Professional Documents
Culture Documents
Final Report PTTGC Thailand 2016
Final Report PTTGC Thailand 2016
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
FINAL REPORT
Period of inspection : 23rd of June, 2016, until the 5th of July, 2016
Report by : M. Vedder,
M. Wisse
Development - Revisions
Revision No. Prepared By Date Approved By Date Amendment Details
This publication is the intellectual property of Applus RTD and may not be used in whole or in part for any purpose other than the
business of Applus RTD and may not be used for the business of the recipient and may not be passed to any other person without
the permission of Applus RTD.
Page 1 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
CONTENTS
EXECUTIVE SUMMARY 3
1 INTRODUCTION 5
3 PREPARATIONS 13
4 CALIBRATION 14
5 LOCATION 16
5.1 Location 16
5.2 Parameters 16
5.3 Data collection 16
5.4 Data analysis 16
5.5 Result explanation 18
8 RESULT DISCUSSION 22
8.1 General information 22
8.2 Specific information 22
9 CONCLUSION 23
LIST OF ENCLOSURES 24
LIST OF ABBREVIATIONS 25
Page 2 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
EXECUTIVE SUMMARY
General;
The actual inspection of the 48” loading line was performed from the 29th of June, 2016 until the 4th of July,
2016.
This pipeline has been previously inspected, in 2009 and 2011. During the inspection in 2011, only the first
3,784.03 m. was inspected to determine the ovality.
During the inspection the pipeline was filled with Crude Oil.
The inside surface of the pipeline was clean, allowing a reliable ultrasonic inspection.
The flange of the existing pipeline at the entrance of the pipeline is the zero point. All axial distance
information is related to this point.
Two 90 degree bends are present at the beginning of the pipeline, but not visible in the inspection data
due to the crude oil level in the pipeline. The first bend is going 90 degrees down and the second bend is
90 degrees back to horizontal and 90 degrees to the right.
The distance covered during this inspection is 17,746.52 m against 19,000 m inspection distance as per
service contract requirement; at this point the tool was not capable to drive forward.
The pipeline is constructed out of longitudinal welded pipe sections.
No indications of internal corrosion were detected in the pipeline.
A total of 3 external wall loss indications were detected in the pipeline.
The ovality present in the first 2.043.62 m of the pipeline is calculated by using the following equation:
(IDmax – IDmin) / (IDmax + IDmin) x 100%.
An overview of the ovality and a comparison can be found in Enclosure 2.0 List of Anomalies.
All features detected during the inspection are listed in Enclosure 2.0 List of Anomalies.
For general details see Enclosure 1.0, the layout of the site and Enclosure 6.0, the system Block Diagram.
Page 3 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
Inspection Details
Date of actual inspection: 29th of June, 2016 until the 4th of July, 2016
Diameter of pipeline: 48”
Pipeline material API 5L - X60
Total length of pipeline inspected: 17,746.52 m
Inspection medium: Crude Oil
Average wall thickness: 19.2 mm
Average pipe section length: 12.5 m
Inspection Results
Number of welds: 1,423
Number of external metal loss: 3
Number of internal metal loss: 0
Number of bends: 2
Number of flanges 0
Number of high points 0
Number of low points 7
Ovality (distance) From 85.56 m till 2,044.25 m
Ovality (percentage) From 0.7 % till 6.5%
Number of longitudinal welds around 6 o’clock 0
Number of longitudinal welds with the same 0
clock position in adjacent pipe sections
Page 4 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
1 INTRODUCTION
PTTGC decided to have their 48” Loading line inspected with the Applus RTD Pipeline Inspection Tool. The
Applus RTD PIT is an umbilical operated tool with a maximum range of, for this job, 21,000 m.
Page 5 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
2.1 General
The Pipeline Inspection Tool is an umbilical operated system that performs ultrasonic inspections from the
inside of a pipeline. The PIT system is able to detect and quantify internal and external surface defects. If the
internal surface is clean and not (or only slightly) affected by corrosion, the remaining wall thickness can be
measured.
On the internal surface, defects of any depth can be measured.
For remaining wall thickness of external defects, the minimum value that can be measured depends on the
transducers applied and the inner surface condition of the pipeline.
In optimal conditions, the minimum wall thickness that can be measured is 2.6 mm.
