Aux Boiler Commissioning

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

CJ Project

Activity Activity Name Remaining Start Finish Total Float Physical % January 2020 February 2020 March 2020 April 2020
ID Duration Complete
29 05 12 19 26 02 09 16 23 01 08 15 22 29 05 12 19 26
AUX BOILER 83 01-Jan-20 23-Mar-20 0 23-Mar-20,AUX BOILER

AUX BOILER 2 X 1000 MW 83 01-Jan-20 23-Mar-20 0 23-Mar-20,AUX BOILER 2 X 1000 MW

LEVEL 1 83 01-Jan-20 23-Mar-20 0 23-Mar-20, LEVEL 1


MILESTONES 83 01-Jan-20 23-Mar-20 0 23-Mar-20, MILESTONES
Works Commencement 0 01-Jan-20 0 0% Works Commencement
Works Completion 0 23-Mar-20 0 0% Works Completion
LEVEL 2 68 15-Jan-20 23-Mar-20 0 23-Mar-20, LEVEL 2
CONSTRUCTION 36 15-Jan-20 21-Feb-20 32 21-Feb-20, CONSTRUCTION
REMAINING MECHANICAL WORKS 32 15-Jan-20 16-Feb-20 36 16-Feb-20, REMAINING MECHANICAL WORKS
REMAINING PIPING WORKS 18 03-Feb-20 21-Feb-20 32 21-Feb-20, REMAINING PIPING WORKS
REMAINING ELECTRICAL & INSTRUMENTATION WORKS 21 30-Jan-20 20-Feb-20 33 20-Feb-20, REMAINING ELECTRICAL & INSTRUMENTATION WORKS
COMISSIONING 50 03-Feb-20 23-Mar-20 0 23-Mar-20, COMISSIONING
PRE - COMMISSIONING ACTIVITIES 16 03-Feb-20 18-Feb-20 34 18-Feb-20, PRE - COMMISSIONING ACTIVITIES
Utilities Supply for Auxiliary Boiler 16 03-Feb-20 18-Feb-20 34 18-Feb-20, Utilities Supply for Auxiliary Boiler
ECC/Punch List 3 10-Feb-20 13-Feb-20 38 13-Feb-20, ECC/Punch List
ECC/SRCC/Punch A Clearing 3 10-Feb-20 13-Feb-20 38 0% ECC/SRCC/Punch A Clearing
Fuel Oil Transfer System Commissioning 10Feb *LFO transfer system available date> 12 07-Feb-20 18-Feb-20 34 18-Feb-20, Fuel Oil Transfer System Commissioning 10Feb *LFO transfer system available date>
SA for LFO Line flushing (by air blow) 1 07-Feb-20 08-Feb-20 0 0% SA for LFO Line flushing (by air blow)
IA for LFO Line flushing (by air blow) 1 08-Feb-20 09-Feb-20 0 0% IA for LFO Line flushing (by air blow)
LFO Transfer System Flushing (by air blow). 6 08-Feb-20 14-Feb-20 0 0% LFO Transfer System Flushing (by air blow).
IA Line Flushing (by air blow). 6 08-Feb-20 14-Feb-20 0 0% IA Line Flushing (by air blow).
Reinstatement of piping and instrumentation 2 09-Feb-20 11-Feb-20 40 0% Reinstatement of piping and instrumentation
Pneumatic Control Valve Function Test 1 13-Feb-20 15-Feb-20 38 0% Pneumatic Control Valve Function Test
Reinstatement of LFO Transfer System piping and instrumentation 2 14-Feb-20 16-Feb-20 0 0% Reinstatement of LFO Transfer System piping and instrumentation
Reinstatement of IA piping and instrumentation 2 14-Feb-20 16-Feb-20 0 0% Reinstatement of IA piping and instrumentation
LFO Forwarding Pump - A/B Motor Solo-run 1 16-Feb-20 17-Feb-20 0 0% LFO Forwarding Pump - A/B Motor Solo-run
LFO Forwarding Pump - A/B Heat-run Test (*using minimum flow line) 1 17-Feb-20 18-Feb-20 0 0% LFO Forwarding Pump - A/B Heat-run Test (*using minimum flow line)
Instrument Air/Service Air for Auxiliary Boiler 7 07-Feb-20 14-Feb-20 2 14-Feb-20, InstrumentAir/Service Air forAuxiliary Boiler
Compressed-Air Generation Operation/Test & Dryer, Function Test, & Tuning <15Feb *Compressed
7 07-Feb-20
Air System Available
14-Feb-20
date> 2 0% Compressed-Air Generation Operation/Test & Dryer, Function Test, & Tuning <15Feb *Compressed Air System Available date>
IA/SA Receiver tank pressure relief valve Popping Test 3 09-Feb-20 12-Feb-20 2 0% IA/SA Receiver tank pressure relief valve Popping Test
SA for Auxiliar Boiler Line flushing 2 09-Feb-20 11-Feb-20 2 0% SA for Auxiliar Boiler Line flushing
IA for Auxiliary Boiler Line flushing 2 11-Feb-20 13-Feb-20 2 0% IA for Auxiliary Boiler Line flushing
Reinstatement of piping and instrumentation 1 13-Feb-20 14-Feb-20 2 0% Reinstatement of piping and instrumentation
Pneumatic Control Valve Function Test 2 14-Feb-20 16-Feb-20 2 16-Feb-20, Pneumatic Control Valve Function Test
Deaerator Steam Inlet 1 14-Feb-20 15-Feb-20 2 0% Deaerator Steam Inlet
Deaerator Water Inlet 1 14-Feb-20 15-Feb-20 2 0% Deaerator Water Inlet
Feed Water 1 15-Feb-20 16-Feb-20 2 0% Feed Water
Desuperheating Water 1 15-Feb-20 16-Feb-20 2 0% Desuperheating Water
Demin Water Supply 3 03-Feb-20 06-Feb-20 15 06-Feb-20, Demin Water Supply
Flushing of Demin Water Line from Main Line to Aux. Boiler 1 03-Feb-20 04-Feb-20 15 0% Flushing of Demin Water Line from Main Line to Aux. Boiler
Reinstatement of piping and instrumentation 2 04-Feb-20 06-Feb-20 15 0% Reinstatement of piping and instrumentation
Service Water Supply 2 03-Feb-20 05-Feb-20 21 05-Feb-20, Service Water Supply
Flushing of Service Water Line from Main Piping to Blowdown Tank 1 03-Feb-20 04-Feb-20 21 0% Flushing of Service Water Line from Main Piping to Blowdown Tank
Reinstatement of piping and instrumentation 1 04-Feb-20 05-Feb-20 21 0% Reinstatement of piping and instrumentation
COMMISSIONING ACTIVITIES 48 05-Feb-20 23-Mar-20 0 23-Mar-20, COMMISSIONING ACTIVITIES
Auxiliary Boiler System Cold Commissioning 30 05-Feb-20 05-Mar-20 18 05-Mar-20,Auxiliary Boiler System Cold Commissioning
Sequence System 2 16-Feb-20 18-Feb-20 2 18-Feb-20, Sequence System
Sequence check, Loop check 2 16-Feb-20 18-Feb-20 2 0% Sequence check, Loop check

