Professional Documents
Culture Documents
PTS 11.32.01 CP System For Onshore Buried and Shore Approach Pipeline
PTS 11.32.01 CP System For Onshore Buried and Shore Approach Pipeline
PTS 11.32.01
June 2015
FOREWORD
PETRONAS Technical Standards (PTS) has been developed based on the accumulated knowledge,
experience and best practices of the PETRONAS group supplementing National and International
standards where appropriate. The key objective of PTS is to ensure standard technical practice across
the PETRONAS group.
Compliance to PTS is compulsory for PETRONAS-operated facilities and Joint Ventures (JVs) where
PETRONAS has more than fifty percent (50%) shareholding and/or operational control, and includes
all phases of work activities.
Contractors/manufacturers/suppliers who use PTS are solely responsible in ensuring the quality of
work, goods and services meet the required design and engineering standards. In the case where
y
nl
specific requirements are not covered in the PTS, it is the responsibility of the
O
Contractors/manufacturers/suppliers to propose other proven or internationally established
standards or practices of the same level of quality and integrity as reflected in the PTS.
se
lU
In issuing and making the PTS available, PETRONAS is not making any warranty on the accuracy or
completeness of the information contained in PTS. The Contractors/manufacturers/suppliers shall
na
ensure accuracy and completeness of the PTS used for the intended design and engineering
er
requirement and shall inform the Owner for any conflicting requirement with other international
nt
PETRONAS is the sole copyright holder of PTS. No part of this document may be reproduced, stored
AS
in a retrieval system or transmitted in any form or by any means (electronic, mechanical, recording or
otherwise) or be disclosed by users to any Owner or person whomsoever, without the prior written
N
consent of PETRONAS.
O
TR
The PTS shall be used exclusively for the authorised purpose. The users shall arrange for PTS to be
kept in safe custody and shall ensure its secrecy is maintained and provide satisfactory information to
PE
Table of Contents
1.0 INTRODUCTION ..................................................................................................... 5
1.1 SCOPE ............................................................................................................................ 5
1.2 GLOSSARY OF TERMS..................................................................................................... 5
1.3 SUMMARY OF CHANGES ............................................................................................... 7
2.0 DESIGN REQUIREMENTS ........................................................................................ 8
2.1 DESIGN INFORMATION .................................................................................................. 8
2.2 BASIC DESIGN ................................................................................................................ 8
2.3 DETAILED DESIGN .......................................................................................................... 8
y
2.4 PROTECTION CRITERIA .................................................................................................. 9
nl
O
3.0 SITE SURVEYS ...................................................................................................... 10
3.1 GENERAL TERRAIN DESCRIPTION ................................................................................ 10
3.2
se
RESISTIVITY OF SOIL ..................................................................................................... 10
lU
3.3 SOIL INVESTIGATION ................................................................................................... 11
na
y
nl
10.6 MISCELLANEOUS MONITORING FACILITIES................................................................. 29
O
10.7 CABLES, TEST POSTS AND DISTRIBUTION BOXES ........................................................ 29
se
11.0 SPECIAL FACILITIES .............................................................................................. 30
lU
11.1 TEMPORARY PROTECTION........................................................................................... 30
na
1.0 INTRODUCTION
This PTS specifies the minimum technical requirements for the design of cathodic protection
systems for onshore buried pipelines and based on PETRONAS lesson learnt and best
practices.
1.1 SCOPE
1.1.1 This PTS applies for onshore pipeline system and shore approach section.
y
Refer to PTS Requirements, General Definition of Terms, Abbreviations & Reading Guide PTS
nl
00.01.03 for General Definition of Terms & Abbreviations.
O
1.2.2 Specific Definition of Terms
se
lU
No Term Definition
na
No Term Definition
the same electrolyte and may cause
interference to the existing cathodic
protection system.
y
be equal.
nl
O
10 Natural Potential Pipe to soil potential taken without the
se
application of cathodic protection system.
lU
11 "OFF" Potential Pipe to soil potential taken prior to the
decrease of pipeline polarization once the
na
contract.
TR
No Term Definition
No Abbreviations Description
Silver/Silver Chloride type of reference
Ag/AgCl
1 electrode
y
nl
Copper/Copper Sulphate type of reference
Cu/CuSO4
O
2 electrode
se
AC Alternating Current
3
lU
DC Direct Current
na
4
er
2.1.1 The Owner shall submit all the technical information required for cathodic protection design
to the Contractor which shall include but not limited to items below:
i. Pipeline details i.e. length, size, type of coating, intended protection scope.
iv. Pertinent drawings i.e. pipeline route, existing systems, and foreign
y
structures/pipelines.
nl
O
v. Environmental and operating conditions
se
2.2 BASIC DESIGN lU
2.2.1 A basic cathodic protection design shall be submitted by the Contractor to the Owner for
na
review and approval. The design submitted shall include the documentation list as in
subsection 13.1. Detailed design shall only commence once the basic design is approved,
er
2.3.1 All necessary information to procure cathodic protection equipment and to construct,
commission and hand over the cathodic protection system shall be covered in the detailed
N
"OFF" POTENTIALS, mV
REFERENCE ELECTRODE :
Cu/CuSO4 Ag/AgCl/ Zinc
seawater
Protection potential for steel -850 -800 +250
aerobic
in environment
Protection potential for steel -950 -900 +150
in
anaerobic environment
Overprotection limit for -1150 -1100 -50
y
carbon
steel
nl
O
Table 3: Potential Limits for Cathodic Protection of Pipelines
NOTE: Cu/CuSO4 reference is used for pipelines in soil,
se
Ag/AgCl/seawater reference is used in seawater.
lU
Zinc reference is used in both soil and seawater for special monitoring purposes only.
na
In this specification the pipe-to-soil potential is used as a criterion for effective cathodic protection.
er
nt
2.4.1 The "OFF" potential on all parts of the pipeline shall be equal to or more negative than the
-I
protection potential value stated in Table 3 fo the pipeline to be considered fully cathodically
protected.
