Professional Documents
Culture Documents
Kuwait Oil Company (K.S.C.) : KOC Standard' General Specification For Civil Engineering and Building Works
Kuwait Oil Company (K.S.C.) : KOC Standard' General Specification For Civil Engineering and Building Works
Kuwait Oil Company (K.S.C.) : KOC Standard' General Specification For Civil Engineering and Building Works
-- STANDARDS PUBLICATION
1022
KOC STANDARD''381
( STANDARDS
KUWAIT OIL COMPANY (KrnSrnCrn)
This is to introduce the New Revision of the "General Specification for Civil
Engineering and Building Works. " .
The object of this General Specification is to establish standards for workmanship and
some material and to provide documentary guidance for personnel engaged in the execution
of typical ~ i v iEngineering
i building works carried out by the Kuwait Oil Company. The
specififation is to be read in Eonjunction with contract drawings, Particular Specifications and
other contract documents.
The requirements of this Specification shall apply for any work described in the
sections except where specific amendments provided in the Particular Specification are shown
on the drawings or the Superintendent issues a variation.
The word "Superintendent" has been used throughout this Specification only as an
abbreviation for the term "Superintendent's Representative", a title which is identified with
a company designation in other contract documents.
This is to inform all Departments concerned that effective 1st February, 1982, this
Specification will supercede the "General Specification for Civil and Building Works of May
1970H,and reference for any projects should refer to this Specification.
.-'ANYS E. RASHID
GEN. SUPDT. STANDARDS & INSPECTION DEPT.
GENERAL INDEX
1. EXCAVATOR
- - . . -_ . .,.
2. CONCRETOR- -
3. BRICKWORK
5. PLASTERER
6. CARPENTER
7. JOINER
8. IRONMONGER
9. ROOFER
.- .
lo. F L O O R - r n WALL TILER
12. GLAZIER
16. WELDER
KUWAIT OIL COMPANY (K.S.C.)
SECTION 1[
1.1 Profiles
1.2 Clearsite
1.3 ~xcavatiin~enera$y.. . .. -
SECTION !
EXCAVATOR
The Contractor shall provide and erect profiles, templates, sight rails and the like,
including supplying boning rods, and properly set out the proposed works from the
base lines, levels, co-ordinates or a datum given by the Superintendent.
The Contractor shall break up and.remove old concrete, brick or block foundations,
drains or manholes empty and clean old wells, cesspools, etc., found during the
process of excavation, seal up connections where required, remove all contaminated
earth and fill in voids with compacted material in accordance with this specification.
Excavation shall be to the lines and levels indicated on the drawings, or instructed by
the Superintendent. Where excavating works is carried out by machine, sufficient
depth will be left unexcavated to enable the exact depth required to be obtained by
hand excavating.
I
When vertical work against which concrete is to be placed without shuttering, is
* ---
carried-.--
out by machine, sufficient margin shall be allowed to make possible the
finishing of such faces by hand to the exact dimensions required.
-- l b
- -
1.4 APPROVALOF METWODS B ~ F O R ECOMMENCEMENT
Earthworks shall not commence until the Contractor has provided the Superintendent
with, and obtained his approval to, the methods of excavation, the means of support
to sides of excavation, the safety and support of neighbouring private and public
property, the system of dewatering, the demolition of existing surface and
underground structures and obstacles, moving of any existing services, pipes, culverts
and the like on the side or affecting the works.
1.5 BOTTOMS OF EXCAVATIONS
Bottoms of all excavations shall be graded true to level and will be inspected and
I
approved by the Superintendent before foundations or pipes are laid. The Contractor
shall notify the Superintendent in writing when formation levels are reached stating
the date and time that such formation is ready for inspection.
The Contractor shall take all necessary steps to protect any existing services, drains,
water and gas mains, power and telephone cables and the like endangered by'
excavations and/or slips and falls, and shall effect all necessary repairs at his own
expense. If any such utilities are encountered, the pipes, cables, etc., shall be
protected
- as shown on the relevant drawing, or as directed by the Superintendent. .
