REVIEW OF MEP WORKS AT

HOTEL SHERATON, DHAKA


SUMMARY OF MEP WORKS AT HOTEL SHERATON, DHAKA
Balance Work
SL Work Package Work done (%)
(%)
P1 Plumbing System 93 7
P2 Fire Protection and Detection System 95 5
P3 Heat Ventilation And Air Condition 91 9
P4 Electrical System 92 8
P5 Pool, Spa, Salon and Gym 95 5
P6 Lift/ Elevator 80 20
P7 Kitchen & Laundry 92 8
P8 Building Management System 78 22

Work Weightage
SL Work Package
(%)
Average Work Done 90.75% P1 Plumbing System 7%
9.25% P2 Fire Protection and Detection System 5.00%
Average Balance Work
P3 Heat Ventilation And Air Condition 9.00%
P4 Electrical System 8.00%
P5 Pool, Spa, Salon and Gym 5.00%
P6 Lift/ Elevator 20.00%
P7 Kitchen & Laundry 8.00%
P8 Building Management System 22.00%
P1. PLUMBING SYSTEM
SL Vendors Work Package Activities Breakdown (%) Work done (%)
CPVC Piping for Hot & Cold water supply 35.00% 32.00%
TC of Heat Pump and Heat Exchanger, Water Pneumatic
5.00% 3.00%
System
Plumbing system Installation of Drainage Pipe 35.00% 34.00%
1 M/s Sigma in/c STP and Installation of concealed part of sanitary/ CP fixtures 5.00% 2.50%
Sanitary Fixture Preparation of Manholes/ GT/ Inspection Pits 5.00% 3.00%
TC of STP softener Not yet install 2.00% 0.00%
Submission of Commissioning report/ O&M Manual and HO
3.00% 0.00%
Docs
SIT&C of WTP 9.00% 9.00%
M/s Ion
2 WTP Submission of Commissioning report/ O&M Manual, Water
Exchange 1.00% 0.00%
test report and HO Docs
Total 100.00% 83.50%
P2. FIRE PROTECTION AND DETECTION SYSTEM
Breakdown
SL Vendors Work Package Activities Work done (%)
(%)
Conduiting and Cabling for FAS (FACP and FARP) 25.00% 22.00%
Wiring for CM as per FLS requirements 5.00% 4.50%
Installation of devices 5.00% 4.50%
Programming &TC of FACP/FARP as per the C & E Matrix
5.00% 3.00%

Fire Protection, Piping for sprinklers & Hydrant network 35.00% 30.00%
1 M/s ICEL
Detection & PA System Installation of Sprinkler, Zone control valve, Fire Hose Reel
Cabinet, activation of zones 10.00% 8.00%

Pressure Test and Loop Test 5.00% 5.00%


TC of Fire Pump & Control Panel 5.00% 5.00%
Submission of Commissioning report/ O&M Manual and
H/O Docs 5.00% 0.00%
Total 100.00% 82.00%
P3.1. HEAT VENTILATION AND AIR CONDITIONING SYSTEM (HOTEL)
SL Vendors Work Package Activities Breakdown (%) Work done (%)
Equipment Positioning
Guest Floor 2.00% 2.00%
Public area 1.75% 1.75%
BoH 0.75% 0.75%
Basement 0.25% 0.25%
Plant Room 0.25% 0.25%
Ducting
Guest Floor 8.50% 8.30%
Public area 8.50% 8.30%
BoH 5.50% 5.20%
Basement 1.75% 1.70%
Plant Room 1.75% 1.75%
Grille / Diffuser
Guest Floor 7.50% 7.00%
Public area 6.50% 6.20%
M/s
1 HVAC (Hotel) BoH 2.99% 2.50%
Haroon Basement 0.50% 0.30%
Plant Room 0.01% 0.01%
CWP
Guest Floor 15.00% 10.00%
BoH 15.00% 10.00%
All Plant Room 7.50% 5.50%
Electrical Starter Panel
Cabling 1.50% 1.20%
Commissioning of Equipment 2.50% 1.50%
Water Balancing 3.00% 0.00%
Air Balancing 3.00% 0.00%
Cleaning & test run of Chiller & Equipment 2.00% 0.50%
Submission of Commissioning report/ O&M
Manual and HO Docs 2.00% 0.00%

Total 100.00% 75.00%


P4.3. DIESEL GENERATOR

SL Vendors Work Package Activities Breakdown (%) Work done (%)