AS
2.4.2 The "OFF" potentials for carbon steel shall not be more negative than the overprotection limit
N
value as stated in Table I to avoid detrimental effects on the applied coating or on the pipeline
O
due to overprotection.
TR
2.4.3 The protection criteria for corrosion resistant steel and some high strength steel pipelines
PE
shall be determined by taking into account the material susceptibility to hydrogen induced
stress cracking. This shall include cathodic protection design for pipeline crossing or
approaching another pipeline made of such materials.
2.4.4 Presence of active sulphate reducing bacteria in anaerobic soil shall be confirmed via soil
investigation to determine the imminent protection for anaerobic environments.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 10 of 43
A pre-design site survey shall be carried out prior to execution of cathodic protection design.
Seasonal changes shall be taken into consideration if the surveyed area is affected and
different seasonal condition surveys shall be performed if possible. The worst case out of the
surveys shall be taken as the basis for the design.
3.1.1 General information of the terrain along the pipeline route shall be acquired from the survey
including:
y
nl
i. Terrain and vegetation types e.g. urban areas, industrial areas, farm land, forests,
O
open fields, desert, swamps, and rocks
se
ii. Visible relevant features and crossings e.g. rivers, canals, railways, main roads,
lU
overhead power lines, other pipelines
na
iii. All other information that is considered relevant to the design of a cathodic
protection system.
er
nt
3.2.1 Resistivity of soil shall be measured along the pipeline route at pipeline depth. The
N
measurements should at least be performed when there are changes in the soil characteristic
O
3.2.2 Readings should be taken in at least two different locations for each type of soil. Minimum of
2 measurements shall be taken at each location.
PE
3.2.4 For the purpose of determining the appropriate location for surface groundbeds, the four
terminal methods shall be used to measure resistivity at greater depths (10m maximum).
3.2.5 Any other methods for soil resistivity measurement shall require approval by the Owner.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 11 of 43
3.3.1 Chemical and bacterial soil analysis shall be carried out, if corrosive condition assumed to
occur due to presence of bacterial activity. Reference for test methods can be made to BS
1377 parts 3 and 9. This shall also applied for imported backfill used for pipeline construction.
3.3.2 Soil boring shall be conducted for hilly and rocky area and the characteristic of soil that can
affect the cathodic protection flow e.g. graphitic soil, shall be analysed and determined from
the coring sample.
3.4.1 Current drainage test should be performed to determine current requirement and optimal
current distribution for cathodic protection system design of existing pipelines.
y
nl
3.4.2 Prior to performing current drainage test, pipeline isolation equipment and monitoring
O
facilities should be installed to obtain relevant results.
se
3.4.3 To determine the current requirement, total polarisation of pipeline length should be
lU
achieved and “OFF” potentials taken at regular points along the pipeline should be within the
potential limits outlined in Table 3. Allowance for probability of coating damage throughout
na
the pipeline remaining life shall be made by adjusting the current demand.
er
3.5.1 Potential sources of hazardous AC and/or DC stray currents shall be investigated by the
Contractor and the mitigation of stray current effects shall be proposed in the design.
AS
3.5.2 The contractor shall carry out a stray current survey during commissioning, in the event that
N
3.5.3 Source of stray current shall be eliminated by appropriate insulation. Other means such as
installation of current drainage system shall be designed if insulation is not applicable.
PE
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 12 of 43
Electrical isolation shall separate pipeline cathodic protection system from other plant, foreign
structures/pipeline and electrical and instrument earthing systems.
The Contractor shall justify his decision for any isolation omittance in his basic design i.e.
incorporation of short branch line, small pipeline facilities and/or crossing of small rivers into
main pipeline cathodic protection system, subject to Owner’s approval.
Isolation joint/flange shall be installed above ground or in inspection pits; and shall not be
buried. Each isolation joint/flange shall be provided with test facilities.
y
The isolation joint/flange shall be equipped with earthing or surge arrestors in areas with risk
nl
of high voltages presence on the pipeline i.e. due to adjacent power systems or lightning.
O
For ease of identification, isolation joint/flange should be painted in a contrasting colour. The
se
paint shall be compatible with the pipeline coating and colour code used should be consistent
lU
in one area i.e. red paint or black coal tar epoxy are commonly used. Isolation joint/flange
shall not use paints containing metallic pigments such as zinc or aluminium.
na
iv. Between pipeline sections running in different types of electrolyte (e.g. river
crossings) and/or different method of installation (e.g. HDD for river crossings,
TR
Unless running in the same trench and having the same coating system, parallel pipelines shall
be electrically isolated from each other.
Pipelines should avoid touching or near any metal; and should be electrically isolated from
pipe supports.
The Contractor shall ensure adequate arrangement for effective cathodic protection if the
pipeline isolation is designed by other party.
In case of designing for existing pipelines, the Contractor shall determine the quality of
available pipeline isolation system and propose any improvements required to achieve
appropriate isolation together with his basic design.
Safety or instrument earthing shall be compatible with the cathodic protection system.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 13 of 43
4.1.1 Isolation joints shall be designed with materials, dimensions and constructed to meet the
pipeline design requirements.