_ . --.. _ - . . .-
1.7 ~ E T Y PRECAUTIONS
The Contractor shall provide sufficient safety signs on and along the excavated areas,
all to the satisfaction of the Superintendent. Lamps with fluid fuel shall never be
used. Hard hat should be provided tdall the working people on any site, even for
visitors.
Trenching in residential or industrial areas shall not exceed 300M in length until pipe
or cable laying has begun.
Where other services are encountered, they shall be properly supported and protected
including reinstating disturbed work, covers or similar protection, upon completion
of the new work.
Continuous access for vehicular traffic shall be maintained at all truck and road
crossings by the provision and laying of temporary bridging and/or back filling
trenches as instructed by the Superintendent. I
The C.ontractor shall be responsible for the design, supply fixing and removal of all
pl&king, strutting, shoring and/of sheet piling required to support sides of
excavations, and all costs of the additional quantities of concrete foundations and
earth filling occasioned thereby. Where excavations are cut vertically and not
supported, they shall be backfilled as soon as practicable. Supportad, they shall be
backfilled as soon as practicable. Supports to sides of excavations shall be provided
wherever directed by the Superintendent.
Materials for supports to sides of excavation shall be furnished and driven or set in
place by the Contractor where necessary and wherever ordered by the Superintendent,
even if it is not considered necessary by the Contractor.
If in the opinion of the Superintendent, the material furnished by the Contractor is not
acceptable quality or of sufficient size and is not properly placed to ensure the safety
of the work or of the adjacent structures and property, the Contractor shall upon
notice from the Superintendent to that effect, provide shoring approved by the
Superintendent. If he shall fail or neglect to do so, the Superintendent may order all
or any part of the work to be stopped until such material is placed to his approval and
I
the costs of such stoppages shall be borne by the Contractor.
Trench excavations for all pipes (except stoneware drain pipes having a concrete bed
under) shall be taken down to extra depths and backfilled with fine sandy material and
consolidated to provide a continuous bearing under the pipe throughout the whole of
its length as follows: .
lSOmm diameter pipe: 75mm extra.
Explosives shall not be used to remove obstructions nor shall they be brought on to
site unless approved by the Superintendent in writing.
1.15 DEWATERING
Dewatering shall be carried out without interruption until the Superintendent directs
otherwise and standby equipment and maintenance staff shall be available to ensure
continuous working.
Prior to the commencement of excavations, the Contractor shall prepare and present
to the Superintendent detailed proposals for dewatering the site. The Contractor
shall, at his own cost, incorporate into such proposals any amendments required by
the Superintendent and the Contractor shall obtain the Superintendent's approval of
the system prior to the installation on site.
The dewatering system shall not be stopped until the completion of the foundation and
site services work and backfilling to same, or until such time as the weight of the
completed portion of the Works is sufficient to offset the uplift characteristics of the
water table as confirmed in writing by the Superintendent.
!
1.16 BTSPOSAL OF SURFACE WATER
The Contractor shall be responsible for the disposal of all surface water as it
accumulates on the site during the construction period until such time as, in the
opinion of the Superintendent, the permanent drainage system is complete the
Contractor shall provide all necessary drainage, manholes, soakaway etc., as directed
and approved by the Superintendent. .
1.17 FILLING AND BACKFILLING
-
--- -Th<-~onuactor shall notify the Superintendent of his intention to commenci -
backfilling operation prior to starting work on this item of the Works.
If, in the Superintendent's opinion, fill material is too dry, immediate steps shall be
taken to rectify the situation and no additional material shall be placed until the
compaction can be resumed and the suitable moisture content and densities can be
obtained. If the material is too wet, compaction work and placement of additional fill
shall be delayed until the material has dried to the extent that suitable moisture
content and densities may be attained.
