Professional Documents
Culture Documents
GM NDC 2019 Pilot
GM NDC 2019 Pilot
Prerequisite Requirement
All relevant prerequisite requirements for the specific Green Mark Rating are to
be complied with
1
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
2
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
Note:
1) PUE is a metric that illustrates data centre efficiency using the total annual facility energy
divided by total annual IT equipment energy. The IT equipment energy shall be measured at
PDU output [PUE category 2]. Please refer to SS 564 for PUE definition.
2) PUE performance of the data centres shall be determined using energy modelling software
at the 25%, 50%, 75% and 100% of IT load.
Platinum 0.78
Note:
1) Performance of the system shall be subject to measurement and verification.
2) In general, for data centres with cooling load of more than 500 RT, the use of air cooled
cooling system is not applicable. However, if the system efficiency of the air cooled cooling
3
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
system is comparable with the stipulated efficiency of water cooled cooling system, it will be
assessed on a case-by-case basis.
3) The prescribed system efficiency shall be achieved at 25%, 50% and 75% of the design IT
load.
4) For data centres with purchased cooling, the efficiency of the cooling system shall be
provided for assessment and verification. If the efficiency of the cooling plant is not available,
the default plant efficiency of 0.8 kW/RT shall be applied. Please refer to GM NRB: 2015
Technical Guide 2.1 (c) on DCS baseline efficiency.
All data logging with capability to trend at 1-minute sampling time interval, and recorded to
the 3rd decimal digit
Magnetic in-line flow meter, with 1% uncertainty and capable of electronic in-situ verification
to within ±2% of its original factory calibration. If installation of magnetic in-line meters is not
possible, ultrasonic flow meters may be used
Temperature sensors are to be provided for chilled water and condenser water loop and shall
have an end-to-end measurement uncertainty not exceeding ±0.05°C over the entire
measurement range. Provisions shall be made for each temperature measurement location
to have test plugs or additional thermo-wells located before and after each temperature
sensor for verification of measurement accuracy. All thermo-wells are recommended to be
installed in a manner that ensures the sensors can be in direct contact with the fluid flow.
There shall be valid justification if direct immersion of the temperature sensor(s) is/are not
possible. Such projects will be assessed on a case-by-case basis
Dedicated power meters of accuracy Class 1 or better and metering current transformers,
where applicable, of Class 1 or better, are to be provided for each of the following groups of
equipment: chillers, chilled water pumps, condenser water pumps, cooling towers fans and
air side equipment
4
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
(i) All forms of energy related to PUE calculation shall be measured and trended over time;
the data centre owners and/or operators shall verify that the energy related systems are
performing according to design.
(ii) The data centre shall, at a minimum, be equipped with energy metering to provide total
facility energy, total IT equipment energy at PDU output, in order to provide real-time
display and data collection of PUE, and to compute the annual average PUE.
(iii) All sources of energy serving the data centre shall be measured, including but not limited
to electricity, natural gas, steam and chilled water. Power meters of Class 1 or better shall
be used to measure electricity.
5
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
Refer to Annex A for Energy Modelling Guideline. PUE at 25% IT load is used for base point
calculation; However, if PUEs at 50% or 75%
cannot meet the reference PUE curve of
respective ratings, points will be deducted, i.e.
6
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
*Note: Where there is a combination of different type of Point scored = 0.6 x (% improvement)
system, points scored will be pro-rated based on the
weighted cooling consumption by the respective systems.
Refer to Annex C for working example.
