Norms for Rate Analysis

Activity Group:- 8 : Quarries, Borrow Pits, Stock Pile and Spoil Areas.
Resources
Spec.
Activity
Nos
Clause Description of works Labour Materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
8.01.01 Collection of stone, gravel including selection, screening
and stacking within 10m. Hauling distance.

3
a) Size 40mm - 70mm m Unskilled md 4.00
3
b) Size 70mm - 100mm m Unskilled md 3.20
8.01.02 Collection and seiving gravel including stacking within
10m. Hauling distance.

3
a) 5mm - 70mm m Unskilled md 2.00
b) 5mm - 40mm m3 Unskilled md 3.20
c) 5mm - 20mm m3 Unskilled md 4.70
d) 5mm - 8mm m3 Unskilled md 8.00
8.01.03 Collection of rubble of required size, hauling
distance10m. and stacking.
m3 Unskilled md 1.40
8.01.04 Collection and seiving sand within 10m. hauling
distance.
3
a) Quarry output less than 33% m Unskilled md 4.00
b) Quarry output 33 - 66% m3 Unskilled md 3.00
c) Quarry output more than 66% m3 Unskilled md 1.43
8.01.05 Collection, quarring and seiving sand in hilly areas
within 10m. hauling distance.
m3 Unskilled md 1.50
8.01.06 Common material haulage - 50% by basket and 50% by
wheel barrow for every aditional 10m haul.

m3 Unskilled md 0.12

8-1
Norms for Rate Analysis
Activity Group:- 8 : Quarries, Borrow Pits, Stock Pile and Spoil Areas.
Resources
Spec.
Activity
Nos
Clause Description of works Labour Materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
8.01.07 Rock material haulage - 50% by basket and 50% by
wheel barrow for every aditional 10m haul.
m3 Unskilled md 0.16
8.01.08 Washing broken stone and sand. m3 Unskilled md 1.50
Washing rubble. m3 Unskilled md 0.40
8.02.01 Breaking stones including Collection, seiving and
stacking within 10m.

3
a) 70mm - 100mm m Unskilled md 6.00
b) 40mm - 70mm m3 Unskilled md 8.00
c) 20m - 40mm m3 Unskilled md 12.00
d) 10mm - 20m m3 Unskilled md 18.00
e) 5mm - 10mm m3 Unskilled md 25.00
8.02.02 Making Blocks of required size out of stratified rocks
including hammer dressing, hauling distance 10m. and
stacking.
m3 Unskilled md 5.88
8.02.03 Making rubbles of required size including making hole,
blasting and breaking with chisel or hammer, hauling
distance 10m. and stacking.
m3 Gelatine kg 0.25
Unskilled md 4.50 Detonator no 2.00
Blaster md 0.10 Fuse wire m 2.00
8.02.04 Making rubbles of required size including breaking with
chisel or hammer (without use of explosive), hauling
distance 10m. and stacking.
m3 Unskilled md 5.50

8-2
Norms for Rate Analysis
Activity Group:- 8 : Quarries, Borrow Pits, Stock Pile and Spoil Areas.
Resources
Spec.
Activity
Nos
Clause Description of works Labour Materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
8.03. 800 Transportation of materials by manpower including
loading, hauling, unloading and stacking.

1) Excavated earthwork.
8.03.01.01 800 a) First 10m.with load unload and haul m3 Unskilled md 0.47
8.03.01.02 800 b) Every additional 10m. upto 100m m3 Unskilled md 0.12
8.03.02 800 2) Loose sand
8.03.02.01 800 a) First 10m.with load unload and haul m3 Unskilled md 0.47
8.03.02.02 800 b) Every additional 10m. upto 100m m3 Unskilled md 0.12

8.03.03 800 3) Gravel, river shingle, broken stone


aggregates and bats.
8.03.03.01 800 a) First 10m.with load unload and haul m3 Unskilled md 0.30
8.03.03.02 800 b) Every additional 10m. upto 100m m3 Unskilled md 0.13

8.03.04 800 4) Boulder, Cobbles, quarry stone


8.03.04.01 800 a) First 10m.with load unload and haul m3 Unskilled md 1.10
8.03.04.02 800 b) Every additional 10m. upto 100m m3 Unskilled md 0.19