I
A uniform moisture content shall be required throughout the layer for the particular
material involved and wetting or drying and manipulation of the material may be
required to accompkh &is -objective. During the progress of the work, the
Superintendent will inspect the material as to type, cbndftion, moisture content and
densities, and may direct the locason of its placement in the fill. The compaction of
each layer shall be completed both in width and longitudinal extent before the next
lift is started. The quality of material being placed shall not exceed the capacity of
the compaction equipment. The distribution of materials shall be such that the
compacted material will be free from lenses, pockets, streaks or other imperfections.
The Contractor shall be responsible for the stability of all fill carried out under the
Contract and shall replace any portion which, in the opinion of the Superintendent,
has become displaced.
1.18 STORAGE AND DISPOSAL OF EXCAVATED MATERIALS
The Superintendent will not allow excavated materials to be piled up along sides of
excavations in a number that will overload or increase danger of collapse of
excavation sides. Excavated materials shall be separated into those suitable for fill
and those unsuitable for fill, as directed by the Superintendent. Materials unsuitable
for fill shall, as soon as practicable, preferably immediately after excavation, be
removed from the site and legally disposed of. Materials suitable for fill shall,
subject to the provisions detailed under "Filing and Backfilling," be put to immediate
use or stockpiled for later use, at the option of the Contractor. Material obviqusly
in excess of that required for fdl and bacW111 shall be removed from the site and
legally disposed of to the approval of the Superintendent. In no event will the
Contractor be allowed extra payment for establishing temporary storage piles of
-
materials suitable for fill, or for any multiple handling involved in filling, backfilling
or-disposing of excavated from within the boundaries of the site, nor shall excavated ,
Where the Superintendent permits the Coritractor to obtain filling from borrow pits,
the following procedure shall be adopted:
I) The site of the borrow pit shall be stripped of all overburden. The
overburden and all material not suitable for filling shall be heaped well clear
of the borrow pit in the area indicated by the Superintendent.
11) On abandonment of the borrow pit by the Contractor the borrow pit shall be
backfilled with the over-burden and other suitable material and the pit graded
to the approval of the Superintendent. I
~ a i e r i a lfor filling over areas shall be approved, sandy ezirth, gatch or hardcore as
described on the drawings, or instricted by the Superintendent.
The material shall be deposited in layers not exceeding 150mm thick and well
compacted with hand or mechanical. rammers and watered.
The soil having a maximum density of 1600kgIcuM and below as determined by the
modified AASHTO T99 test shall Mf be used as filling materials unless mixed with
heavier soils to obtain densities above 1600kgIcu.M.
The loose top soil and non-compactable soft soil shall be removed and caited away
before starting and filling.
1.21 FILLING UNDER FLOORS
Only clean, inert, sandy material shall be used to make up levels under floors. Such
material shall be deposited in layers not exceeding 150mm thick and well compacted
1
with hand or mechanical rammers and watered. The use of "gatch" material is not
permitted.
The foundations and works up to ground level will be inspected and approved by the
Superintendent before back filling is started. They return filling around foundations
and walls shall be deposited in layers not exceeding 150mm thick and well compacted
with hand or mechanical rammers up to original ground level or as instructed by the
-
Superintendent.
FIL-LTNG
,
, IN -PIPETRENCHES
The filling shall be free from stones or other material which is liable to damage the
pipe or corrosion protection material around the pipe. Trenches shall be partially
backfilled over pipes leaving joints free for inspection during testing.
Backfill shall be completed after testing and shall be hand rammed to a depth of not
less than 450mm above crown of the pipe.
The remainder of the trench shall be filled by hand or machine, well compacted
150mm layers and finished to a height of 150mm above surrounding ground levels.
Pipes passing through a rock formation shall be encased in approved sandy. material
to a depth not less than 450mm above crown of pipe. I
All compacted fill and compaction in general will be under the continuous supervision
of the Superintendent. All mpactiowests will be performed by Contractor.
- -
KUWATT OIL COMPANY IKSC)
GENERAL SPECIFICATION
CONCRETOR
SECTION I1
INDEX
PAGE NO.
