WEEKLY SUMMARY REPORT

PT GUNUNG SAMUDERA INTERNASIONAL


PERIODE : 23 MARET – 29 MARET 2020
WEEK 13

Prepared by :
SITE PT CERIA NUGRAHA INDOTAMA MINE TECHNICAL CONTROL
PIT BOUNDARY MAP

2
MINE CONDITION

3
LAND CLEARING BUKAAN BARU

4
DISPOSAL

5
CONTRUCTION DISPOSAL

6
CLEAN UP ORE EXPOSED

7
ORE EXPOSED

8
ORE GETTING

9
PENGAMBILAN SAMPEL

10
ORE STOCK

ORE STOCK ON PIT

11
MATERIAL MOVEMENT REPORT

OB PRODUCTION BY RETAGE
Total (Tonnage)
Day Week Date FROM PIT ( TONNAGE )
Disposal 1 Disposal 2 Week
83 13 23-Mar-20 374 - 374
84 13 24-Mar-20 - - -
85 13 25-Mar-20 - 902 902
86 13 26-Mar-20 - 1,045 1,045
87 13 27-Mar-20 - - -
88 13 28-Mar-20 - - -
89 13 29-Mar-20 - - -
Total 374 1,947 2,321

12
MONITORING MATERIAL MOVEMENT BY TRUCK FACTOR

CUMMULATIVE PLAN VS ACTUAL MATERIAL MOVEMENT BY TRUCK FACTOR


23-Mar-17 24-Mar-17 25-Mar-17 26-Mar-17 27-Mar-17 28-Mar-17 29-Mar-17
Week 13 TOTAL ACHIEVMENT
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Plan Load 202 202 202 202 202 202 202 1,413
Actual Load 34 - 82 95 - - - 211
Overburden 15%
Plan WMT 2,220 2,220 2,220 2,220 2,220 2,220 2,220 15,540
Actual WMT 374 902 1,045 2,321

13
EQUIPMENT MONITORING

CUMMULATIVE PLAN VS ACTUAL EQUIPMENT & HOURS UNIT

ACHIEVMENT B/H

ACHIEVMENT D/T

ACHIEVMENT DZ
EQUIPMENT
Week 13

B/H D/T DZ B/H D/T DZ B/H D/T DZ B/H D/T DZ B/H D/T DZ B/H D/T DZ B/H D/T DZ

23-Mar-17 24-Mar-17 25-Mar-17 26-Mar-17 27-Mar-17 28-Mar-17 29-Mar-17

Plan Unit 14 9 1 14 9 1 14 9 1 14 9 1 14 9 1 14 9 1 14 9 1
41.84% 19.05% 0.00%
Actual Unit 5 2 0 5 0 0 6 2 0 6 3 0 6 0 0 6 0 0 7 5 0

Plan Hour 210 135 15 210 135 15 210 135 15 210 135 15 210 135 15 210 135 15 210 135 15
22.31% 10.16% 0.00%
Actual Hour 40 16 0 40 0 0 48 16 0 48 24 0 48 0 0 48 0 0 56 40 0

14
EQUIPMENT MONITORING GRAFIK

15
PEMAKAIAN HM

NAMA KODE TTL Total Unit


NO UNIT
DRIVER UNIT HM 23 24 25 26 27 28 29 Bekerja

1 DARLIS PC 195 EX 201 61.4 9 9.2 9.4 9.8 8.3 8 7.7


7

2 AMRAN PC 195 EX 213 57.0 8 9 9 9 8 7 7


7

3 RASYID PC 195 EX 214 58.0 7 9 8 10 9 7 8 7

4 HENDRA PC 210 EX 219 20.5 9 8.1 0 0 3.4 0 0


3
5 SUKMO PC 210 EX 231 52.7 8 5.3 8.9 8.6 8.6 6.6 6.7
7
6 RIFAL PC 300 EX 302 48.0 7 0 9 9 9 7 7
6

TOTAL 291.2

16
PERBANDINGAN HM/FUEL

PERIODE MARET 2020


Jumlah HM Pemakaian Total
No Nama C/N Jenis Unit TOTAL HM RASIO AVG HM
SIANG MALAM BBM / Liter Operating Day