4.1.2 Manufacturer shall internally coat the isolation joints with an amine cured epoxy coating,
applied on a blast cleaned surface (Sa 2½, ISO 8501-1). 50mm allowance for welding at both
ends shall be left uncoated.
4.1.3 All sealing and isolation materials shall not react with the product transported.
4.1.4 The isolation joints shall withstand for 5 minutes without bridging or reduction in electrical
resistance, a voltage of 1500 volt AC, 50 Hz across the joint.
y
4.1.5 The joint shall achieve electrical resistance higher than 1 M Ω measured at 1000 volt DC in dry
nl
air.
O
4.1.6 The overall length of the isolation joint shall be at least one metre, if the product transported
se
by the pipeline is dry gas, dry crude oil, or oil products.
lU
4.1.7 The following requirements shall apply for pipeline transporting an electrolyte or anticipated
na
i. The overall length of the isolation joint shall be four times the pipe diameter (with
nt
a minimum of one metre), if the resistivity of the electrolyte is higher than 100
-I
ohm.cm, or the volume occupied by the electrolyte is less than 5% of the pipeline
volume.
AS
ii. Isolating spools shall be used if the resistivity of the electrolyte is below 100
N
ohm.cm and the volume of electrolyte is more than 5% of the pipeline volume.
O
TR
iii. Immediately prior to welding the isolation joints onto the pipeline, the resistance
across the joints shall be shall be measured. The minimum resistance shall be 1
PE
MΩ.
Where:
4.3.1 Insulated flanges shall be used as an electrical isolation when application of i isolation joints
is not possible i.e. cathodic protection retrofit for existing pipelines.
4.3.2 Flanges and insulation kits shall meet the design requirements of the pipeline. Raised face or
full face flanges should used insulating gasket of neoprene coated phenolic resin type.
4.3.3 Both sides of the bolts shall be insulated with full length phenolic or composite sleeves and
phenolic resin insulating washers and steel washers.
4.3.4 Prior to welding onto the pipeline, insulated flanges should be assembled and tested. The
insulated flange shall withstand a voltage of 1500 volt DC across the flange assembly for one
minute without causing breakdown of the insulation or flash over. The resistance across the
y
assembled flange shall be taken successively and shall read higher than 1 MΩ.
nl
O
4.3.5 The bolt-to-pipe resistance shall be measured for application on existing flanges and the
overall isolated flange efficiency shall be determined after cathodic protection is in placed.
se
This can effectively been done by measuring the current through the attached pipe using a
lU
"Swain-type" current clamp/meter.
na
4.3.6 With the exceptional of sour service condition, flange protectors or protective tape shall be
applied to protect insulated flanged from dirt and moisture ingress.
er
nt
4.4 EARTHING
-I
4.4.1 Cathodic protection system for pipeline should be electrically isolated from common or plant
AS
4.4.2 Electrical earthing devices installed on the protected pipeline may be required for safety
O
reasons or pipeline earthing may be required to mitigate the effect of induced electrical
TR
voltages.
PE
4.4.3 Electrical safety earthing application shall be made compatible with the cathodic protection
systems as per following requirements:
iii. Install in the earthing circuit or by the installation of separate earthing electrodes.
4.4.4 For the purpose of mitigating the AC induced voltages effects on pipeline, earthing should be
installed at the following locations:
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 15 of 43
y
nl
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 16 of 43
Isolation joints installed at coating/electrolyte changes shall always be bonded at test posts;
to keep the pipeline electrically continuous when the cathodic protection is operational.
For non-welded pipeline applications, the continuity of the cathodic protection shall be
maintained and shall be tested i.e. by carrying out overlapping potential measurements. This
can be ensured by erection of permanent bonds over high resistance flanges/couplings, using
cables and approved attachment methods.
y
nl
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 17 of 43
6.1.1 The Owner shall provide the existing or planned coating system to the Contractor upon
request.
6.1.2 The appropriate design parameters for each coating type shall be used in the design in case
of adjacent structures having different type of coatings or significant difference in coating
condition. Pipeline isolation shall be provided should the interference is expected.
6.2.1 Unless stated otherwise by the Owner, the cathodic protection system shall be designed for
y
the pipeline design life.
nl
O
6.2.2 In the event that the above requirement cannot be realized, due to normal life of cathodic
protection system components lesser that pipeline design life or incompatible control of
se
cathodic protection levels at the beginning and at the end of the design life, the Contractor
lU
shall take into account and justify this shorter life on its installation system, methods and
instructions for future upgrading of the system in his basic design.
na
6.3.1 As required during the pipeline design life, the Contractor shall determine the pipeline current
-I
demand and spacing between cathodic protection stations by calculating the attenuation. For
new construction projects, the minimum design values shall be based on current densities in
AS
Table 4.
N
6.3.2 A current drainage test shall be carried out to determine the current requirement for existing
O
6.3.3 The higher of the two values computed by above methods; pipeline current demand and
PE
current drainage test, shall be used as the cathodic protection system capacity.
