Volume = l x w x t

= 5 x 3 x 0.10

= 1.5 cu. m

For Class C concrete mixture

Cement = 1.5 x 5.49 = 8.235 => 9 bags of cement.

Sand = 1.5 x 0.44 = 0.66 m^3 of sand

Gravel = 1.5 x 0.89 = 1.335 m^3 of gravel.


Answer:
Volume = l x w x t

= 1000 x 4 x 0.15

= 600m3

For class A concrete mixture.

Cement = 600 x 7.85 = 4710 bags of cement

Sand = 600 x 0.42 = 252 m3 of sand

Gravel = 600 x 0.84 = 504 m3 of gravel


Answer:
Volume = l x w x h

= 0.30 x 0.25 x 5

= 0.375m3

Total Volume = 0.375 x 8 = 3m3

For class A concrete mixture:

Cement = 3 x 7.85 = 23.55 => 24 bags of cement

Sand = 3 x 0.42 = 1.26m3 of sand

Gravel = 3 x 0.84 = 2.52m3 of gravel


Answer:
Volume = l x w x h

Volume for Column = 0.25 x 0.20 x 4 = 0.2m3

Total volume column = 0.2 x 12 = 2.4 m3

For Class B concrete mixture

Cement = 2.4 x 6.49 = 15.576 => 16 bags

Sand = 2.4 x 0.44 = 1.056m3

Gravel = 2.4 x 0.87 = 2.088m3 of gravel


Answer:
Volume = l x w x h or t

Volume of column = 0.30 x 0.30 x 0.90 = 0.081m3

Total volume = 0.081 x 4 = 0.324m3

Volume of footing = 0.80 x 0.80 x 0.15 = 0.096 m3

Total Volume = 0.096 x 4 = 0.384m3

Total Volume = 0.324 + 0.384 = 0.708m3

For Class A concrete mixture

Cement = 0.708 x 7.85 = 5.55 => 6 bags of cement

Sand = 0.708 x 0.42 = 0.30m3 of sand

Gravel = 0.708 x 0.84 = 0.60m3 of gravel

Volume of flooring slab = 0.10 x 3 x 4 = 1.2 m3

For Class C cement mixture

Cement = 1.2 x 5.49 = 6.588 => 7 bags of cement


Sand = 1.2 x 0.44 = 0.528 m3 of sand : Gravel = 1.2 x 0.89 = 1.068 m3 of gravel

Answer:
Volume = l x w x h or t

0.60 x 0.40 x 5 = 1.2m3

Total volume = 1.2 x 8 = 9.6 m3

For Class A concrete mixture

Cement = 9.6m3 x 7.85 = 75.36 => 76 bags of cement

Sand = 9.6 x 0.42 = 4.032 m3 of sand

Gravel = 9.6 x 0.84 = 8.064 m3 of gravel


Answer:
Volume of a circular column = A x h where A is (pi)r^2

= pi(0.3)^2 x 6 = 1.70 m3

Total Volume = 1.70m3 x 5 = 8.5m3

For Class A concrete mixture =

Cement = 8.5 x 7.85 = 66.725 => 67 bags of cement

Sand = 8.5 x 0.42 = 3.57m3 of sand

Gravel = 8.5 x 0.84 = 7.14m3 of gravel