1 DARLIS EX 201 PC 200 61.4 0 61.4 1221 19.89 Ltr/HM 7 8.77


2 AMRAN EX 213 PC 195 57 0 57 1035 18.16 Ltr/HM 7 8.14
3 RASYID EX 214 PC 195 58 0 58 1007 17.36 Ltr/HM 7 8.29
4 HENDRA EX 219 PC 210 20.5 0 20.5 466 22.73 Ltr/HM 3 6.83
5 SUKMO EX 231 PC 210 52.7 0 52.7 955 18.12 Ltr/HM 7 7.53
6 RIFAL EX 302 PC 300 48 0 48 1666 34.71 Ltr/HM 6 0.00

SUB TOTAL 298 JAM 6,350 LITER

17
Monitoring Material Movement by Truck Factor
ACTUAL WEATHER WEEK 13

23-Mar-20 24-Mar-20 25-Mar-20 26-Mar-20 27-Mar-20 28-Mar-20 29-Mar-20


Total per week
DESCRIPTION Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day (Minute) Night (Minute)
Rainy 0.00.00 0.00.00 0.00.00 0.00.00 0.00.00 0.00.00 0.00.00 0.00.00 0.00.00 0.00.00 3.00.00 0.00.00 1.00.00 3.20.00 240 200
Sunny 12.00.00 12.00.00 12.00.00 12.00.00 12.00.00 12.00.00 12.00.00 12.00.00 12.00.00 12.00.00 10.00.00 12.00.00 1.00.00 8.40.00 4260 4840
Total 12.00.00 12.00.00 12.00.00 12.00.00 12.00.00 12.00.00 12.00.00 12.00.00 12.00.00 12.00.00 13.00.00 12.00.00 2.00.00 12.00.00 4500 5040

18
HEALTH SAFETY ENVIRO

◼ Accident/Incident :-

No accident/incident in activity this week.

DATA KECELAKAAN :
ACCIDENT LOCATION COMPANY LAST WEEK MTD YTD
FATALITY
LTI
FIRST AID
PROPERTY DAMAGE
FIRE CASE
NEAR MISS
ENVIRONMENT

19
SAFETY TALK :
TANGGAL LOKASI JUMLAH PESERTA PEMBICARA MATERI FOTO

26.03.2020 PIT AMETHYS 13 Suryadi Sosialisasi Rambu-rambu

DOKUMENTASI SAFETY ACTIVITY:


1 2 3

P2H Excavator Inspeksi Area Pit Penyemprotan desinfektan area office

20
MANHOURS

21
SUMMARY ACTIVITY

LUASAN BUKAAN : 1.8 Ha ORE STOCK


29 MARET 2020
HAULING TOP SOIL
09 – 13 MARET 2020 ON PIT :
- VOLUME ESTIMATE : 704.37 m3
RETASE : 235 RET - TONNAGE ESTIMATE :1,127.00 MT
VOLUME ESTIMATE : 2.585 m3

HAULING OB
14 – 26 MARET 2020

RETASE : 659 RET


VOLUME ESTIMATE :
- DISPOSAL 1 : 5,302.00 m3
- DISPOSAL 2 : 1,947.00 m3

22
CONSTRAIN FOR MINING ACTIVITY

• Kurangnya support alat berat seperti tidak adanya dozer sehingga dapat menghambat
pekerjaan dari plan waktu.
• Man Hours/ jam kerja yang tidak sesuai dengan plan mengakibatkan terhambatnya
progress kegiatan.
• Equipment yang belum sesui plan mengakibatkan progress mining terhambat.

23
TERIMA KASIH