6.3.4 The minimum design current densities given in Table 4 shall be increased by 25% per 10°C rise
in temperature above 30°C for protection of pipelines with elevated operating temperatures.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 18 of 43
Asphalt bitumen, 6 mm
Butyl rubber tape 0.040 0.100 0.200
Asphalt mastic
Fusion bonded epoxy
Liquid epoxy Coal
tar epoxy 0.010 0.020 0.05
y
Table 4: Design current densities for different pipeline coatings (operating temperature up
nl
to 30 °C)
O
NOTE: The current densities given in Table 4 already include the current requirements due to the expected
se
coating breakdown during the pipeline life.
lU
na
er
nt
-I
AS
N
O
TR
PE
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 19 of 43
By means of requisition, the type of cathodic protection system shall be indicated. In case not
specified, the type of cathodic protection system shall be proposed by the Contractor with his
justification included in the basic design.
i. Soil resistivity
y
iv. Presence of stray currents
nl
O
v. Availability of power supply
se
vi. Site layout lU
vii. Presence of other conductors
na
viii. Maintenance
er
Impressed current shall be used if the above criteria do not clearly justify one particular
system.
AS
N
O
TR
PE
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 20 of 43
By means of requisition, the DC voltage source shall be indicated if required. The Contractor
shall propose one of the DC sources alternative if it was not specified in the requisition.
Justification of his choice shall be provided and shall be made based on local geographical
circumstances and infrastructure.
8.1.1 Transformer/rectifiers
y
nl
ii. Transformer/rectifiers shall be of a special design for cathodic protection service
O
and should be 3-phase units if available.
se
iii. Transformer/rectifiers shall be fit to operate under the normal service conditions.
lU
The output voltage shall be adjustable from zero to the maximum rated output
when on load. Tapping switches shall be front-mounted; if required, with a step-
na
v. The rectifier shall be fabricated to provide full wave rectification using high
current density selenium cells or silicon diodes. The current rating of the diodes
N
shall be higher than 1.25 times the maximum current rating of the rectifier and
O
vi. The output rms ripple current shall not exceed 5% of the DC output current
PE
ix. Meters of approximately 70mm diameter or similarly sized square pattern meters
with measuring accuracy better than 2% of full scale shall be provided to the
transformer/rectifier to read the output voltage and current.
x. The polarity of the DC terminals and AC supply terminals shall be clearly marked.
AC and DC cables shall be separated by an insulating panel.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 21 of 43
xi. Unless otherwise stated, a built-in timer unit shall be required. The timer unit shall
be capable of switching the full output current in a sequence of 50 seconds on
and 10 seconds off and may be mechanical or electronic. All transformer/rectifier
timer units should be provided with a facility for synchronous switching in the
event that a pipeline system is cathodically protected by more than one
transformer/rectifier. The timer shall be bypassed during normal operation.
xii. The incoming cables shall terminate in separate non oil filled cable boxes and
penetration into the tank shall be via bushings above oil level for an oil cooled
transformer/rectifier. A sight glass and thermometer shall be provided.
y
information on area classification to the Contractor.
nl
O
xiv. The enclosure shall have a minimum degree of protection IP 54 in accordance with
se
IEC 529, if installed outdoors.
lU
8.1.2 Engine generator sets
na
A remote survey unit with alarms shall be installed. If not possible, a two generator system
shall be used (one running, one on standby) with an automatic change-over system.
er
nt
and/or current control equipment and a load cut off system shall be provided to
protect the batteries from damages due to a complete discharge.
N
O
ii. Battery chargers and generators shall be equipped with regulators to ensure that
TR
the recommended charging rates are practiced and shall be provided with a
protection system to avoid overcharged batteries.
PE
iii. Wind and solar generators shall be designed based on extensive local weather
reports, stating average and minimum sun and/or wind periods and intensity
during all seasons, generally a one year period, to determine the capacity of the
system.
iv. Wind and solar generators shall be rated to recharge the batteries in less than 48
hours from a partially discharged state due to extended period of no wind/sun.
v. In tropical areas the generators and batteries shall be designed to operate in the
high ambient temperatures. Solar generators should be designed to maintain the
design capacity at the highest ambient temperature.
The use of thermoelectric generators shall be justified by the Contractor; and shall obtain
approval from the Owner for their use.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 22 of 43
8.2 GROUNDBEDS
8.2.1 The groundbed of an impressed current cathodic protection system shall be designed such
that:
i. Its mass and quality is sufficient to last for the design life of the system.
ii. Its resistance to earth allows the maximum predicted current demand to be met
at 80% or less of the voltage capacity of the DC source during the design life of
the system.
iii. Its location is remote from the pipeline and any other buried structure, to provide
a regular distribution of current along the pipeline.
y
iv. The risk of causing harmful interference on other buried structures is minimized.
nl
O
8.2.2 The selection of the location and the type of groundbed shall depend on local conditions such
as:
se
i.
lU
Soil conditions and resistivity at various depths.
na
i. If the soil conditions at the required depth are suitable to meet the requirements
in subsection 8.2.
8.2.4 The Contractor shall include and specify information below in his basic design:
vi. Backfilling.
The design and construction of borehole shall prevent any undesirable transfer between
water bearing formations and pollution of underlying strata from the surface (e.g. tank farms).
Casing at depth shall be electrically isolated from metal casing and structures at the surface.
To prevent gas blocking of the well, adequate venting pipes shall be provided to the deepwell
y
groundbeds. The vent pipe shall be of chlorine resistant material. Vent pipe blockage by coke
nl
backfill shall be avoided using filter gravel.
O
8.2.5 Surface groundbeds
i. If the soil conditions at the proposed groundbed depth, are suitable to meet
the requirements in subsection 8.2.
er
nt
ii. If sufficient distance from the pipeline can be achieved and there is no risk of
shielding.
-I
AS
The anodes or the highest point of the carbonaceous backfill shall be not less than 1 metre
below ground level.
N
i. Graphite.
iii. Magnetite.
v. Platinised titanium/niobium.
The selected anode material, weight and dimensions shall be demonstrated suitable to cater
for the required anode current output, to cover the design life of the cathodic protection
system and shall be compatible with the soil composition.
