Norms for Rate Analysis

Activity Group:- 2 : Site Clearance


Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
201 Clearing and grubbing of forest
2.01
including uprooting, carrying and
disposing of vegetation, grass, bush,
sapling and trees of girth upto 300mm
(measured at a height of 1m above the
ground level). lead 10m.

2.01.01 Trees & sapling less than 15 numbers


per 100 sq.m
m2 unskilled md 0.030 Add 3% for tools

2.01.02 Trees & sapling more than 15 numbers


per 100 sq.m
m2 unskilled md 0.040 Add 3% for tools

2.02 Clearing of grass, removing roots


201
breaking sods, levelling the surface and
disposal to 10m.

m2 unskilled md 0.023 Add 3% for tools

2.03 201 Felling and uprooting of bamboo,


clearing the area, stacking of bamboo
and disposing of wastes to 10m.
(Volume of the excavated area should
be measured.)
m3 unskilled md 2.800 Add 3% for tools

2-1
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
2.04 201 Felling trees (the girth measured at a
height of 1 m above ground level)
including cuttting of trunks and
branches, removing the roots, stacking
serviceable materials and disposal of
unserviceable materials to 10m
distance and back filling the
depressions/pits

a) above 300mm to 600mm no unskilled md 0.920 Add 3% for tools

b) above 600mm to 900mm no unskilled md 3.500 Add 3% for tools

c) above 900mm to 1800mm no unskilled md 9.750 Add 3% for tools

d) above 1800mm to 2400mm no unskilled md 16.000 Add 3% for tools

e) above2400mm to 3000mm no unskilled md 40.000 Add 3% for tools

f) above 3000mm no unskilled md 78.710 Add 3% for tools

2.05 201, Dressing and levelling of the


construction surface including cutting
909
and filling of small undulation.

m2 unskilled md 0.010 Add 3% for tools

2-2
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
2.06 201, Excavation of top soil (sub grade) and In rehabilitation
carrying away from construction site
909 works
lead 10m.
Add 3% for tools
2
2.06.01 Thickness upto 100mm m unskilled md 0.080
2
2.06.02 Thickness upto 150mm m unskilled md 0.120
2
2.06.03 Thickness upto 200mm m unskilled md 0.160
2.07 201, Preparation of surface (subgrade) by In rehabilitation
filling with common soil and Add 3% for tools
2800 works
compaction.

2.07.01 Thickness upto 100mm m2 unskilled md 0.090


2
2.07.02 Thickness upto 150mm m unskilled md 0.140
2
2.07.03 Thickness upto 200mm m unskilled md 0.180
2.08 201, Spreading,Shaping and light
compacting of top soil on slopes.
2800 m2 unskilled md 0.050 Add 3% for tools

2.09 202 Dismantling Bridge, culvert and other


structures including stockpiling the
reusable materials and disposal of
unusable materials within 50m. lead

2.09.01 Plain cement concrete; 1:4:8 or leaner m3 skilled md 0.050 Add 3% for tools
mix .
unskilled md 1.400

2.09.02 plain cement concrete; 1:3:6 or richer m3 skilled md 0.050 Add 3% for tools
mix
unskilled md 2.300

2-3
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
2.09.03 Reinforced cement concrete work m 3
skilled md 0.050
unskilled md 3.250 Add 3% for tools
2.09.04 Cutting reinforcement in R.C.C or R.B
work. ( to be calculated on the basis of Add 15% for tools like chisels,
cross-sectional area i.e length x Hackshaw or gas cutters,gas
2
thickness) m skilled md 0.100
etc.
unskilled md 1.200
2.09.05 202 Scrapping, cleaning and straightening
reinforcement from R.C.C or R.B work Add 3% for tools
t skilled md 0.400
to be calculated on the basis of wt. of
reinforcement unskilled md 6.300

2.09.06 Dismantling Bridge, culvert and other


structures including stockpiling the
reusable materials and disposal of
unusable materials within 50m. lead

(a) Brick work


2.09.06.01 (i) in mud mortar m3 skilled md 0.050 Add 3% for tools
unskilled md 0.650
2.09.06.02 (ii)in lime mortar m3 skilled md 0.050 Add 3% for tools
unskilled md 0.770
3
2.09.06.03 (iii)in cement mortar m skilled md 0.100 Add 3% for tools
unskilled md 1.900
2.09.06.04 (iv)Reinforced Brick work m 3
skilled md 0.050 Add 3% for tools
unskilled md 2.900

2-4
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
2.09.07 (b) Random rubble stone masonry
2.09.07.01 (i) in dry masonry m3 skilled md 0.100 Add 3% for tools
unskilled md 0.800
3
2.09.07.02 (ii) in lime mortar m skilled md 0.100 Add 3% for tools
unskilled md 1.100
3
2.09.07.03 (iii) in cement mortar m skilled md 0.100 Add 3% for tools
unskilled md 2.250
2.09.08 202 Removing mortar from bricks and 1000
cleaning bricks and stacking.
nos
.

