COOLING TOWER
SUMMARY
14.2 EARTHWORK -
14.3 CONCRETE -
BILL NO. 14
CARRIED TO SUMMARY -
14.2.2 EARTHWORK
B To Pile Cap m3
C To Slab m3
D To Tie Beam m3
E To Pile Cap m2
F To Slab m2
G To Tie Beam m2
H To Pile Cap m2
I To Slab m2
J To Tie Beam m2
K To Pile Cap m2
L To Slab m2
M To Tie Beam m2
14.2.5 OTHERS
Plastic sheet
N To Pile Cap m2
O To Slab m2
P To Tie Beam m2
14.2 EARTHWORK
CARRIED TO SUMMARY AT END OF BILL NO. 14 Rp. -
14.3.1 FORMWORK
A To Pile Cap m2 -
B To Slab m2 -
C To Tie Beam m2 -
E To Wall m2 -
14.3.2 CONCRETE
In-Situ Concrete
F To Pile Cap m3 -
G To Slab m3 -
H To Tie Beam m3 -
J To Wall m3 -
Lean Concrete
K To Pile Cap m2 -
L To Slab m2 -
M To Tie Beam m2 -
To Collection Rp. -
14.3.3 REINFORCEMENT
14.3.4 SUNDRIES
I Waterstop joint, sika water including all necessary per drawings and m
specification
To Collection Rp. -
COLLECTION
Page 14.3 /1 -
Page 14.3 /2 -
14.3 CONCRETE