BNK.
Attn.: ATN.
APL.
APPRAISED BY: APD.
DOCUMENTS: COPIES OF N.I.C., APPROVED SITE PLAN & BOQ’s
(PROVIDED BY THE BANK).
______________________________________________________________________________
Dear Sir,
We enclose the schedule of costs duly filled in and signed by the applicant, Apl& M/s. Design
Consortium, Architects, Engineers & Planners, Lahore. We have scrutinized and found it in order
and signed the same / We have scrutinized the same. Where necessary changes have been
made. The same is also appended. Our observations on the same are given below:-.
We have not checked legal status or any other legal aspect of the valuated property or the
documents. Our scope is limited to assessment of market value of property as identified to us.
____________________________________________ ____________________________________________
For & on behalf of For & on behalf of
for HARVESTER SERVICES (PVT) LTD. for HARVESTER SERVICES (PVT) LTD.
MUHAMMAD HASEEB APD.
MANAGER. EVALUATION. (VALUATOR).
(P.E.C. NO. 31467 / CIVIL). PBA NO. (PBA-PV-0108-BF).
INVOICE # HSPL-MCB-38. JAN 02, 2020.
MESSRS. BNK.
ATTENTION. ATN.
----------------------------------------------------------------------------------------------------------------------------- ---
_____________________________________________________________________________________
CLIENT : APL.
APD
PARTICULARS:
PROFESSIONAL FEE:
BOQ / Land & Building Inspection, Inquiries & Measurement to Rs. 3,000/-
assess the Current Value.
STAGE 2: RCC slab GF, brick masonry FF & RCC slab FF plaster, door
frames, water supply, electrical conducting, boundary wall.
STAGE 1.
Item # Description & Specification Quantity Unit Rate Total Cost Work Done Remaining
STAGE 2.
Item # Description & Specification Quantity Unit Rate Total Cost Work Done Remaining
1 Frames (chowkats) for doors and 88.87 m 950 84428.3 Nil All
windows
2 Brick work F.Floor 90 m3 7660 689400.0 Nil All
3
3 RCC slab GL 25 m 5920 148000.0 Nil All
3
4 RCC slab FF 22 m 5920 130240.0 Nil All
3
5 Brick work on GL 101.8 m 7665 780297.0 Nil All
6 Plaster all work including GL,FF 1070 m2 290 310300.32 Nil All
&mumty walls etc
7 Water supply; all PVC pipes 1540 m 45 68130.0 Nil All
8 Electrical work; wiring rings, plugs 55 each 1005 55275.0 Nil All
etc
9 Electrical work; single core cable 592 m 38 22496.0 Nil All
3
10 Earth filling 133.012 m 211 28065.6 Nil All
Total: 2289213
STAGE 3.
Item # Description & Specification Quantity Unit Rate Total Cost Work Done Remaining
STAGE 4.
Item # Description & Specification Quantity Unit Rate Total Cost Work Done Remaining
_____________________________
_____________________________
SIGNATURE OF APPLICANT
____________________________________________ ____________________________________________
For & on behalf of For & on behalf of
for HARVESTER SERVICES (PVT) LTD. for HARVESTER SERVICES (PVT) LTD.
MUHAMMAD HASEEB APD.
MANAGER. EVALUATION. (VALUATOR).
(P.E.C. NO. 31467 / CIVIL). PBA NO. (PBA-PV-0108-BF).