2.09.08.01 (i) in mud mortar skilled md 0.040 Add 3% for tools


unskilled md 3.900

2.09.08.02 (ii) in lime mortar skilled md 0.750 Add 3% for tools


unskilled md 4.100
2.09.08.03 (iii) in cement mortar skilled md 1.200 Add 3% for tools
unskilled md 4.850
2.09.09 Dismantling of dressed stone works,
ashlar face stone work, marble work
and precast concrete work.

2.09.09.01 (i) in lime mortar m3 skilled md 0.100 Add 3% for tools


unskilled md 1.400
3
2.09.09.02 (ii)in cement mortar m skilled md 0.100 Add 3% for tools
unskilled md 2.700

2-5
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
2.9 202 Removing and cleaning mortar from
stones and concrete articles and
stacking. Net quantity will be 90% of
stack measurement of cleaned
materials.

(i) in lime mortar m3 skilled md 0.180 Add 3% for tools


unskilled md 1.050
(ii)in cement mortar m3 skilled md 0.220 Add 3% for tools
unskilled md 1.150
Dismantling and stacking of wood work
in frames, trusses, purlins and rafters
upto 10 m span and 5m height.

(I) Sectional area below 40 sq.cm. m skilled md 0.010


Add 10% for pulleys, ropes,
unskilled md 0.020
ladder, sledge and hammer etc.

(ii) sectional area 40sq.cm and above m3 skilled md 1.250


Add 10% for pulleys, ropes,
unskilled md 2.600
ladder, sledge and hammer etc.

Dismantling trusses, rafters, purlins, for


every additional span of 1m or part
there-of beyond 10 m.

2.9 202 (i) sectional area below 40sq.cm m skilled md 0.0005


unskilled md 0.002

2-6
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
(ii) sectional area 40 sq.cm and m3 skilled md 0.100
above unskilled md 0.450

Dismantling steel work into individual


sections including dis-membering and
stacking.

(I) Rolled steel Joists t skilled md 0.500 Add 10% for pulleys, ropes,
gas, gas-cuttter etc.
unskilled md 3.400

(II) Channels,angles,tees and flats t skilled md 0.500 Add 10% for pulleys, ropes,
gas, gas-cuttter etc.
unskilled md 3.000

Dismantling steel work in built up


sections in angles, tees, flats and
channels including all gusset plates,
bolts, nuts, cutting rivets, weldings etc.
including dis-membering and stacking.
t skilled md 1.500
Add 5% for pulleys, ropes, gas-
unskilled md 7.000 cuttter, gas & supporting
arrangement. etc.
2.9 202 Dismantling steel work in built up
section without dismembering but with Add 5% for pulleys, ropes,
t skilled md 1.000
stacking. ladder, gas, gas-cuttter &
unskilled md 6.000
supporting arrangement etc.

2-7
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
Dismantling fencing posts, struts with
concrete surrounding including earth
work for excavation & refilling.

(I) R.C.C post/strut no unskilled md 0.450 Add 3% for tools

(ii) Iron angles or pipe post/strut no unskilled md 0.420 Add 3% for tools

Excavation of metalled road and


removal of all materials including
soling and screening sorting out
reusable materials and disposing
unusable materials upto 20m. Lead.

(a) water bound Macadam materials m3 skilled md 0.010 Add 3% for tools
including soling/sub-base.
unskilled md 0.890

(b)Bitumenous materials m3 skilled md 0.010 Add 3% for tools


unskilled md 2.420

2.9 202 Dry stone pitching/rip-rap (15- sq.m skilled md 0.020 Add 3% for tools
25cm.thick)
unskilled md 0.160

Grouted stone pitching (15-25cm.thick) sq.m skilled md 0.025 Add 3% for tools
unskilled md 0.225

2-8
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
R.C.C pipes
(excluding excavation & refilling) Add 3% for ballies,ropes Excavation & refilling
I) upto 600mm dia. pulleys, Tripod etc. shall be calculated
m skilled md 0.010
seperately considering
unskilled md 0.400 the dia. of pipe, height of
ii) above 600mm dia. m skilled md 0.010 filling etc.
unskilled md 0.800

(iii)Gabion m3 skilled md 0.100 Add 3% for tools


unskilled md 1.000