaust fan or/and 2 x air conditioner
 To provide fiber pit inside the telco room that connect to the
nearest manhole
 Telecommunication earth bar with resistance less than 1 ohm.
 300mm cable tray
 Below diagram illustrates proposed building plan for telco room.

____________________________________________________________________________________________________
October, 2014 Page 16 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

 To provide fiber pit with minimum size 600mm (L) x 600mm (W)
x 750mm (D)

1. Secondary Room
 One (1) Secondary room per tower if necessary; depending on the
density of the house units
 Room size minimum of 3mtr x 3mtr X 3mtr (W x D x H) useable space
 Independent power meter
 Electrical DB with minimum two (2) 30 Amp isolators, and two (2) 13
Amp power points from normal power supply
 2 x 28Watt-T5 bare channel
 2 x Ventilation/exhaust fan
 Telecommunication earth bar with resistance less than 1 ohm.
 300mm cable tray
 Next page illustrates proposed building plan for secondary telco
room.

____________________________________________________________________________________________________
October, 2014 Page 17 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

____________________________________________________________________________________________________
October, 2014 Page 18 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

1. Vertical Trunking
Cable
1. Cable tray runs long the riser; from MDF to the rooftop
Tray/Conduit 2. Minimum size for telecommunication riser shall be 1,000mm (W) x 600mm
for Building (D)
and Within 3. Entrance clearance of the riser with a minimum of 800mm opening
House Unit
2. Horizontal Trunking
i. Concealed cable tray/conduit from Floor Riser room to Corridor of each
floor

Sizes for cable trays :


> 100mm (W) x 100mm (H) to 600mm(W) x 100mm (H) depending on
number of cables and load.

• To provide at least one (1) dedicated concealed conduit for fibre cabling for
FTTH/O termination from corridor to Fibre Wall Socket (FWS) within the
house unit.

• Conduit shall be of uPVC type with the size of 25mm or more depending on
number of cable fill.

Terminations 1. Minimum one unit of FWS must be provided by the developer in all
premises. However the number of FWS can be more depend on the number
of potential customer in each unit of premise. The FWS must be type
approved by SIRIM

2. The Fibre Wall Socket (FWS)/ Faceplate provided must come with Standard
Connector (SC) output for connection to Customer Premises Equipment
(CPE) patch cord. Recommended size as per below:

____________________________________________________________________________________________________
October, 2014 Page 19 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

i. H86mm×W86mm×D19mm

3. The FWS must be placed at 300mm above the floor level and 300mm from
the corner of the wall or from electrical points and within living area.

4. The FWS is highly recommended to be placed adjacent to the electrical


power socket for FTTP CPE to function. Minimum two (2) of power units
installed adjacent to FWS

5. To provide Indoor drop cable from FWS up to FTB location in telco riser of
each floor with a buffer of 1m at FWS and 3m at telco riser of each floor and
place marking to indicate the floor and unit

6. PR1MA will advise on the exact type of drop cable during the design review.
Typically, it will be 1 x 4- core indoor drop cable

____________________________________________________________________________________________________
October, 2014 Page 20 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

5.3 GUIDELINE FOR SINGLE-DWELLING UNITS (SDU)

1. Must follow the General Guideline in Section 5.1.

2. Additionally, must follow the guidelines specific to SDU (please refer to the table below).

3. Telecommunication infrastructure shall be designed based on underground system, unless


mentioned otherwise

4. The network design and OSP planning requirements for SDU is illustrated below:

5.3.1 NETWORK DESIGN

____________________________________________________________________________________________________
October, 2014 Page 21 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

5.3.2 OSP PLANNING REQUIREMENTS

OPEN
SPACE

LEGEND
JRC7 MANHOLE c/w HEAVY DUTY COVER
JB30 MANHOLE c/w HEAVY DUTY COVER
JB30 MANHOLE c/w LIGHT DUTY
FIBER PIT 600mm(L) x 600(W) x 750mm(D) GUARD
HOUSE
JUNCTION BOX
1 WAY 25mmØ HDPE DUCT
2 WAY 32mmØ HDPE DUCT (TYPICAL DESIGN)*
STREET LIGHT
FIBER DISTRIBUTION CABINET

* PR1MA shall advice the number of ducting


per-project basis

Planning Requirement for High Rise Development (for illustration purposes only)

Land To allocate a reserved land for telecommunication, with minimum size 10m x
10m. The telecommunication reserved land shall be titled under Perbadanan
PR1MA Malaysia
• Room size minimum of 3m x 2m X 3m (W x D x H)
Telco Room • Independent power meter
• Electrical DB with minimum two (2) 30 Amp isolators, and two (2) 13
Amp power points from normal power supply
• 2 x 28Watt-T5 bare channel
• 2 x Ventilation/exhaust fan
• To provide fiber pit inside the telco room that connect to the nearest
manhole
• Telecommunication earth bar with resistance less than 1 ohm.
• 300mm cable tray
• One (1) equipment room per development area
• To provide fiber pit with minimum size 600mm (L) x 600mm (W) x
750mm (D)

____________________________________________________________________________________________________
October, 2014 Page 22 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

Plinth 1. To provide a plinth for FDC (Outdoor cabinet)

2. Location and size of the plinth is to be advised by PR1MA during design


review

____________________________________________________________________________________________________
October, 2014 Page 23 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

3. Location of the plinth to be advised by PR1MA Communications

4. To provide the telecommunication ducting from the plinth to the nearest


manhole. PR1MA Communications will advise on the manhole location
during telecommunication infrastructure design proposal

