TGP SULFUR HANDLING FACILITIES

PACKAGE 14

Nesma & Partners Cont. Co. Ltd


Contract No- 10044546
INSPECTION TWO WEEKS LOOK AHEAD SCHEDULE (Jan-31 TO Feb-13, 2021)

Inspection Responsibility
Assignments
S/N Activity/Description Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Remarks
NESMA SA
31-Jan 1-Feb 2-Feb 3-Feb 4-Feb 5-Feb 6-Feb 7-Feb 8-Feb 9-Feb 10-Feb 11-Feb 12-Feb 13-Feb
Package # 14

I PIPE SLEEPERS (ZONE-1, SLEEPER CORRIDOR) WEEK NO. 06 WEEK NO. 07

A Soil Sampling, Testing and Review of Test Reports H H

B Visual Inspection for Site Prep.& Excav (-) (-)

C Fill Placement & Compaction I S

D Compaction Testing I W

E Grade & Site Preparation I W

F Formwork Inspection for Blinding H H

G Concrete Placement & Sampling for Blinding I W

Installation of Uncoated Steel Rebars, Embedded


H Items and Form Closure Inspection H H

Formwork Instl'n (Sleeper Foundation Footing Base,


I Sleeper Foundation Pedestal) H H

Concrete Placement & Sampling (Sleeper


J Foundation Footing Base, Sleeper Foundation I W
Pedestal)

K Concrete Coating pre-installation Inspection H H

Inspection & Installation of embedded Items (incl


L Rebars receiving inspection)
TGP SULFUR HANDLING FACILITIES
PACKAGE 14

Nesma & Partners Cont. Co. Ltd


Contract No- 10044546
INSPECTION TWO WEEKS LOOK AHEAD SCHEDULE (Jan-31 TO Feb-13, 2021)

Inspection Responsibility
Assignments
S/N Activity/Description Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Remarks
NESMA SA
31-Jan 1-Feb 2-Feb 3-Feb 4-Feb 5-Feb 6-Feb 7-Feb 8-Feb 9-Feb 10-Feb 11-Feb 12-Feb 13-Feb
Package # 14

II PIPE SUPPORT AREA

A Soil Sampling, Testing and Review of Test Reports H H

B Visual Inspection for Site Prep.& Excav (-) (-)

C Fill Placement & Compaction I S

D Compaction Testing I W

E Grade & Site Preparation I W

F Formwork Inspection for Blinding H H

G Concrete Placement & Sampling for Blinding I W

Installation of Uncoated Steel Rebars, Embedded


H Items and Form Closure Inspection H H

Formwork Instl'n (Pipe Support Foundation Footing


I Base, Pipe support Pedestal) H H

Concrete Placement & Sampling (Pipe Support


J Foundation Footing Base, Pipe support Pedestal) I W

k Concrete repair application & Inspection

l Concrete Coating pre-installation Inspection H H


TGP SULFUR HANDLING FACILITIES
PACKAGE 14

Nesma & Partners Cont. Co. Ltd


Contract No- 10044546
INSPECTION TWO WEEKS LOOK AHEAD SCHEDULE (Jan-31 TO Feb-13, 2021)

Inspection Responsibility
Assignments
S/N Activity/Description Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Remarks
NESMA SA
31-Jan 1-Feb 2-Feb 3-Feb 4-Feb 5-Feb 6-Feb 7-Feb 8-Feb 9-Feb 10-Feb 11-Feb 12-Feb 13-Feb
Package # 14

III IRRIGATION TANK

A Visual Inspection for Site Prep.& Excav. (-) (-)

B Fill Placement & Compaction I S

C Compaction Testing & Sampling I W

D Grade & Site Preparation I W

E Formwork Inspection for Blinding H H

F Concrete Placement & Sampling for Blinding I W

Installation of Uncoated Steel Rebars, Embedded


G Items and Form Closure Inspection H H

H Formwork Instl'n (Ring wall formwork) H H

Concrete Placement & Sampling (Ring wall


I formwork) I W

J Concrete Coating pre-installation Inspection H H

k Inspection of embedded Items (Anchor Bolts)

IV Sulfur Block Area

A Visual Inspection for Site Prep.& Excav. (-) (-)

B Fill Placement & Compaction I S

C Compaction Testing I W

D Material Receiving for HDPE Membrane

Inspection Schedule
PREPARED BY: Tarek Dandachli
Lead Civil Engineer Friday