The PIT system contains the following items:
The PIT vehicle measurement unit with 32 ultrasonic transducers
21,000 m reinforced optical fiber umbilical cable
Two winches, motor powered
Electronic and ultrasonic system
One computer system with two monitors for ultrasonic settings and measurements, color presentation
and data storage of the inspection results
One computer system for driving and inclination monitoring.
One computer for off-line data analysis
Enclosure 6.0 Block diagram shows an overall view of the PIT inspection system.
The PIT is driven by the 8 wheels of the traction unit and is electrically powered.
Electric power is supplied to the inspection tool via the umbilical cable.
Page 6 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
Typical speed of the system for this job is between 100 and 150 mm/sec (between 360 and 540 m/hr.).
The top wheel of the traction unit is pressed against the pipe inner wall by adjustable air pressure, causing
extra pressure on the traction wheels. This is required to drive the vehicle and to pull the umbilical.
Position and speed are continuously displayed at the PIT Control Unit and the various computers inside the
electronic equipment container. A side wheel connected to the electronic module acts as an odometer.
Proximity switches detect notches machined in the wheel and provide distance pulses, from which the position
and speed of the PIT are determined.
The transducer ring contains the ultrasonic transducers and is mounted at the very front of the vehicle.
Page 7 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
Page 8 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
The second measuring gate for each transducer is used in the so-called "echo start" technique. (B) This
measuring gate is calibrated in mm steel and is used for measuring the remaining wall thickness.
Page 9 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
Page 10 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
2.7 Winch
The 2 winches that contain a total of 21,000 m cable are both mounted in a frame with similar dimensions as
a 20' shipping container.
A winch is equipped with an electrical driven motor providing constant and adjustable torque (pulling force)
and speed by means of a remote control unit.
Page 11 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
A: Underwater Receiver
B: Pinger Unit
C: Land Receiver
Page 12 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
3 PREPARATIONS
To get open access to the 48” pipeline, a spool piece was removed from the pipeline and a launch platform
was placed in front of the pipeline. See the illustrations below for details.
A support has been fabricated and placed in front of the pipeline entrance, to support the guiding wheel.
The reference for circumferential locations is transducer no. 1 (12’ o’clock) on the transducer array at the front
of the tool.
All axial distance information of the inspection is recorded from the existing flange (zero point) of the pipeline.
Page 13 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
4 CALIBRATION
With the PIT inspection two different types of measurements are carried out at the same time, as explained
earlier in chapter 2.5.
Measurement in liquid, from initial pulse to first echo (= pipe inner wall) gives the internal profile of the pipe.
Measurement in steel from first echo (= pipe inner wall) to the next echo gives the wall thickness.
The calibration was done with immersion technique while the transducer was mounted in a calibration set up
and the tray was filled with crude oil. During the inspection, the pipeline was filled with the same liquid.
The stand-off measurement and the wall thickness measurement were calibrated separately using a special
step wedged calibration block increasing and decreasing in steps of 2.0 mm.
See below for a drawing of the PIT calibration block.
The actual calibration was carried out with one transducer and recorded in the appropriate recorder channel
on the computer. All other channels were programmed identical and all transducers were checked with a
special caliper gauge.
CRUDE OIL
Page 14 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
The below color plot shows an example of the calibration for one transducer as presented on the PIT
computer screen. The calibration for the stand-off, as well as the calibration for the wall thickness
measurements is visualized in this plot.
Page 15 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
5 LOCATION
5.1 Location
The 48” Loading line is located at the Map Ta Phut Tank Terminal, Map Ta Phut, Thailand.
The picture below shows a view of the inspection area.
5.2 Parameters
For this inspection the transit distance times for the inner profile were calibrated in mm crude oil.
Sound velocity in Crude Oil is V Crude Oil ≈ 1305 m/s.
The average standoff distance used during the inspection is 82.0 mm.
For the wall thickness measurements, transit distance times were calibrated in mm steel.
Sound velocity in steel is V steel ≈ 5950 m/s.
Page 16 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
Internal profile:
Internal profile readings are taken with all transducers.
From the standoff signals the following features can be observed:
Typical signature for the PIT tool passing weld penetrations
Internal corrosion defects
Signal pattern indicating wax layers/dirt
Signal pattern flanges
Signal pattern bends
Signal pattern dents
Signal pattern offtakes
Signal pattern reducers
Signal pattern low points/high points
Signal pattern of longitudinal welds
Wall thickness:
From the wall thickness signals the following features can be observed:
External corrosion defects
Signal pattern mill defects (inclusions, laminations)
Signal pattern external welds (attachments, sleeves, supports)
Actual wall thickness readings for each individual pipe section are taken from the stored computer data and
are available in Enclosure 2.0 List of Anomalies.
