2-1
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
2.04 201 Felling trees (the girth measured at a
height of 1 m above ground level)
including cuttting of trunks and
branches, removing the roots, stacking
serviceable materials and disposal of
unserviceable materials to 10m
distance and back filling the
depressions/pits
2-2
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
2.06 201, Excavation of top soil (sub grade) and In rehabilitation
carrying away from construction site
909 works
lead 10m.
Add 3% for tools
2
2.06.01 Thickness upto 100mm m unskilled md 0.080
2
2.06.02 Thickness upto 150mm m unskilled md 0.120
2
2.06.03 Thickness upto 200mm m unskilled md 0.160
2.07 201, Preparation of surface (subgrade) by In rehabilitation
filling with common soil and Add 3% for tools
2800 works
compaction.
2.09.01 Plain cement concrete; 1:4:8 or leaner m3 skilled md 0.050 Add 3% for tools
mix .
unskilled md 1.400
2.09.02 plain cement concrete; 1:3:6 or richer m3 skilled md 0.050 Add 3% for tools
mix
unskilled md 2.300
2-3
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
2.09.03 Reinforced cement concrete work m 3
skilled md 0.050
unskilled md 3.250 Add 3% for tools
2.09.04 Cutting reinforcement in R.C.C or R.B
work. ( to be calculated on the basis of Add 15% for tools like chisels,
cross-sectional area i.e length x Hackshaw or gas cutters,gas
2
thickness) m skilled md 0.100
etc.
unskilled md 1.200
2.09.05 202 Scrapping, cleaning and straightening
reinforcement from R.C.C or R.B work Add 3% for tools
t skilled md 0.400
to be calculated on the basis of wt. of
reinforcement unskilled md 6.300
2-4
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
2.09.07 (b) Random rubble stone masonry
2.09.07.01 (i) in dry masonry m3 skilled md 0.100 Add 3% for tools
unskilled md 0.800
3
2.09.07.02 (ii) in lime mortar m skilled md 0.100 Add 3% for tools
unskilled md 1.100
3
2.09.07.03 (iii) in cement mortar m skilled md 0.100 Add 3% for tools
unskilled md 2.250
2.09.08 202 Removing mortar from bricks and 1000
cleaning bricks and stacking.
nos
.
2-5
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
2.9 202 Removing and cleaning mortar from
stones and concrete articles and
stacking. Net quantity will be 90% of
stack measurement of cleaned
materials.
2-6
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
(ii) sectional area 40 sq.cm and m3 skilled md 0.100
above unskilled md 0.450
(I) Rolled steel Joists t skilled md 0.500 Add 10% for pulleys, ropes,
gas, gas-cuttter etc.
unskilled md 3.400
(II) Channels,angles,tees and flats t skilled md 0.500 Add 10% for pulleys, ropes,
gas, gas-cuttter etc.
unskilled md 3.000
2-7
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
Dismantling fencing posts, struts with
concrete surrounding including earth
work for excavation & refilling.
(ii) Iron angles or pipe post/strut no unskilled md 0.420 Add 3% for tools
(a) water bound Macadam materials m3 skilled md 0.010 Add 3% for tools
including soling/sub-base.
unskilled md 0.890
2.9 202 Dry stone pitching/rip-rap (15- sq.m skilled md 0.020 Add 3% for tools
25cm.thick)
unskilled md 0.160
Grouted stone pitching (15-25cm.thick) sq.m skilled md 0.025 Add 3% for tools
unskilled md 0.225
2-8
Norms for Rate Analysis
Activity Group:- 2 : Site Clearance
Spec. Resources
Activity Clause
Description of works Labour Materials Equipment Remarks
Nos No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
R.C.C pipes
(excluding excavation & refilling) Add 3% for ballies,ropes Excavation & refilling
I) upto 600mm dia. pulleys, Tripod etc. shall be calculated
m skilled md 0.010
seperately considering
unskilled md 0.400 the dia. of pipe, height of
ii) above 600mm dia. m skilled md 0.010 filling etc.
unskilled md 0.800