Actual Work Near Critical Milestone Page 1 of 3 Data date: 01-Jan-20


Remaining Work Critical Remaining Work Summary
CJ Project
Activity Activity Name Remaining Start Finish Total Float Physical % January 2020 February 2020 March 2020 April 2020
ID Duration Complete
29 05 12 19 26 02 09 16 23 01 08 15 22 29 05 12 19 26
Air & Flue Gas system Commissioning 11 05-Feb-20 15-Feb-20 7 15-Feb-20,Air & Flue Gas system Commissioning
ECC/SRCC/Punch A Clearing 3 05-Feb-20 08-Feb-20 7 0% ECC/SRCC/Punch A Clearing
Forced Draft Fan Motor solo-run 2 08-Feb-20 10-Feb-20 7 0% Forced Draft Fan Motor solo-run
Forced Draft Fan Fan Heat-run Test 2 10-Feb-20 12-Feb-20 7 0% Forced Draft Fan Fan Heat-run Test
Draft adjustment 3 12-Feb-20 15-Feb-20 7 0% Draft adjustment
Feed Water System Commissioning 16 11-Feb-20 27-Feb-20 1 27-Feb-20, Feed Water System Commissioning
Water Flushing (by gravity) from Deaerator to BFP Suction Line 1 11-Feb-20 12-Feb-20 1 0% Water Flushing (by gravity) from Deaerator to BFP Suction Line
Reinstatement of piping and instrumentation 2 12-Feb-20 14-Feb-20 1 0% Reinstatement of piping and instrumentation
ECC/SRCC/Punch A Clearing 3 14-Feb-20 17-Feb-20 1 0% ECC/SRCC/Punch A Clearing
BFP Motor Solo-run 3 17-Feb-20 20-Feb-20 1 0% BFP Motor Solo-run
BFP Heat-run Test (*by minimum flow line) 1 21-Feb-20 22-Feb-20 1 0% BFP Heat-run Test (*by minimum flow line)
Boiler water filling & Water Flushing (*by gravity) 3 22-Feb-20 25-Feb-20 1 0% Boiler water filling & Water Flushing (*by gravity)
Boiler Water Level & Feed Water Control Function Test 2 25-Feb-20 27-Feb-20 1 0% Boiler Water Level & Feed Water Control Function Test
Blow down system Commissioning 5 21-Feb-20 26-Feb-20 2 26-Feb-20, Blow down system Commissioning
ECC/SRCC/Punch A Clearing 3 21-Feb-20 24-Feb-20 2 0% ECC/SRCC/Punch A Clearing
Quenching Water Supply Function Test (Service water) 1 24-Feb-20 25-Feb-20 2 0% Quenching Water Supply Function Test (Service water)
Water Drum Blowdown Valve Function Test 1 25-Feb-20 26-Feb-20 2 0% Water Drum Blowdown Valve Function Test
Chemical Dosing System Commissioning 11 11-Feb-20 22-Feb-20 6 22-Feb-20, Chemical Dosing System Commissioning
ECC/SRCC/Punch A Clearing 3 11-Feb-20 14-Feb-20 6 0% ECC/SRCC/Punch A Clearing
Chemical dosing pumps operation test (water test) 1 14-Feb-20 15-Feb-20 6 0% Chemical dosing pumps operation test (water test)
Chemical mixers operation test 1 15-Feb-20 16-Feb-20 6 0% Chemical mixers operation test
Chemical dosing line flushing (water) 3 16-Feb-20 19-Feb-20 6 0% Chemical dosing line flushing (water)
Chemical filling to each tank and dilution 2 19-Feb-20 22-Feb-20 6 0% Chemical filling to each tank and dilution
Sampling System Commissioning 5 29-Feb-20 05-Mar-20 18 05-Mar-20, Sampling System Commissioning
Sampling Line Flushing 2 29-Feb-20 02-Mar-20 18 0% Sampling Line Flushing