Unless the ground conditions dictate otherwise, a carbonaceous backfill or other low
resistivity backfill material shall be used.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 24 of 43
For the purpose of measuring anode current outputs, individual anode circuits shall be
provided with shunts.
ii. If required, variable resistors shall be installed in the negative drain circuit to
balance the current to each of the adjacent pipelines. An appropriately sized
shunt and diode shall be provided at the DC source for each of the negative circuit.
iii. A distribution box for all cables, diodes and current measurement facilities shall
y
be installed.
nl
O
8.3.2 Automatic potential control
se
By the means of requisition, the DC voltage source shall be provided with automatic potential
lU
control. The suitable permanent reference electrode shall be buried close to the pipeline to
achieve this.
na
The potential measuring circuit shall have a minimum input resistance of 100 MΩ. The control
er
system shall have an accuracy of 10 millivolts and shall be provided with adjustable voltage
nt
and current limiting circuits and/or alarms to protect the pipeline against overprotection in
-I
case of failure of a reference cell. A panel mounted meter to read the pipe-to-soil potential
shall be provided.
AS
8.3.3 Cables
N
O
All cables, cable connections and cable accessories shall be in accordance with section 12.
TR
The Contractor shall specify in the detailed design the civil works required to install the
cathodic protection system. Such works should include transformer/rectifier plinths, deepwell
head works, mounting details of distribution boxes and test posts, cable trenches, security
fencing etc.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 25 of 43
i. If the pipeline (section) runs in low resistivity soil, water, swamps or marshes.
y
nl
vi. If it can be assumed that maintenance of electrical equipment associated with
O
and Impressed current system cannot be carried out by the operator.
se
vii. For localised (hot-spot) protection to supplement impressed current systems.
lU
If cathodic protection by sacrificial anodes is selected, the Contractor shall prove by
na
sacrificial anodes.
-I
ii. The selected type of anode is capable of continuously supplying the maximum
AS
current demand.
iii. The total mass of anode material is sufficient to supply the required current during
N
The anodes should be buried in low resistivity chemical backfill to obtain the required output.
PE
The Manufacturer/Supplier of sacrificial anodes shall supply anodes which are clearly marked
with the type of material (trade name), anode weight (without backfill), and charge number.
The supplier shall provide full documentation of number, types, weight, dimensions, chemical
analysis and performance data of the anodes.
The anodes shall be inspected for mechanical damage, casting quality and the bonding of the
anode core/cable.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 26 of 43
9.1.1 Zinc anodes should not be used if the resistivity of the electrolyte is greater than 1500
ohm.cm.
9.1.2 Zinc anode composition for standard applications shall be in accordance with Table 5.
Cu 0.005 max. %
Al 0.10 - 0.50 %
Si 0.125 max. %
Fe 0.005 max. %
Cd 0.025 - 0.07 %
Pb 0.006 max. %
y
Zn remainder
nl
Table 5: Chemical composition for Zinc Anodes
O
se
9.1.3 For non-standard applications (e.g. high temperature) special alloys may be used which shall
be approved by the Owner.
lU
9.2 MAGNESIUM ANODES
na
er
9.2.1 Magnesium should not be used if the resistivity of the electrolyte is higher than 3000
ohm.cm.
nt
-I
9.2.2 The use of chemical backfill around buried anodes shall be used to increase current output
and to avoid passivity.
AS
9.2.3 Magnesium anode composition for standard applications shall be in accordance with Table 6.
N
O
Cu 0.02 max. %
TR
Al 5.3 - 6.7 %
Si 0.1 max. %
PE
Fe 0.003 max. %
Mn 0.15 min. %
Ni 0.002 max. %
Zn 2.5 - 3.5 %
Mg remainder
9.2.4 For special applications (e.g. high output in high resistivity soil) special alloys may be used,
which shall be approved by the Owner.
9.3.1 Backfill for sacrificial anodes shall consist of a mixture of gypsum, bentonite clay and sodium
sulphate. The ratio of the components shall be such to obtain optimum results in the
prevailing resistivity and soil wetness.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 27 of 43
9.3.2 The supplier shall include the composition of the backfill material in the anode
documentation.
9.4.1 All cables, cable connections and cable accessories shall be in accordance with section 12.
Sacrificial anode cables shall be connected to the pipeline via a bondbox and shunts to allow
anode current monitoring.
9.4.2 For magnesium anodes it should be allowed to install a resistor in the anode circuit to limit
the protection levels to within the protection criteria.
y
nl
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 28 of 43
The contractor shall include in his design sufficient monitoring facilities to ensure effective
survey of the level of the cathodic protection along the pipeline. The minimum requirements
for monitoring facilities are given below.
10.1.1 To monitor pipe to soil potentials, test posts shall be installed at distances of maximum 1000m
along the pipeline. In urban or industrial areas a closer distance (maximum 200m) should be
taken. At least one test post shall be installed between major obstacles such as waterways,
main roads and railways to allow unobstructed close interval potential surveys.
10.1.2 Two separate cables shall be attached to the pipeline and terminated in the test post.
y
nl
10.1.3 If pipelines are running in parallel regardless in the same trench or not, each pipeline shall be
O
provided with separate potential monitoring facilities. Test posts should be installed not more
than 2.5m away from the pipeline.
se
lU
10.2 FOREIGN PIPELINE BONDING FACILITIES
na
At crossings with foreign pipelines, a bonding facility shall be provided, consisting of two
separate cables attached to each individual pipeline, terminating in a test post with suitable
er
facilities to install direct or resistive bonds. The cables to each pipeline shall be identified by
nt
10.3.1 If the casing is longer than 10 metres, a test facility shall be installed at both ends of the casing.
N
Shorter casings shall be provided with a test facility at one end only.
