Hydrotest Procedure For Piping
Hydrotest Procedure For Piping
Hydrotest Procedure For Piping
Prepared By
Approved By
1.Purpose
2.Scope
3.Preparation
4.Storage of Water
5.Water Quality
6.Procedure
7.Safety
8.Inspection and Rectification
9.Reference documents
This Practice provides leak-testing procedures for piping designed and constructed
to ASME B31.3 Process Piping, hereinafter referred to as the Code.
2. SCOPE
Testing will be witnessed as per test marks issued by Third Party (SGS Pakistan)
3. PREPARATION:
Test shall be carried out after completion of all welding activities, Radiographic
tests, and DPT (if applicable) but before surface treatment.
It shall be insured that 100% welding has been completed and all weld seams
shall visually be inspected from inside with proper lighting arranged.
All cleats, erection attachments, remaining weld tacks near weld seam shall be
removed by proper grinding. In case of excessive grinding during removal of
attachments, that portion shall be built-up by tack welds.
All loose material and debris shall be removed.
All openings shall be blanked-off and metallic gaskets shall be used for
sealing purpose.
One vent shall be provided to remove the air pockets/ bubbles. (Filling shall be
continued till the over flow from the vent.)
Connect the water piping for supply and drain.
All nozzles will be boxed up prior to filling of water with metallic gaskets, seals,
and Teflon except vents, inlet and outlet nozzles.
Two calibrated pressure gauges shall be installed out of which one will be at
the highest point.
A temperature gauge will also be available to ensure the required water/metal
temperature.
4. STORAGE OF WATER:
Water shall be stored in Storage Tank available at Site or inside the water
bowser.
5. WATER QUALITY:
Sweet water shall be used for leak test. In case of stainless-steel vessel, the
chloride content of the water shall not be exceedingly more than 50 ppm (mg/l). The
water shall also be clear of any solid particles.
7. SAFETY:
All tools being used should be appropriate and in proper operating condition.
Only qualified and skilled personnel appointed by the QA/QC manager shall
be allowed to conduct the test.
Sign shall be displayed to indicate the pressure test is in progress and the
area shall be barricaded.
Safety relief valve to be used for releasing excess pressure.
Irrelevant persons entry to be avoided during hydro testing at site.
Proper PPE’s should be used in the hydro testing area.
Any leak shall be identified and marked on the Piping. The area shall be
documented. The piping shall be completely drained and defective welds /
joints shall be repaired.
Applicable forms and documents shall be filled which will become part of the Manufacturer’s
Data Report to be submitted to the client at the time of delivery.
9. REFERENCE DOCUMENTS