2.0 MATERIALS 1 -
2.1 CEMENT
2.1.1 TYPES OF PORTLAND CEMENT
2.+.2.
. .
AGGREGATES
..?
-
2.2 AGGREGATES
2.3 WATER
2.4 ADMIXTURE
2.5 BATCHING OF CONCRETE
MATERIALS
2.1 Cement
.
All cement shall be obtained from an approved source and comply with requirements of the
appropriate British Standard or ASTM. Normally, the cement used shall be ordinary Portland
Cement to BS 12, or ASTM C-150 of an approved brand name, or where particularly
-
s p H. i @ rapid hardening cement to BS 12 or ASTM C-150.
+
The cement shall he delivered to the Site(s) in the original sealed an? branded
bags and shall stored in a proper manner off the ground to prevent
deterioration. No cement shall be used which has been manufactured more
than twelve months prior to its proposed use on site.
- Cement shall not be stacked on a work site for more than one week within
two miles of the coast:
Cement shall be sampled and tested in accordance with ASTM C-150 so that
the results are known immediately prior to its use on site.
Both fine and coarse aggregates shall comply with the requirements of ASTM C33, or B.S.
882 (aggregate from natural sources for concrete.)
Aggregates shall be stored in bins of adequate size with a canopy cover and a floor of mass concrete
sloped to drain towards the adjacent ground.
Suitable divisions shall be provided to prevent the different types of aggregate from mixing.
All aggregates shall be tested for potential alkalilaggregate reactivity'in accordance with ASTM 289.
2.2.1- c
Coarse aggregates used in concrete mixes shall consist of crushed stone, gravel slag,
volcanic rock, or other approved inert material with similar characteristics or such
material having clean hard durable uncoated particles free from injurious substances
in such a form or in sufficient quantities to affect the strength, at any age, or the-
durability of the concrete, including where applicable, the resistance to corrosion of
the reinforcement.
The water absorption of each, size of coarse aggregate shall not exceed 2.5% by
weight.
The flakiness and elongation indick of the predominant size fractions in each coarse
aggregate determined in accordance with B.S. 812 shall not exceed 20% and 35% '
The total acid soluble sulphate content of coarse aggregates expressed as sulphur
trioxide shall not exceed 0.04% by weight. The total acid soluble chloride contents
of coarse aggregate expressed as sodium chloride shall not exceed 0.05% by weight.
2.2.2 Fine A m I
Fine aggregate for all types of concrete shall consist of sand or similar inert materials
(such as gravel, crushed stone, slag or volcanic rock), or combination thereof, having
- clean durable uncoated grains an2 frge from ir&ri&s amounts of dust, lumps,
gypsum, soft or flaky particles, shale, loam organic matter or other deleterious
substances in such a form, Br in sufficient quantity, to affect adversely the strength
at any age, or the durability of the concrete, including where applicable, the
resistance to corrosion of the reinforcement. The fine aggregate shall be
mechanically washed with fresh sweet water. Under no circumstance shall hand
washed sand, unwashed desert sand, or seashore sand be permitted to be used in the
works.
The aggregate shall not contain more than 3% by weight of clay or silt determined
in accordance with the test given in B.S. 882, for the amount of aggregate passing
a No. 200 B.S. 410 fine test sieve. Fine aggregate should contain not less than 15%
passing a No. 50 sieve and at least 4% passing a No. 100 sieve. These minimum
must be met to regulate the water gain and add to the cohesiveness of the mix.
Fine aggregate shall not be used for reinforced concrete if the salt content and the
aggregate expressed as chlorides exceeds 0.02 % .
(0 Coarse A I Z ~
Fine Aggregate
- -
2.3 WATER
I Water used in all types of concrete shall be clean and free from hjurious quantities of oil, acid,
alkali, organic or other deleterious substances and shall be fresh water as produced by the State
Distillation Plant.
Sea-water shall not be used for mixing or curing any type of concrete, plasters and mortars.