O
TR
10.3.2 In each test facility, one test cable shall be connected to the pipeline and, if a steel casing is
used, one test cable shall be connected to the casing. Both cables shall be terminated in one
PE
test post.
10.4.1 At all isolation joints/flanges, two cables shall be connected to each side of the joint or flange.
All cables shall be separately terminated in one test post with suitable facilities to install direct
or resistive bonds.
10.4.2 The cables to each side of the isolation joint shall be identified by colour coding or tags.
10.5.1 At the drain points each negative connection to the pipeline shall be provided with current
measurement facilities. Where multiple negative connections are installed separate shunts
and blocking diodes shall be provided, installed in a distribution box.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 29 of 43
10.5.2 At the drain point a potential monitoring station shall be installed; except on an above ground
section of the pipeline, using a separate test cable connected to the pipeline for the
measurement of the drain point potential.
The Contractor should propose other test facilities which he considers necessary for cathodic
protection monitoring. Such test facilities may include in-line current measurement facilities,
buried polarization coupons, etc.
All cables, test posts and distribution boxes shall be designed and installed in accordance with
section 12.
y
nl
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 30 of 43
11.1.1 In the case that the pipeline is to be buried in highly corrosive soil and the installation of the
permanent cathodic protection system cannot be finalized before the pipeline is buried or if
specified by the Owner, a temporary cathodic protection system shall be installed. Such a
system shall be designed in the same way as a permanent cathodic protection system with
the exception that material quantities and quality shall be adequate to cover a lifetime equal
to the time of the pipeline construction until the expected commissioning of the permanent
cathodic protection system. Anode connections shall be constructed such that they can easily
be connected/disconnected during and/or after commissioning of the permanent system.
11.1.2 The permanent monitoring facilities connected to the pipeline shall be constructed
y
simultaneously with the pipeline to allow monitoring of the performance of the temporary
nl
system.
O
11.2 PROTECTIVE CASING
se
lU
To obtain effective cathodic protection the use of pipeline casings should not be
recommended. However, if their use is mandatory, the design of the casing should be such as
na
ii. The pipeline shall be electrically insulated from the casing using non-metallic
spacers (thinsulators).
N
O
iv. The casing should be sealed using non-metallic end seals and provided with vent
PE
Non-metallic casings which act as a shield preventing the flow of protective current to the
carrier pipe shall be dried and suitable end seals and vent pipes installed. Additional cathodic
protection shall be provided to the carrier pipe inside the casing, by installing ribbon anodes
together with a zinc reference cell. Magnesium ribbons shall be attached to the carrier pipe
via a cable in a test post.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 31 of 43
11.3.1 If the pipeline runs in the vicinity of high voltage power lines, the Contractor shall investigate
whether high AC voltages can be present on the pipeline by induction or otherwise and
whether devices have to be installed for protection of the pipeline and personnel.
11.3.2 The Contractor shall show (by calculation or otherwise) that no harmful voltages can be
present or design additional facilities to prevent excessive voltages.
In areas of lightning activity the Contractor shall install suitable lightning protection to protect
the pipeline isolation and cathodic protection equipment. This should consist of suitably rated
surge arrestors. Surge arrestors shall be mounted across isolation joints/flanges and across
y
the output terminals of DC voltage sources.
nl
O
11.5 SURGE ARRESTOR
se
11.5.1 Surge arrestors required to prevent elevated voltages due to faults in adjacent electrical
lU
power systems or lightning shall be of the spark gap type and shall be designed such that:
na
i. The impulse breakdown voltage of the electrodes is lower than that of the
isolation joint across which they are mounted.
er
nt
ii. The spark gap is capable of discharging the expected lightning currents
-I
iii. The spark gaps are fully encapsulated to prevent sparks in open atmosphere and
to protect the spark gaps from moisture.
N
O
11.6.1 For regular monitoring of cathodic protection systems the equipment to be used shall meet
the following requirements:
PE
ii. In-line current meters shall not be used except for trouble shooting. Cathodic
protection currents shall be measured using fixed shunts or resistors or clamp-on
current probes.
iii. Voltmeters and other monitoring equipment used to measure pipe to soil
potentials shall have an accuracy of better than 5 millivolts and shall have an input
resistance of at least 100 MΩ.
iv. Data loggers used to monitor pipe to soil potentials over prolonged periods shall
have an input resistance of at least 100 MΩ (also in a "dormant" mode, otherwise
shall be disconnected from the pipeline or reference electrode while the data
logger is in the "dormant" mode, e.g. by an automatic relay switch).
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 32 of 43
v. Cu/CuSO4 reference electrodes shall be used in combination with soil and fresh
water.
vii. Zinc reference electrodes shall only be used as permanent reference electrodes
in combination with soil and seawater.
y
nl
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 33 of 43
12.1 CABLES
12.1.1 All cables shall be single core stranded copper cables, suitable for DC use and shall be double
insulated and sheathed to withstand the prevailing chemical and mechanical (soil) conditions.
The minimum cable size shall be 6 mm2.
12.1.2 All cables shall be sized such that no excessive voltage drops occur which reduce the capacity
of the system.
