Professional Documents
Culture Documents
SECTION 16740 Communication and Data Processing Equipment Rev 0
SECTION 16740 Communication and Data Processing Equipment Rev 0
SECTION 16740 Communication and Data Processing Equipment Rev 0
~\
ww~1 ~~ .J w'i~'il wl~ :i;';'~I w~I,yJ1
SECTION 16740:
KINGDOM
OFSAUDIARABIA
~~~I 4i,j-!J1d.61ooJl
Royal Commissionfor Jubail & Yanbu tf.4 ~ ~144fJ1
SECTION 16740
COMMUNICATION AND DATA PROCESSING EQUIPMENT
TABLE OF CONTENTS
PART 1 GENERAL............................................................................................................ 1
1.04 REFERENCES..................................................................................................... 2
1.06 SUBMITTALS....................................................................................................... 3
3.02 INSTALLATION.................................................................................................. 12
PART 1 GENERAL
A. Wires, cables, connecting devices, installation and testing for wiring systems to be
used as signal pathways for voice and high-speed data transmission.
1.04 REFERENCES
A. The referred codes and standards are intended to provide an acceptable level of
quality for materials and products. In case of conflict between these standards and
the text of this Specification, the Specification text shall govern.
B. The latest revision of the referred codes and standards shall be used wherever
applicable. In case of conflict, the Contractor shall propose equipment conforming to
one group of codes and standards.
1.05 DEFINITION
C. local area network (LAN): A network used for bit serial communication of
information between interconnected, independent devices and is completely under
F. twisted pair cable (TP): A type of communication transmission cable in which two
individually insulated wires are twisted around each other to reduce induction (thus
interference) from one wire to other. The pair may be surrounded by a shield,
insulating jacket, to form Shielded Twisted Pair (STP) cable other wise it is
Unshielded Twisted Pair (UTP).
1.06 SUBMITTALS
A. The Contractor shall submit to the Royal Commission, under the provisions of
SECTION 01330, the following items for review and approval before commencing
work:
B. After installation and commissioning of the equipment, the Contractor shall submit
the following:
2. All test results and commissioning reports to show all tests specified have
been performed and all requirements have been met.
A. The Contractor shall be responsible for the quality of work and shall develop and
propose programs and methods of construction and testing such as to achieve the
specified quality to the approval of the Royal Commission in accordance with
SECTION 01450.
3. Contractor
B. In the absence of any of the above, best accepted industry practice shall be
employed throughout.
A. All the equipment/materials installed indoor shall be suitable for continuous operation
under the following service conditions:
a) A maximum of 40°C.
b) A minimum of 0°C.
a) A maximum of 50°C.
b) A minimum of 0°C.
A. All the equipment/material shall be tested at factory. The Contractor shall notify the
Royal Commission in writing not less than 30 days prior to the scheduled starting
date of the factory tests.
B. The Royal Commission reserves the right of deputing their representative for
witnessing the factory test.
C. Upon completion of factory test, and before shipment of the equipment/material, the
Contractor shall submit 5 certified copies of test reports not later than 10 days after
the completion of all factory tests for review/approval of the Royal Commission.
1.11 COORDINATION
A. The Contractor shall be held responsible for the proper coordination of all phases of
the work under this Contract.
B. It shall be the responsibility of the Contractor to coordinate the work and equipment
as specified herein with work to be performed and equipment to be furnished under
other Sections of the specifications in order to assure a complete and satisfactory
installation.
A. The Contractor shall deliver, handle and store equipment and materials in
accordance with SECTIONS 01650 and 01660, as well as the following
requirements:
4. R
PART 2 PRODUCTS
2.01 GENERAL
A. All goods and products covered by these Specifications shall be procured, when
available, from an in-Kingdom manufacturer. Procurement of all goods and products
manufactured out-of-Kingdom shall be approved by the Royal Commission.
B. All materials for subterranean use shall suffer no deterioration from corrosive
elements found in the ground. Those materials used above ground shall suffer no
deterioration from constant exposure to direct sunlight.
C. All basic LANs hardware specification shall comply with SECTION 16715.
A. The Contractor shall coordinate the features of materials and equipment so that they
form an integrated system.
C. Unless otherwise indicated, provide spare fibers and conductor pairs in cables;
positions in patch panels, cross-connects and terminal strips and space in backbone
cable trays and wire-way to accommodate 20% future increase in active work-
stations.
D. The technical characteristics of a LAN such as network topology, access method and
data transmission rate shall comply with IEC 60847 and SECTION 16715.