8.03.05 800 5)Dressed Stone


8.03.05.01 800 a) First 10m.with load unload and haul m3 Unskilled md 1.10
8.03.05.02 800 b) Every additional 10m. upto 100m m3 Unskilled md 0.19

8.03.06 800 6)Bricks


8.03.06.01 800 a) First 10m.with load unload and haul 1000 nos Unskilled md 1.10
8.03.06.02 800 b) Every additional 10m. upto 100m 1000 nos Unskilled md 0.19

8-3
Norms for Rate Analysis
Activity Group:- 8 : Quarries, Borrow Pits, Stock Pile and Spoil Areas.
Resources
Spec.
Activity
Nos
Clause Description of works Labour Materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
8.03.07 800 7)Cement
8.03.07.01 800 a) First 10m.with load unload and haul t Unskilled md 0.50
8.03.07.02 800 b) Every additional 10m. upto 100m t Unskilled md 0.13

8.03.08 800 8)Reinforcement Steel and gabion wire


8.03.08.01 800 a) First 10m.with load unload and haul t Unskilled md 1.11
8.03.08.02 800 b) Every additional 10m. upto 100m t Unskilled md 0.36

8.03.09 800 9) Bitumen


8.03.09.01 800 a) First 10m.with load unload and haul 100 lit Unskilled md 0.15
8.03.09.02 800 b) Every additional 10m. upto 100m 100 lit Unskilled md 0.05

8.03.10 800 10) GI,CI,Pipe and fittings ,Black pipe


8.03.10.01 800 a) First 10m.with load unload and haul t Unskilled md 0.50
8.03.10.02 800 b) Every additional 10m. upto 100m t Unskilled md 0.13

8.03.11 800 11)Timber for temporary works


8.03.11.01 800 a) First 10m.with load unload and haul m3 Unskilled md 0.50
8.03.11.02 800 b) Every additional 10m. upto 100m m3 Unskilled md 0.08

8.03.12 800 12) Fabricated Structural Timber


8.03.12.01 800 a) First 10m.with load unload and haul m3 Unskilled md 0.70
8.03.12.02 800 b) Every additional 10m. upto 100m m3 Unskilled md 0.12
8.03.13 800 13) Fabricated Structural Steel
8.03.13.01 800 a) First 10m.with load unload and haul t Skilled md 0.40
Unskilled md 8.00
8.03.13.02 800 b) Every additional 10m. upto 100m t Skilled md 0.10
Unskilled md 2.00

8-4
Norms for Rate Analysis
Activity Group:- 8 : Quarries, Borrow Pits, Stock Pile and Spoil Areas.
Resources
Spec.
Activity
Nos
Clause Description of works Labour Materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
8.03.14 800 14)RCC Precast Element t To be estimated on the basis of size & shape of the elements.
8.03.15 800 15) Equiptment & accessories etc. requiring careful
handling.

a) First 10m.with load unload and haul t Skilled md 1.00


Unskilled md 10.00
b) Every additional 10m. upto 100m t Skilled md 0.20
Unskilled md 2.00
8.03.16 800 16) RCC hume pipe
8.03.16.01 800 i) 900mm dia
8.03.16.01.01 a) First 10m.with load unload and haul m Skilled md 0.040
Unskilled md 0.400
8.03.16.01.02 800 b) Every additional 10m. upto 100m m Skilled md 0.010
Unskilled md 0.100
800 ii) 750mm dia
a) First 10m.with load unload and haul m Skilled md 0.035
Unskilled md 0.330
800 b) Every additional 10m. upto 100m m Skilled md 0.010
Unskilled md 0.090
8.03.16.02 800 iii) 600mm dia
8.03.16.02.01 a) First 10m.with load unload and haul m Skilled md 0.03
Unskilled md 0.25
8.03.16.02.02 800 b) Every additional 10m. upto 100m m Skilled md 0.01
Unskilled md 0.08
8.03.17 800 17) Water
a) First 10m.with load unload and haul 1000 lit Unskilled md 0.47
b) Every additional 10m. upto 100m 1000 lit Unskilled md 0.12

8-5