2.4 ADMIXTURES
1
Admixtures are added to the mixing water to improve workability, reduce segregation, accelerate
setting, on-trainlair, reduce shrinkage, or harden the concrete surface. The only approved additive
for use as an accelerator is calcium chloride. The amount used should be restricted to less than 2
percent by -weight of the cement in the mix. The amount required to retard-setting time is governed .
by temperature, humidity and wind. No additiveplasticisers or the w6r'kahility aients shall he used,
without the approval of the Superintendent.
2.5.1 Batchinv hv W e u
the cement and each size of aggregate shall be measured hy weight and added water shall
preferably be measured by weight rather than by volume. The weight batching plant used
shall be to the approval of the Superintendent and shall be kept in good condition whilst in
use on the works. Checks shall be made as required by the Superintendent to determine that
the weighing devices are registering correctly.
2.6 MTXTNG C O N C R m
Unless otherwise approved in writing by the Superintendent, all concrete shall be made in an
approved free-fall, tilting drum type concrete mixer which shall generally confirm with the design
data contained in BS 1305 (Batch type concrete mixers) and have an accurate water measuring device.
Mixing shall continue until there is uniform distribution of materials and the mass in uniform in
colour and consistency. The minimum time permitted for mixing one batch is 2 minutes in the mixer.
Excessive mixing shall not be permitted.
The amount of concrete mixed in any one batch is not to exceed the rated capacity of the mixer and
the whole of the batch shall be removed before materials for a freslibatch enter the drum.
TRANSPORTING CONCREn
A number of methods of transporting concrete are available, but in all cases the concrete must be
transported so that it does not segregate and so that it does not become contaminated with water or,
any other material after it has left the mixer.
Concrete shall be deposited as nearly as possible in its final position to avoid re-handling and shall
- . - ., - be immediately compacted.
- --.. - -. -
When concrete is conveyed by chutting, the plant shall be so designed that there will be a continuous
flow in the chute. The slope of the chute shall be such as to allow the concrete to flow without the
use of water and without the segregation of the materials. The delivery end of the chute shall be
close as possible to the point of deposit. the chute sh'all be thoroughly flushed with water before and
after each working period and the water used for this purpose shall be discharge outside the
formwork.
a. Pumping
b. Crane and Skip
c. Chute and
d. Dumper and Wheelbarrow.
" 'Befofe thEconcrete is placed in its final position, the insides of the forms should be inspecfed tu3WE '--"
sure they are clean and have been treated with release agent. Where the forms are deep, temporary
openings should be provided for this inspections. Rubbish, such as sawdust, shaving and wire, should
be blown out with compressed air. The concrete must be placed in its final position whilst it is still
workable and shall not subsequently be disturbed.
Where concrete is to be placed on or against ground it shall be placed immediately following the final
preparation of the formation.
Immediately prior to recommencement of concreting at a joint, the surface of the existing concrete
shall be free from laitance and shall be roughened so that the tips of the largest aggregate are exposed
but not disturbed.
Concrete shall be deposited as nearly as practicable in its final position to avoid rehandling. All
! placing and compacting shall be carried out under the direct supervision of a competent member of
the Contractor's staff.
No extra water shall be added to the mix after the concrete has left the mixer.
Care shall be taken to avoid the displacement or movement of formwork and damage to faces of
formwork.
Concrete shall not be placed by any method which causes segregation undesirable finish or defective
.
structural quality nor shall it be moved into position by rakes or vibrators. Chutes, skips, pumps
hoppers, etc., shall be kept free from coatings of hardened concrete and shall not be wetted during
use. --
- - 6.
Concrete shall be carefully rammed during placing to ensure full compaction and to produce a dense
and uniform mass. Approved power driven vibrators shall be used in all concreting operations.
and shall be used solely to compact concrete when it has been placed in its final position.
Vibrators shall not be used to spread or drive the concrete along forms, care muSt be taken
to ensure that damage does not occur to the form faces and that the rebar is not displaced.