12.1.3 Resistance of anode cables may be used to balance the output of different anodes or
groundbeds. The detailed design shall give calculations to support this design detail.
y
12.1.4 In industrial or urban areas armoured cables should be used.
nl
O
12.1.5 All cables shall be laid without coils or kinks, buried in soft sand at a depth of at least 0.5m,
provided with cable protection tiles or warning tape as considered suitable for the area.
se
lU
12.1.6 All buried cables shall be of one continuous length without splices. Cable to cable connections
should be made above ground inside distribution boxes to reduce the risk of damage and to
na
allow monitoring.
er
12.1.7 Cable routes shall be clearly marked using cable markers. These should be installed at
nt
approximately 100 metre intervals and at every change of direction of the cable route.
-I
12.2.1 Minimum anode cable size shall be 10 mm2. Cable connections shall be insulated using epoxy
N
12.2.2 The cables of impressed current anodes shall be connected to the positive feeder cable inside
TR
an above ground distribution box to enable current monitoring. The cables of sacrificial
anodes shall be connected to the pipeline via an above ground distribution box to allow
PE
12.3.1 General
ii. The Contractor shall include in the design detail procedures of processes to be
used for cable connections. The detail procedures shall be approved by Owner.
Welders shall be fully qualified for the applicable welding process.
iii. Welding of cable connections shall not be carried out on bends or within 200mm
from welds.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 34 of 43
iv. All below ground electrical connections shall be fully encapsulated to comply with
the original coating standards before backfilling.
v. The following guideline for the selection of cable connections shall be followed:
a) Drain cables shall be connected using welding or studwelding.
b) Bond cables shall be connected using welding, studwelding or pinbrazing.
c) Potential measuring cables shall be connected using any of the referred
methods.
12.3.2 Welding
i. A metal plate, 50x50mm minimum, provided with a welded M10 threaded stud
bolt, shall be welded to the pipeline by two continuous welds in the
y
nl
circumferential direction of the pipe only. The plate shall be made of the same
material as the pipeline.
O
se
ii. The cables shall be connected to the threaded studbolt using crimped or brazed
cable lugs, nuts and serrated washers.
lU
12.3.3 Stud welding
na
er
ii. The stud material and consumables shall be compatible with the pipeline
material. The process shall not influence the pipeline material properties to fall
AS
iii. The size of threaded studs shall be 8mm or more to suit the cable size. The cables
O
shall be connected to the stud using crimped or brazed cable lugs, nuts and
TR
serrated washers.
PE
12.3.4 Pinbrazing
i. The pinbrazing process shall use specially designed cable lugs and brazing pins to
braze the cables to the pipeline and shall be approved by the Owner.
ii. The brazing materials shall be compatible with the pipeline material. Penetration
of copper and/or other brazing metals into the pipeline shall not be deeper than
1mm and the hardness shall remain inside the original pipeline requirements.
iii. Pinbrazing shall not be used on austenitic stainless steel and duplex stainless steel
pipelines.
i. Thermit welding process shall be such that copper penetration into the pipeline
material shall not be deeper than 1mm and that the hardness shall remain inside
the original pipeline requirements.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 35 of 43
ii. Thermit weld charges shall not be greater than 15 grams and cable cores shall not
be heavier than 16mm2. If heavier cables need to be attached, the core shall be
separated into smaller strands of less than 16mm2 each and welded separately.
iii. Thermit welding shall not be used for austenitic stainless steel and duplex steel
pipelines.
Where welding, brazing or thermit welding is not possible, e.g. for safety reasons, the
Contractor may design glued electrical connections using metal plates bonded with electrically
conductive epoxy resin. This method shall not be used for current carrying cables (drain
cables, bond cables). The materials to be used and the installation procedure shall be
approved by the Owner.
y
nl
12.4 TEST POSTS AND DISTRIBUTION BOXES
O
12.4.1 Test posts shall provide sufficient room for the termination of test cables and for the
se
installation of bonding cables and/or resistors as required by the design.
lU
12.4.2 If installed above ground they shall be provided with lockable access doors or caps, or have
na
external insulated contacts fitted, to allow easy connection of test clips for regular monitoring.
Cable entry shall be at the bottom through protective tubes.
er
nt
12.4.3 If test stations are required to be installed underground, they shall have adequate water
-I
drainage facilities and they shall be provided with a closure to avoid ingress of dirt.
AS
12.4.4 Distribution boxes shall provide sufficient room for control and test equipment. All cables shall
be connected to individual terminals.
N
O
12.4.5 Distribution boxes shall always be installed above ground and shall be provided with hinged
TR
12.4.6 Distribution boxes shall be weatherproofed in accordance with the minimum degree of
protection IP 54 in accordance with IEC 529.
12.4.7 Test posts and distribution boxes shall be accessible during all seasons and shall be designed
such that they are not prone to vandalism or damage.
12.4.8 Distribution boxes and test posts used for bonding of current carrying cables (including bonds
between pipelines/structures or across isolation joints) shall be located outside hazardous
areas. If this is not possible, a box approved for the relevant area classification shall be used.
12.4.9 The Contractor shall propose the type of test post and distribution box for each application in
the detail design.
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 36 of 43
13.0 DOCUMENTATION
13.1.1 The basic design documents shall be submitted for approval by the Owner, covering the
following requirements:
i. Results of any site surveys and soil investigations that have been carried out.
ii. Results of any current drainage tests that have been carried out for retrofitting on
existing pipelines.
y
nl
iv. Justification of the selected cathodic protection system and anode materials if the
O
choice is made by the Contractor.
se
v. Calculations of current requirement, pipeline attenuation, resistance and current
lU
output of groundbeds.
na
viii. A list of the estimated number and types of cathodic protection monitoring
-I
facilities.