Installation of DG Sets 33.44% 33.44%
Piping and installation valves, Heat Exchanger Pump
5.00% 5.00%
and Cooling towers
Installation of DG Auxiliary Panels 5.00% 5.00%
Installation Exhaust Fans and Room Canopy 10.00% 9.32%
Testing of Pipe Networks 3.32% 3.32%
M/S Rahim Diesel DG Earthing and Cabling 6.68% 6.68%
3 Installation of DG Exhaust 3.30% 3.30%
Afrooz Generators
Inusulation and Jacketing 3.36% 3.30%
Installation and jacketing of Silencer Box 3.30% 3.00%
Pre test & Test run of DG 13.30% 6.95%
Submission of Commissioning report/ O&M Manual and
HO Docs 13.30% 6.71%

Total
100.00% 86.02%
REINSTALLING PRESSURIZATION FAN & TOILET EXHAUST DUCT FROM ROOFTOP FLOOR M1 TO M2 (HELIPAD AREA).
NEWLY DONE INSULATION WORK IN CHILLED WATER LINE OF MEP ROOM IN DIFFERENT LOCATION

Chilled Water Line


Insulation Work
MEP ROOM TFA FRESH AIR INTAKE NEW DUCTING WORK IN DIFFERENT FLOOR

TFA Fresh Air


Ducting Newly Done
L-08, BANQUET STORE CHILLED WATER LINE, FCU INSTALLATION & FIRE DETECTION, PROTECTION WORK
L-08, DOCTOR’S ROOM CHILLED WATER LINE, FCU INSTALLATION & FIRE DETECTION, PROTECTION WORK
DRY TYPE SPRINKLER INSTALLATION IN ALL WALK IN CHILLER & FREEZER
L-26 CORRIDOR EXHAUST NOISE LEVEL MINIMIZED IN DIFFERENT FLOOR

Corridor Exhaust
Access
L-26, MALE JACUZZI FIRE LINE RECTIFICATION WORK

Previous Fire
Line

Now Fire Line Removed Inside The Ceiling


CHILLER PLANT ROOM EXHAUST AIR DUCTING RECTIFICATION & FAN INSTALLATION

Newly Installed
Exhaust Ducting
& Fan
NEWLY INSTALLED CHILLER PLANT ROOM FRESH AIR SYSTEM

Newly
Installed Fresh
Air Ducting &
Fan
BASEMENT 1, 2, & 3 EXHAUST AIR SYSTEM DUCTING
BASEMENT 1,2 & 3 FRESH AIR SYSTEM DUCTING
COMMERCIAL SUB STATION FRESH AIR & EXHAUST AIR SYSTEM
HOTEL SUB-STATION ROOM A/C INSTALLATION WORK & READY FOR TAKE OVER
L-12 UPS ROOM FCU INSTALLATION
L-11, BLAST CHILLER INSTALLATION FOR BANQUET KITCHEN
CHILLER PLANT WALL MADE IN FRONT OF LOUVER
DUCT RECTIFICATION WORK BESIDE CHILLER PLANT FOR PDR NOISE REDUCTION
SERVICE LIFT LOBBY FRESH AIR DUCTING & DIFFUSER INSTALLATION

Newly Installed
Diffuser For
Fresh Air
MASIONARY SHAFT CIVIL WORK DONE

Masionary
Shaft Wall
Newly Done
WATER FLOW METER INSTALLED IN DIFFERENT LOCATION
DIESEL GENERATOR SILENCER JACKETING WORK

Jacketing Work
NEWLY INSTALLED FRESH AIR SYSTEM IN DIESEL GENERATOR ROOM OF HOTEL
BASEMENT-01, DESCO METERING PANEL INSTALLED
RMU (RING MAIN UNIT) INSTALLATION DONE
SOLAR POWER PANEL INSTALLATION WORK DONE
ASSOCIATE ENTRY ALL HVAC, PLUMBING, FIRE & ELECTRICAL WORK DONE
PILLAR HYDRANT INSTALLATION IN L-01 (OUTSIDE), FOR FIRE BRIGADE OPERATION

Pillar Hydrant
L-10, TRAY INSTALLATION UNDER FCU TO PROTECT CONTROLLER IN OFFICE LIFT M/C ROOM

Tray Installation
L-10, AHU DUCT INSIDE WORK TO REDUCE NOISE
LAUNDRY PLANT ROOM WATER SUPPLY LINE RECTIFICATION WORK
PROTECTION COVER BOX WORK FOR GAS SUPPLY METER & VALVE IN ALL REQUIRED AREA

Fencing for
protection of gas
valve
L-08, WATER DISTRIBUTION PLANT IS READY FOR TAKE OVER
FIRE PUMP PLANT IS READY FOR TAKE OVER
WATER TREATMENT PLANT IS READY FOR TAKE OVER
WATER SOFTENER PLANT IS READY FOR TAKE OVER
SEWERAGE PLANT INSTALLATION WORK IS GOING ON
THANK YOU