5. To provide the power ducting from the plinth to the nearest power feeder
pillar

6. To provide earth chamber for the plinth

7. The images below are one of the plinth specification

____________________________________________________________________________________________________
October, 2014 Page 24 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

1. From Outside of the House Unit


Conduit for
To provide at least 1 concealed cable conduit from back box (FTB location) to
Building and junction box
Within House
Unit
2. Within the House Unit
To provide concealed cable conduit inclusive with indoor drop cable from Fibre
Termination Box (FTB) located at the outside wall to Fibre Wall Socket (FWS)
located inside the premise.
 Conduit shall be of uPVC type with the size of 25mm or more depending on
number of cable fill

____________________________________________________________________________________________________
October, 2014 Page 25 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

• The location of FTB must be at the back of house units (for development that
have back lane access road) and must be 1500mm above the floor level.
Terminations 1. Minimum one unit of FWS must be provided by the developer in all
premises. However the number of FWS can be more depend on the number
of potential customer in each unit of premise. The FWS must be type
approved by SIRIM.

2. The Fibre Wall Socket (FWS)/ Faceplate provided must come with Standard
Connector (SC) output for connection to Customer Premises Equipment
(CPE) patch cord. Recommended size as per below:

a) H86mm×W86mm×D19mm

3. The FWS must be placed at 300mm above the floor level and 300mm from
the corner of the wall or from electrical points and within living area

4. Location of the FWS:


a) Single (1) storey house: at ground floor
b) Double (2) storey house: at ground floor
c) Three (3) storey house: at first floor
Townhouse: at the lower floor of every unit
7. The FWS is highly recommended to be placed adjacent to the electrical
power socket for FTTP CPE to function. Minimum of two (2) units of power
point installed adjacent to FWS.

8. To provide end caps for each conduits

9. To provide back box (75mm(h) x 75mm(l) x 75mm(d)) at the location of FTB

10. To provide Indoor drop cable from FWS up to FTB location with a buffer of
1m at FWS and 1.5m at FTB point

11. PR1MA will advise on the exact type of drop cable during the design review.
Typically, it will be 2- core indoor drop cable

____________________________________________________________________________________________________
October, 2014 Page 26 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

5.4 GUIDELINE FOR CCTV

Monitoring For both high rise and landed development, monitoring center will be
centre centralized at one of the following locations, subject to actual requirement and
Facility Management decision

To provide CCR room with required facilities :-


• Work station and furniture
• Power points (to de defined during design)
• Fire extinguisher

CCTV camera The CCTV cameras will be at the following locations:


Locations

Actual locations will be finalised together with the Facility Management team.
Next page illustrates CCTV installation for guardhouse.

____________________________________________________________________________________________________
October, 2014 Page 27 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

• To provide and install dedicated concealed cable conduit for CCTV


cameras (not sharing with FTTH/O cable conduit).
Conduit for
Internal building • Conduit shall be of uPVC type with the size of 25mm or more depending
on number of cable fill.
• To provide CAT6 from the CCTV point to the location of CCTV switch
which will be advised by PR1MA during design review
• To provide AC power source at CCTV switch location for CCTV cameras
that distance are more than 100 meters from CCTV switch.
• For outdoor CCTV cameras: To provide and install concealed cable
conduit from CCTV camera points to the nearest junction box or
manhole.
• For indoor CCTV cameras: To provide and install cable conduit from
CCTV camera points to the nearest cable trunking.

5.5 SMATV GUIDELINES ( ONLY APPLIES FOR HIGH RISE)

Rooftop  To allocate space and power supply at the rooftop to install the
central Satellite Dish System and Terrestrial Antenna

 To provide a plinth to sustain approximately 15kg weight (based on


1.2m satellite dish radius) with size of 600mm(W) x 600mm(L) x
150mm(H) for the Satellite Dish System and Terrestrial Antenna
which will be further advised by PR1MA during design review

Fiber Optic horizontal trunking for building


 To utilize the FTTH cable trunking from floor riser room to
corridor of each floor

____________________________________________________________________________________________________
October, 2014 Page 28 of 29
PR1MA DEVELOPMENT ICT INFRA DESIGN GUIDELINES FOR DEVELOPERS

Fiber Optic vertical tray for building

 To utilize the FTTH cable tray runs along the riser, from
Telecommunication Room to the rooftop.

Fiber Optic Cable conduit for house units


 To utilize the FTTH dedicated concealed conduit for fibre cabling
for SMATV termination from Fibre Wall Socket (FWS) within the
house units to trunking at corridor

Fiber Wall Socket (FWS)


 To utilize the FTTH FWS location in all premises

6 CCC SUBMISSION PROCEDURE

The developer/contractor is responsible for obtaining the Certificate of Completion and


Compliance (CCC)

1. The developer/main contractor must engage PR1MA Communications to design and/or review,
and implement the telecommunications network infrastructure.

2. In the event the developer has already designed the telecommunication infrastructure, the M&E
Consultant must submit 3 hardcopy and 1 softcopy of the proposed telecommunications
infrastructure plans to be reviewed and approved by PR1MA Comm.

3 Hardcopy covers

1. To be endorsed by PR1MA Communications to be returned back to M&E consultant


2. For PR1MA Communications record and inventory purpose
3. To be shared with the PR1MA PMD

3. A copy of the approved ‘Surat Sokongan’ letter from PR1MA is to be submitted to MCMC for all
Fibre optic and related broadband services.

____________________________________________________________________________________________________
October, 2014 Page 29 of 29

You might also like