Sampling system commissioning 3 02-Mar-20 05-Mar-20 18 0% Sampling system commissioning
Burner System Commissioning 10 18-Feb-20 28-Feb-20 0 28-Feb-20, Burner System Commissioning
Burner each line flushing 2 18-Feb-20 20-Feb-20 0 0% Burner each line flushing
ECC/SRCC/Punch A Clearing 2 21-Feb-20 23-Feb-20 0 0% ECC/SRCC/Punch A Clearing
Pilot burner igniter spark test 2 23-Feb-20 25-Feb-20 0 0% Pilot burner igniter spark test
BMS Function check & adjustment 2 25-Feb-20 27-Feb-20 0 0% BMS Function check & adjustment
LFO filling (LFO Piping until Auxiliary Boiler Burner 1&2 ) 1 27-Feb-20 28-Feb-20 0 0% LFO filling (LFO Piping until Auxiliary Boiler Burner 1&2 )
Auxiliary Boiler Interlock Test / Hot Commissioning 24 28-Feb-20 23-Mar-20 0 23-Mar-20,Auxiliary Boiler Interlock Test / Hot Commissioning
Initial Firing 4 28-Feb-20 03-Mar-20 0 03-Mar-20, Initial Firing
Burner-1&2 Ignition Test 1 28-Feb-20 29-Feb-20 0 0% Burner-1&2 Ignition Test
Furnace Drying 3 29-Feb-20 03-Mar-20 0 0% Furnace Drying
Boiling out & Passivation 3 03-Mar-20 06-Mar-20 0 06-Mar-20, Boiling out & Passivation
Pressurize & Boiling & Passivation 2 03-Mar-20 05-Mar-20 0 0% Pressurize & Boiling & Passivation
Water blow - Rinsing - Water blow - Water filling (Treatment) 1 05-Mar-20 06-Mar-20 0 0% Water blow - Rinsing - Water blow - Water filling (Treatment)
Blowing Out 7 06-Mar-20 14-Mar-20 0 14-Mar-20, Blowing Out
Blow out from Auxiliary Boiler MS line to removable spool 3 06-Mar-20 10-Mar-20 0 0% Blow out from Auxiliary Boiler MS line to removable spool
Restoration 2 10-Mar-20 12-Mar-20 0 0% Restoration
Auxiliary Boiler Safety valve popping Test (Drum & MS) 2 12-Mar-20 14-Mar-20 0 0% Auxiliary Boiler Safety valve popping Test (Drum & MS)
Closed Loop Tuning 4 14-Mar-20 18-Mar-20 0 18-Mar-20, Closed Loop Tuning
Boiler operating parameters reading 2 14-Mar-20 16-Mar-20 0 0% Boiler operating parameters reading
Check and adjustment of control parameters 2 16-Mar-20 18-Mar-20 0 0% Check and adjustment of control parameters
Dynamic Test 3 18-Mar-20 21-Mar-20 0 21-Mar-20, Dynamic Test
Operation check for the Controls and fine tuning 2 18-Mar-20 20-Mar-20 0 0% Operation check for the Controls and fine tuning

Actual Work Near Critical Milestone Page 2 of 3 Data date: 01-Jan-20


Remaining Work Critical Remaining Work Summary
CJ Project
Activity Activity Name Remaining Start Finish Total Float Physical % January 2020 February 2020 March 2020 April 2020
ID Duration Complete
29 05 12 19 26 02 09 16 23 01 08 15 22 29 05 12 19 26
Check of controlled parameters stability during step-operation 1 20-Mar-20 21-Mar-20 0 0% Check of controlled parameters stability during step-operation
Performance Test 2 21-Mar-20 23-Mar-20 0 23-Mar-20, Performance Test
BMCR operation test 2 21-Mar-20 23-Mar-20 0 0% BMCR operation test

Actual Work Near Critical Milestone Page 3 of 3 Data date: 01-Jan-20


Remaining Work Critical Remaining Work Summary