B. There shall also be a similar means to disconnect the power to all dedicated Heating
Ventilating Air-Conditioning (HVAC) systems serving the room and cause all required
fire/smoke dampers to close. The control for these disconnecting means shall be
grouped and identified and shall be readily accessible at the principal exit doors.
D. A separate HVAC system that is dedicated for information technology equipment use
and is separated from other areas occupancy shall be provided. Any HVAC system
that serves other occupancies shall be permitted to also serve the ITER if fire/smoke
dampers are provided at the point of penetration of the room boundary. Such
dampers shall operate on activation of smoke detectors and also by operation of the
disconnecting means.
E. The room shall be separated from other occupancies by fire rated walls, floors and
ceilings with protected openings.
2. Cord set assembly. Where run on the surface of the floor, they shall be
protected against physical damage.
K. Grounding of cables shall be in accordance with SECTION 16060 and NEC 645.15.
2.04 MATERIALS
C. Distribution Racks
3. UTP Category 6 cable shall have the features presented in Table 2A.
TABLE 2A: DATA CABLE FEATURES (CATEGORY 6)
Conductor 23 AWG, Bare Copper Wire
Insulator Material Polyolefin
Sheath Material LSZH (Low Smoke Zero Halogen)
Outside Diameter of Conductor 0.575 mm
Outside Diameter of Insulation 1.00 mm
Outside Diameter of Sheath 5.90 mm
Number of Twisted Pairs 4 twisted pairs
Pairs Color blue/white-blue, orange/white-orange,
green/white-green, brown/white-brown
4. UTP Category 6 cable shall have the mechanical and electrical properties
presented in Tables 2B and 2C.
TABLE 2B: ENVIROMENTAL AND MECHANICAL PROPERTIES OF CATEGORY 6
CABLE
6. Cross-Connect Panel
b) The number of terminals per field shall be one for each conductor in the
assigned cables.
7. Patch Panel
b) The number of jacks per field shall be one for each four-pair UTP cable.
E. Application of Media
a) UTP cable complying with Category 6 of TIA /EIA 568-B shall be used.
Fiber optic cable shall be used for runs between equipment rooms and
wiring closets and for runs between wiring closets.
PART 3 EXECUTION
3.01 GENERAL
A. The Contractor shall be the responsible for coordinating the installation and activation
of the communication and data processing equipment, as well as obtaining any
required permits.
B. All equipment used to transport and place the cable shall be subject to the Royal
Commission approval.
D. All work shall be done in a workmanlike manner by competent personnel under the
supervision of personnel who have prior experience in the placing of wires and
cables including fiber optic cables.
E. A set of Working Drawings shall also be at the site at all times during the works. All
work shall be subject to acceptance by the Royal Commission.
F. Deviations from the Contract Drawings and specifications shall not be permitted,
except upon prior written permission of the Royal Commission.
G. Installation of Conductor Cables shall comply with SECTIONS 16710 and 16726.
3.02 INSTALLATION
1. Install wires in raceway and cable trays except within consoles, cabinets,
desks, and counters, and except in accessible ceiling spaces and in gypsum
board partitions where cable wiring method may be used.
2. Install cables using techniques, practices and methods that are consistent
with Category 6 rating of components.
4. Avoid damaging of conductors, shield and jacket while installing cables and
ensure that cables are not bent during handling or installing to smaller radii
than minimums recommended by the manufacturer.
8. Secure and support cable at intervals not exceeding 762 mm (30 in.) and not
more than 152 mm (6 in.) from cabinets, boxes, fittings, outlets, racks,
frames, and terminals.
9. Make splices, taps, and terminations only at indicated outlets, terminals, and
cross-connect and patch panels. Use splice and tap connectors compatible
with media types.
10. Separation of wires shall comply with EIA/TIA-569 rules or NEC 800.52 for
separating unshielded copper communication and data-processing
equipment cables from potential EMI sources, including electrical power lines
and equipment.
A. General
1. The Contractor shall carry out all site tests in accordance with approved test
procedures to ensure that the equipment and related accessories comply
with specifications and operational requirements. All tests are subject to
witnessing by the Royal Commission’s representative.
2. At least 4 weeks prior to schedule tests, the Contractor shall submit to the
Royal Commission an outline of the plan and procedures to be used in
performing the site inspection and site tests. This shall include a brief
description of the test equipment, reference drawings, proposed tests and
procedure, test sheets, calculations, reference drawings and
minimum/maximum test and performance values in conformance with the
specification and acceptability of the equipment and acceptability of the
installation.
5. Care shall be taken that the test apparatus does not damage the equipment
or other related accessories during the testing.
END OF SECTION