ESTIMATE OF 3-STOREY HOSPITAL

STRUCTURAL ESTIMATE

AGGREGATES – CLASS AA MIXTURE

DESIGNATION DIMENSION(M) QUANTITY VOLUME


HEIGHT(M) LENGTH(M)
WIDTH LENGTH (PCS) (M³)
COLUMN 9.0 0.4 0.4 19 27.39
BEAM 397 0.35 0.45 1 62.5275
FTB 198.5 0.35 0.45 1 31.185
FOOTING 0.4 2.3 2.3 19 40.204
3RD FLOOR 0.2 18.45 12.46 1 45.9774
2ND FLOOR 0.2 18.45 12.46 1 45.9774
TOTAL 253.261

VOLUME SAND GRAVEL CEMENT


DESIGNATION
(m³) (m³) (m³) (bags)
COLUMN 27.39 13.695 27.39 328.68
BEAMS 62.5275 31.26975 62.5275 750.33
FTB 31.185 15.5925 31.185 374.22
FOOTING 40.204 20.102 40.204 482.448
RD
3 FLOOR 45.9774 22.9887 45.9774 551.7288
ND
2 FLOOR 45.9774 22.9887 45.9774 551.7288
TOTAL 253.261 126.6305 253.261 3038.1356
VOLUME

TOTAL VOLUME TOTAL COST


AGGREGATES UNIT COST
(m³) (Php)
SAND 126.6305 1200 151956.6
GRAVEL 253.261 1000 253261
CEMENT 3038.1356 260 789915.256

REINFORCEMENT
DIAMETER OF SELL BAR USED
DESIGNATION
10ΦBAR 12ΦBAR 16ΦBAR 20ΦBAR 25ΦBAR
COLUMN
BEAM
FTB
FOOTING
3RD FLOOR
2ND FLOOR