MEP Work Status
MEP Work Status
Work Weightage
SL Work Package
(%)
Average Work Done 90.75% P1 Plumbing System 7%
9.25% P2 Fire Protection and Detection System 5.00%
Average Balance Work
P3 Heat Ventilation And Air Condition 9.00%
P4 Electrical System 8.00%
P5 Pool, Spa, Salon and Gym 5.00%
P6 Lift/ Elevator 20.00%
P7 Kitchen & Laundry 8.00%
P8 Building Management System 22.00%
P1. PLUMBING SYSTEM
SL Vendors Work Package Activities Breakdown (%) Work done (%)
CPVC Piping for Hot & Cold water supply 35.00% 32.00%
TC of Heat Pump and Heat Exchanger, Water Pneumatic
5.00% 3.00%
System
Plumbing system Installation of Drainage Pipe 35.00% 34.00%
1 M/s Sigma in/c STP and Installation of concealed part of sanitary/ CP fixtures 5.00% 2.50%
Sanitary Fixture Preparation of Manholes/ GT/ Inspection Pits 5.00% 3.00%
TC of STP softener Not yet install 2.00% 0.00%
Submission of Commissioning report/ O&M Manual and HO
3.00% 0.00%
Docs
SIT&C of WTP 9.00% 9.00%
M/s Ion
2 WTP Submission of Commissioning report/ O&M Manual, Water
Exchange 1.00% 0.00%
test report and HO Docs
Total 100.00% 83.50%
P2. FIRE PROTECTION AND DETECTION SYSTEM
Breakdown
SL Vendors Work Package Activities Work done (%)
(%)
Conduiting and Cabling for FAS (FACP and FARP) 25.00% 22.00%
Wiring for CM as per FLS requirements 5.00% 4.50%
Installation of devices 5.00% 4.50%
Programming &TC of FACP/FARP as per the C & E Matrix
5.00% 3.00%
Fire Protection, Piping for sprinklers & Hydrant network 35.00% 30.00%
1 M/s ICEL
Detection & PA System Installation of Sprinkler, Zone control valve, Fire Hose Reel
Cabinet, activation of zones 10.00% 8.00%
Total
100.00% 86.02%
REINSTALLING PRESSURIZATION FAN & TOILET EXHAUST DUCT FROM ROOFTOP FLOOR M1 TO M2 (HELIPAD AREA).
NEWLY DONE INSULATION WORK IN CHILLED WATER LINE OF MEP ROOM IN DIFFERENT LOCATION
Corridor Exhaust
Access
L-26, MALE JACUZZI FIRE LINE RECTIFICATION WORK
Previous Fire
Line
Newly Installed
Exhaust Ducting
& Fan
NEWLY INSTALLED CHILLER PLANT ROOM FRESH AIR SYSTEM
Newly
Installed Fresh
Air Ducting &
Fan
BASEMENT 1, 2, & 3 EXHAUST AIR SYSTEM DUCTING
BASEMENT 1,2 & 3 FRESH AIR SYSTEM DUCTING
COMMERCIAL SUB STATION FRESH AIR & EXHAUST AIR SYSTEM
HOTEL SUB-STATION ROOM A/C INSTALLATION WORK & READY FOR TAKE OVER
L-12 UPS ROOM FCU INSTALLATION
L-11, BLAST CHILLER INSTALLATION FOR BANQUET KITCHEN
CHILLER PLANT WALL MADE IN FRONT OF LOUVER
DUCT RECTIFICATION WORK BESIDE CHILLER PLANT FOR PDR NOISE REDUCTION
SERVICE LIFT LOBBY FRESH AIR DUCTING & DIFFUSER INSTALLATION
Newly Installed
Diffuser For
Fresh Air
MASIONARY SHAFT CIVIL WORK DONE
Masionary
Shaft Wall
Newly Done
WATER FLOW METER INSTALLED IN DIFFERENT LOCATION
DIESEL GENERATOR SILENCER JACKETING WORK
Jacketing Work
NEWLY INSTALLED FRESH AIR SYSTEM IN DIESEL GENERATOR ROOM OF HOTEL
BASEMENT-01, DESCO METERING PANEL INSTALLED
RMU (RING MAIN UNIT) INSTALLATION DONE
SOLAR POWER PANEL INSTALLATION WORK DONE
ASSOCIATE ENTRY ALL HVAC, PLUMBING, FIRE & ELECTRICAL WORK DONE
PILLAR HYDRANT INSTALLATION IN L-01 (OUTSIDE), FOR FIRE BRIGADE OPERATION
Pillar Hydrant
L-10, TRAY INSTALLATION UNDER FCU TO PROTECT CONTROLLER IN OFFICE LIFT M/C ROOM
Tray Installation
L-10, AHU DUCT INSIDE WORK TO REDUCE NOISE
LAUNDRY PLANT ROOM WATER SUPPLY LINE RECTIFICATION WORK
PROTECTION COVER BOX WORK FOR GAS SUPPLY METER & VALVE IN ALL REQUIRED AREA
Fencing for
protection of gas
valve
L-08, WATER DISTRIBUTION PLANT IS READY FOR TAKE OVER
FIRE PUMP PLANT IS READY FOR TAKE OVER
WATER TREATMENT PLANT IS READY FOR TAKE OVER
WATER SOFTENER PLANT IS READY FOR TAKE OVER
SEWERAGE PLANT INSTALLATION WORK IS GOING ON