TO DO LIST (Foundry)

SR# Machine Remarks


Roller head and boot pulleys installation
1 BE-FDY-01
Buckets fittment
2 Chute Installation From BE-FDY-01 to Sand cooling drum)

3 Exhaust installation between BE-FDY-01 to Sand cooling drum

4 Water Cooling Line installation between BE-FDY-01 to Sand cooling drum

End Caps Fitment


5 Cooling Drum Gear Drive Fitting
Drive Guide Covers Installation
Overband Magnetic Seprator
6 conveyors installtion on BC-FDY-01

from BC-FDY-01 to BE-FDY-02


7 Chute Installation
from BC-FDY-02 to BE-FDY-03
8 Pipe Chute Installation from New Sand Hopper to BE-FDY-03
Bentonite Storage vessel to
9 Fitment of Screw Conveyor
Intensive Mixer
Blender Installation
Water line Installation
10 Intensive Mixer
Discharge Gate Installation
Scrappers Installation
11 BC-FDY-03 Fitment of Rollers and Belt,Gear Motor
12 Chute from BC-FDY-03 to Green Sand Storage Hopper
13 Shakeout Machine Vibratory motors Installation

14 Vibratory conveyor installation from shakeout machine to BE-FDY-01


required
15 Electrical Controls Installation
16 Pattern making Kotmatsu shank d155 175-78-21693