Norms for Rate Analysis

Activity Group:- 9 : Earthworks


Spec. Resources
Activity No Clause Description of works Labour Materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
9.01 905 Road way excavation including disposal Add 3% of
upto 10m and lift upto 1.5 m etc. all
Labour cost
complete as per specification.
for T & P
3
m
a) Soft soil Unskilled md 0.75 Note:-
b)Hard soil/Gravels/B.M.S. Unskilled md 1.00 B.M.S.= Boulder
mixed soil
c) Soft Rock Unskilled md 2.75
d) Hard Rock
i) without blasting Unskilled md 12.00
ii) with blasting
I) Manual drilling Unskilled md 3.50 Gelatin kg 0.25
blaster md 0.10 Detonator no 2
fusewire m 2
II) Mechanical Drilling Unskilled md 1.50 Gelatin kg 0.25 Compressor &
blaster md 0.10 Detonator no 2 drill hr 0.34
fusewire m 2 or Portable Rock
drill hr 1
iii)Using chemicals
I) Manual drilling skilled md 0.10 Chemicals Kg 5
Unskilled md 4.00
II) Mechanical Drilling skilled md 0.10 Chemicals Kg 5 Compressor &
Unskilled md 1.50 drill hr 0.34
or Portable Rock
drill hr 1

9-1
Norms for Rate Analysis
Activity Group:- 9 : Earthworks
Spec. Resources
Activity No Clause Description of works Labour Materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
9.02 905 Earth work excavation for drain and Add 3% of
trenches including shoring, struting,
Labour cost
bracing, sheeting and disposal upto 10m
and lift upto 1.5 m etc. all complete as per
specification. m3
a) Soft soil Unskilled md 0.90
b)Hard soil/Gravels/B.M.S. Unskilled md 1.50
c) Soft Rock Unskilled md 3.00
d) Hard Rock
i) without blasting Unskilled md 16.00
ii) with blasting
I) Manual drilling Unskilled md 4.50 Gelatin kg 0.25
blaster md 0.12 Detonator no 2
fusewire m 2
II) Mechanical Drilling Unskilled md 1.75 Gelatin kg 0.25 Compressor &
blaster md 0.12 Detonator no 2 drill hr 0.4
fusewire m 2 or Portable Rock
drill hr 1.2
iii)Using chemicals
I) Manual drilling skilled md 0.12 Chemicals Kg 5
Unskilled md 5.00
II) Mechanical Drilling skilled md 0.15 Chemicals Kg 5 Compressor &
Unskilled md 2.00 drill hr 0.4
or Portable Rock
drill hr 1.2

9-2
Norms for Rate Analysis
Activity Group:- 9 : Earthworks
Spec. Resources
Activity No Clause Description of works Labour Materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
9.03 905 Haulage of excavated material beyond 10 Add 3% of
m upto 50m.
3
a) Soil material m Unskilled md 0.27 for T & P
b) Rock material m3 Unskilled md 0.33
9.04 905 Vertical lift of excavated material above 1.5 Add 3% of
m for every additional meter. Labour cost
m3 for T & P
a) Soil material Unskilled md 0.12
b) Rock material Unskilled md 0.15
9.05 909 Formation of embankment including Add 3% of
compaction in layers not exceeding
150mm. Compacted depth, watering and
haulage 10m. etc. all complete as per
specification.
m3 Unskilled md 0.50 suitable material cu.m 1.1 Roller 8-10t hr 0.017 Labour cost
fuel lit. 0.08 for T & P
water lit. 100
Note : Add 10 % of the total rate ( except for transporation of material) for necessary testing as per specifications.

9.06 909 Formation of rockfilled embankment


including compaction in layers not
exceeding 450mm. watering and haulage m3
Unskilled md 1.27 rock material Add 3% of
10m. etc. all complete as per specification.
including broken cu.m 1.1 Roller 8-10t hr 0.017 Labour cost
fragments for T & P
fuel lit. 0.08
water lit. 50
Note : Add 5 % of the total rate ( except for transporation of material) for necessary testing as per specifications.

9-3
Norms for Rate Analysis
Activity Group:- 9 : Earthworks
Spec. Resources
Activity No Clause Description of works Labour Materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
Excavation for foundation through all types
9.07.01 907
of soil including relevant lift and disposal
upto 20m.

m3

a)Depth upto 1.5m Unskilled md 2.00 Add 3% of

b)Depth more than 1.5m upto 3m Unskilled md 3.00 Labour cost

c)Depth more than 3m upto 4.5m Unskilled md 4.00 for T & P

d)Depth more than 4.5upto 6m Unskilled md 4.75


Increase by 30% for every additional meter depth of foundation over the rate for the previous depth.
e)Depth of foundation more than 6m

Excavation for foundation through soft rock


9.07.02 907 Add 3% of
including relevant lift and disposal upto
20m. Labour cost
3
m Use roadway excavation for soft rock item with addition of appropriate lift. for T & P

Excavation for foundation through hard rock


9.07.03 907 Add 3% of
including relevant lift and disposal upto
20m. Labour cost
m3 Use roadway excavation for hard rock item with addition of appropriate lift. for T & P

9-4
Norms for Rate Analysis
Activity Group:- 9 : Earthworks
Spec. Resources
Activity No Clause Description of works Labour Materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
9.08 907 Dewatering during foundation excavation Adopt the following percentage of unit rate of foundation excavation depending on the soil type & ratio of water table height to foundation
and foundation works. depth.

m3 Unit refers to the unit of excavation for foundation


soil type Pervious Impervious
Gravelly sandy fine-grained soil
Hw:Df
>1 150% 100% 50% 25%
0.8-1 120% 80% 40% 20%
0.6-0.8 90% 60% 30% 15%
0.4-0.6 60% 40% 20% 10%
0.2-0.4 40% 28% 14% 7%
0-0.2 20% 14% 7% 4%
<o 0 0 0 0
Note:- Hw-Height of water table/ level from the bottom of foundation during working season.
Df- Depth of the bottom of foundation from the ground.
Dewatering to be included in the relevant item of foundation as a sub item.
9.09 907 Providing and fixing, sheeting, shorting,
struting, shoring, bracing, stuffing and
(3-7)
making coffer dam during foundation
excavation and removing upto 10m and lift m3 0.04
Timber (planks,
upto 1.5 m etc. all complete as per unskilled md 0.50 wailing, strut etc).
specification.
spike/nails Kg 0.25
This work is to be included in the relevant item of foundation as a sub item.

9-5
Norms for Rate Analysis
Activity Group:- 9 : Earthworks
Spec. Resources
Activity No Clause Description of works Labour Materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
9.10 908 Back filling in layers in foundaion pits,
Add 3% of
trenches , etc, including compaction and
watering etc. complete, lead 10m. Labour cost
for T & P
3
m
a) Depth of foundation upto 1.5m unskilled md 1.14
b) Depth more than 1.5upto 3m suitable material excavated
unskilled md 1.62
for foundation to be used.
c) Depth more than 3m upto 4.5m unskilled md 2.1
d) Depth more than 4.5m upto 6m unskilled md 2.58
e) Depth more than 6m.

Increase by 30% for every additional meter depth of foundation over the rate for the previous depth.
Note : Add 5% of the total rate ( except for transporation of material) for necessary testing as per specifications.

9.11 905 Ecavation and disposal of slides manually


Add 3% of
haulage distance upto 50m
m3 Labour cost
for T & P
a) Soft soil unskilled md 0.6
b) Hard soil unskilled md 0.8
c) Soft Rock unskilled md 1.6
d) Hard Rock Refer Road way excavation

9-6