It should be noted that any imperfections in the plate material, such as inclusions/laminations, would show up
in the wall thickness measurements. An attempt has been made to discriminate between real metal loss
defects on the external surface and mill defects. Nevertheless, such indications may hamper the detection and
determination of external defects.
Page 17 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
5.5.1 General
The inspection results of the 48” loading pipeline are presented in Enclosure 2.0 List of Anomalies.
The inspection data is also available on DVD Rom and can be visualized with the enclosed PIT-Viewer®
program. An additional manual explains the separate features of this program. The PIT-Viewer® manual is
supplemented with this report.
Page 18 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
CIRCUMFERENCE, 960
WALL THICKNESS MEASUREMENT
B-SCAN STAND-OFF
Page 19 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
A total of 3 metal loss indications are detected in the pipeline, the calculation of the MAOP has been carried
out using ASME B31 G-2009 (original approach) with maximum depth and maximum length of each defect as
parameter.
The following general parameters, received from PTTGC, for this pipeline were used for the assessment:
Diameter : 48”
Pipe material : API 5L - X60
Yield strength : 60,000 Psi
Used design pressure (Pd) : 1,375 bar
Estimated Repair Factor (ERF) = Used design pressure/MAOP
The cross section of missing metal/corrosion has been modeled as: 2/3Ld - parabolic area approach for ASME
B31G Original (L= length and d = max. depth of corrosion)
For the purpose of the calculations, Applus RTD corrosion depth measurement resolution of 0.1 mm has been
extended to 0.5 mm and added to all maximum corrosion depth values in the defect set analyzed. This allows
performing calculations and assessment with conservative assumption of maximum corrosion depths. For each
defect, the actual wall thickness as close to the defect area as possible was used.
The design pressure can be calculated with the following formula:
Pd = 2t/D* SMYS* Fd
Pd : Local design pressure
t : Wall thickness most frequently measured in the line
D : Nominal outer diameter
SMYS : Specified minimum yield strength for the pipe steel
Fd : Design factor, for this case 0.72
Page 20 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
7.1 General
During the inspection an INS unit was attached to the inspection tool.
The INS unit recorded the tool movement through the pipeline. With the recorded data, GPS locations are
added to the features in the pipeline.
7.2 Results
The result of the GPS data acquisition is presented in the List of Anomalies. The latitude, longitude and the
altitude is provided for each weld.
7.3 Accuracy
The provided GPS locations are best estimates.
The final accuracy of the GPS locations is determined by the distance travelled and the provided GPS positions
of the start and end location.
The accuracy will increase with the accuracy of the start and end locations.
Page 21 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
8 RESULT DISCUSSION
Page 22 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
9 CONCLUSION
The 48” Loading line was clean enough to produce reliable inspection results.
Recommendations:
To monitor the condition and ovality of this pipeline, Applus RTD recommends performing a re- inspection
within 5 years’ time.
Page 23 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
LIST OF ENCLOSURES
Page 24 of 25
Number : PIT 266
Revision : 0
Date : 15-08-2016
Project no. : 1141-108979
Client : PTTGC
Object : 48” Loading line
LIST OF ABBREVIATIONS
A : Electrical current
API : American Petroleum Institute
ASME : American Society of Mechanical Engineers
BP : Burst Pressure
CD : Compact Disc
dB : Decibel
DVD : Digital Video Disc
FSH : Full Screen Height
LCD : Liquid Crystal Display
LoA : List of Anomalies
MAOP : Maximum Allowable Operating Pressure
m : Meter
mm : Millimeter
MHz : Megahertz
m/sec : Meter per second
mm/sec : Millimeter per second
PCU : Pit Control Unit
PIT : Pipeline Inspection Tool
PLEM : Pipeline End Manifold
PSI : Pound per square inch
RiserPIT : Riser Pipeline inspection Tool
RPM : Revolutions per Minute
RWT : Remaining Wall Thickness
SF : Safety Factor
SO : Stand Off
V : Sound velocity
WT : Wall Thickness
UT : Ultrasonic Technique
˚C : Degrees Celsius
Page 25 of 25