AS
ix. Any sensitivities in the proposed cathodic protection system that requires
N
special attention.
O
x. Any other information that is regarded by the Contractor as essential for this stage
TR
13.1.2 The detailed design documents shall be submitted to the Owner for approval before
construction starts and shall cover the following requirements:
i. A schedule of materials.
13.2.1 To demonstrate that all materials to be procured are in accordance with this specification a
complete schedule of materials to be used for the installation of the cathodic protection
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 37 of 43
system shall be necessary. This schedule shall include the required quantities and grades of all
materials to construct the cathodic protection system and the proposed manufacturers and
suppliers.
13.2.2 The Contractor shall include in the material schedule a list of proposed monitoring
equipment required to carry out regular surveys of the cathodic protection system.
13.2.3 The Contractor shall also include a list of proposed tools and spare parts required for
maintenance of the system during the first 5 years of operation.
13.2.4 Colour coding for cables shall be as indicated on the requisition. The Owner shall indicate on
the datasheet if existing colour codes shall be followed.
y
nl
13.3.1 In ensuring that the system will be installed in accordance with this specification full
O
construction details and installation procedures of the cathodic protection system shall be
necessary.
se
lU
13.3.2 These shall include:
na
ii. A time schedule for the installation of the system, where required in relation to
-I
iii. Written procedures of all tests required to demonstrate the specified quality of
installation.
N
O
iv. All relevant construction drawings including but not limited to plot plans,
TR
locations of cathodic protection stations and test facilities, cable routing, single
line schematics, wiring diagrams, groundbed construction and civil works,
PE
v. Written procedures to ensure safe working practices during the installation and
operation of the cathodic protection system.
13.3.3 The installation of the cathodic protection system shall start only after approval of the
installation procedures by the Owner.
13.4.1 Commissioning procedures shall prove that the installed cathodic protection system is in
accordance with the design.
vii. A time schedule for the commissioning of the system, where applicable in
conjunction with the construction or commissioning schedule of the pipeline.
ix. Procedures for operation and maintenance of cathodic protection system (in
y
compliance with ASME B31.4 or B31.8 which ever relevant).
nl
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 39 of 43
14.0 SAFETY
The Contractor shall address in his design all safety related topics regarding the cathodic
protection systems and indicate, in the installation and operating documentation, procedures
to ensure safe working practices. The Contractor shall be familiar with local safety rules and
practices and implement these in his work.
y
nl
iv. Isolation flange protectors.
O
v. Hydrogen and chlorine evolution.
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 40 of 43
15.0 BIBLIOGRAPHY
y
BRITISH STANDARDS
nl
Methods of tests for soils for civil engineering purposes BS1377
O
Part 3 Chemical and electrochemical tests,
se
Part 9 In-situ tests
lU
Issued by:
na
W1A 2BS UK
nt
-I
Issued by:
TR
USA 77084-4906
INTERNATIONAL STANDARDS
Degrees of protection provided by enclosures (IP code) IEC 529
Semiconductor convertors IEC 146
Issued by:
Cental Office of the IEC,
3, Rue de Varembé,
CH 1211 Geneva 20,
Switzerland.
Preparation of steel substrates before application of paints and related ISO 8501-1
products; visual assessment of surface cleanliness
Issued by:
International Organisation for Standardisation,
1, Rue de Varembé,
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 41 of 43
y
nl
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 42 of 43
A specimen copy of sheet 1 of the data/datasheetsheet(s) is shown below. The latest revision
of this sheet (and its continuation sheet) shall be used and can be found in the Requisitioning
binder (PTS 00.11.03).
PROJECT NAME:
DATASHEET FOR DESIGN OF CATHODIC PROTECTION SYSTEM FOR ONSHORE
BURIED AND SHORE APPROACH PIPELINES PROJECT NO:
ORDER/ENQUIRY NO:
A PIPELINE DATA
1 Pipeline Name/Code:
2 Pipeline Route:
y
3 Product(s) Transported: Sour Service
nl
4 Years of Construction:
O
5 Design Life: years
se
6 Pipeline Length: m
7 Nominal Diameter: inches
lU
8 Pipeline Material
9 External Coating:
na
10 Backfill Type:
er
11 Route Characteristic:
12 Branch Lines (use separate datasheet for each branch lines):
nt
-I
13 Attached Drawings:
AS
6 Horizontal Vertical
7 Autopotential Required
Control:
8 Sacrificial Anode Material: Magnesium Zinc
9 Monitoring Facilities: Required By Contractor By Others
10 Temporary Protection: Required By Contractor By Others
11 Materials Schedule: Required By Contractor By Others
12 Installation Procedure: Required By Contractor By Others
13 Test/Commissioning Procedure: Required By Contractor By Others
14 Operating/Maintenance Manual: Required By Contractor
15 Colour Code for Cables: As specified below
16 CABLE COLOUR CABLE COLOUR
17 Positive feeder Negative drain
18 Test own Test foreign
19 Bond own Bond foreign
20 I.J. side line I.J. plant side
21 Carrier Casing
PTS 11.32.01
CATHODIC PROTECTION SYSTEMS FOR ONSHORE BURIED AND SHORE
June 2015
APPROACH PIPELINES
Page 43 of 43
22
In shaded boxes, use ‘Y’, ‘N’ or ‘Check Mark’ to indicate selection
y
Made by Date Equipment: Rev.
nl
letter
O
Checked by Date Plant: Date
se
Approved by Date Consignee: lU Sign
Sheet No 1 (cont.d on sheet No.)
Eng. by : Equipm. No.
na