7
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
To encourage on-site generation of renewable 1 point for every 0.01% replacement of total energy
energy to reduce the building’s energy (based on building energy consumption at 25% IT
consumption from the grid and carbon load)
emissions. (Up to 2 points for Sec 1.5(c))
8
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
9
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
10
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
11
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
12
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
(b) Green and Gracious Builder: 0.25 point for Certified or Merit; or
The main builder is a BCA Certified Green 0.5 point for Excellent or Star rating
and Gracious Builder. (Up to 0.5 point for Sec 3.4(b))
13
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
14
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
Section 4 – Smart and Healthy Building Green Mark Points (10 Points)
1
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
2
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
To encourage the use of innovative energy efficient Each feature or innovation shall demonstrate the
equipment, system or design features. following:
The intent of the proposed innovation
To qualify, the features must achieve significant, The additional environmental benefits
measurable improvement of energy performance in delivered
the following areas: The proposed requirements for
compliance
The proposed performance metrics
(Up to 10 Points)
3
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
ANNEX A
Energy Modelling Guideline
The simulation shall be conducted in accordance with the Green Mark NRB: 2015 Technical Guide and
Requirements - Annex C: Energy Modelling Methodology and Requirements, where applicable.
The energy performance of a Data Centre Facility shall take into consideration data centres’ unique
design such as N+1 or 2N design. Energy modelling shall be used to assess PUE and system efficiency
in multiple loads, i.e. IT load at 25% 50%, 75% and 100%. A separate calculator or software shall be
used to estimate the electrical losses in the power supply chain (transformers, switchgear, UPSs, PDUs
and electrical cables.) under various load conditions - 25%, 50%, 75% and 100% IT load. These losses
shall then be included as internal loads, dissipated as heat in the thermal zone.
The energy performance improvements may come from facility infrastructure design, selection of
equipment, their capacities and part load characteristics and how they are operated. The designer may
use the opportunity to determine the optimal operating configuration of equipment and systems in terms
of energy performance but must commit to the selection in the submission. The system configurations
must consider the redundant equipment and sequencing arrangements that enable the spare
equipment capacity to be on “hot” standby, i.e. running together with base capacity. Separate zones
and schedules shall be modelled based on spaces with different temperature, e.g. raise floor, data hall
and ceiling return.
4
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
ANNEX B
Used Case #1
Target Green Mark rating is GoldPLUS, hence the reference curve for GoldPLUS shall apply.
Where PUE Deviation Percentage refers to percentage deviation of the PUE at 50% and 75% IT load
from the reference PUE curve, whichever is higher. The PUE Deviation Percentage shall be capped at
2%. If the PUE at 50% and 75% IT load are better than the PUE Reference for the specific Green Mark
rating, then the PUE Deviation Percentage is zero.
1.7 −1.55
Base Point (at 25% IT load) = 1.4 ∗ ( ) ∗ 100 = 12.3
1.7
As the PUE at 50% and 75% is better (and lower than) the PUE Reference for GoldPLUS, the PUE
Deviation Percentage is zero.
1.55
Reference PUE curve 1.49 1.42
(GoldPLUS)
Data Centre A
1.55 1.48 1.41
Design PUE
5
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
PUE Deviation
Percentage
PUE Deviation N.A
Percentage to be applied
(cap at 2%)
Used Case #2
Target Green Mark rating is Platinum, hence the reference curve for Platinum shall be applicable.
Compare the percentage improvement of PUE at various load points at 50% and 75% IT load,
reference to Platinum reference curve.
1.5
Reference PUE curve 1.45 1.39
(Platinum)
Data Centre B
1.47 1.46 1.41
Design PUE
1.45 − 1.46 1.39 − 1.41
PUE Deviation × 100 = −0.69% × 100 = −1.44%
N.A 1.45 1.39
Percentage
6
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
PUE Deviation
Percentage to be applied 1.44%
(Higher deviation of 50% and 75% IT load)
(cap at 2%)
7
BCA-IMDA Green Mark for New Data Centres (GM NDC: 2019)
ANNEX C
Used Case #1
In this example, the full design IT load is ≥500RT, thus the baseline efficiency shall be 0.9 kW/RT.
Compare efficiency of the cooling system at the various load points, 25%, 50% and 75% IT load. The
highest efficiency value = 0.78 kW/RT at 50% IT load.
0.9−0.78
Cooling System Efficiency Point = 0.72 × ( ) × 100 = 9.6
0.9