Pokers must be withdrawn vertically and slowly to ensure that voids are not left in the
.. .:-* -
withdrawal zones. The poker type shall be inserted in the concraeat po&hn--approximately
-
30cm 6Ocm apart, shall remain in the concrete until wfien the concrete surrounding the
poker has become like a stiff jelly. ,-
The poker shall be inserted around the edges of the work as close to the shuttering as possible
without touching it.
External vibrators shall be securely clamped to the sides of the formwork and be maintained
at a constant depth of 45cm below the surface of the deposited concrete. Care shall be
exercised to prevent the appearance of laitance due to over vibration.
Surface or pan type vibrators shall be employed in the compaction of floors, slabs, etc. and
the whole area cast should he uniformly transversed in order that a homogenous surface
texture should he obtained without the appearance of laititnce.
I
2.92 Hand Com~actionWhen Authorised)
Concrete during and immediately after depositing, shall be thoroughly compacted by means
of suitable tools by rodding, tamping or slicing. Special care shall be taken to see that the
concrete is thoroughly worked next to formwork and reinforcing bars to enable a dense,
compact concrete free from honeycombing and blow holes to be obtained. In this walls, or
portions of the form which are difficult of access, the wncrete shall also be assisted into place
by tapping or hammering the form opposite the freshly deposited concrete.
.
2.10 EMBEDDED ITEMS
Concrete shall not be placed until provisions for housing conduits, pipes, sleeves, anchor bolts,
--- ..- . waterstois~ndother embedded items are positioned accurately, and supported
and approved by the Superintendent.
--
- .. against
- displacement
. r..
.
JOINTS
Where construction joints are shown on the drawings as requestd by the Superintendent, they .
shall be formed at right angles to the axis of the member concerned. The joints shall be
formed by the insertion of rigid stop forms with stud dowels or P.V.C. water-drops as
required and approved by the Superintendent.
Before new concrete is placed, the face of all construction joints shall have laitance removed
and shall have the coarse aggregate expose. It shall be left clean and dry. In no case shall
a thin layer of concrete be first placed in the bottom as slabs without the express permission
of the Superintendent. Where beams and slabs together forms an integral part of the structure
they shall be poured in one operation.
-- .. -
2.1 1.2 Expansion And Contraction Joints -
Expansion and Contraction joints shall be made as shown on the drawings or as instructed by
the Superintendent.
2.11.3 Joint Filler:
Joint fillers shall be a compressed sheet of wood fibre impregnated with bitumen emulsion
complying with ASTM D1751-73. The filler may alternatively be a compressed sheet of cork
granules bonded with bitumen or synthetic resin complying with ASTM Dl751 - 67.
The material should be rot-proof waterproof, non-absorbent and non-staining and shall not
extrude under pressure or the weight of poured concrete.
Prior to pointing, tbe joint shall be cleaned and the edge of the filler tamped down to ensure
that the joint is filled completely and continuous support is provided for the sealant.
2.11.4 Joint S e a l m
All sealants shall have good adhesion to the structure and shall not age, harden or become
brittle over a temperature range from -5°C to 60°C. The sealants shall not slump or flow
- after application is complete during seasonal contraction and expmsion of the joint of up to
-
. + or 12.5% of the joint width.' 'They silafl net stain or discolour'the adjacent concrete
surfaces and shall be formulated so that any toxic materials incorporated or generated during
curing will not migrate to the surfaces where they could be extracted when the sealant has
cured. General purpose sealants shdl be self-curing polysulphide rubber compound and shall
comply with B.S. 4254.
Concrete surfaces shall be finished free from honeycoming and excessing air holes, fines and
projections arising from defective mixing, placing and formwork, and shall, if necessary, be rubbed
with a fine carborundum stone. The finish shall be integral with the body of the concrete and shall
not be obtained by means of an applied rendering.
All exposed surfaces of concrete shall be finished fairface described as "finished air" shall be obtained
I
by the use of wrote formwork.
- _ -"- -_ -_ After
.
-- _- -.
striking formwork, the surface of the concrete shall he leti untouched until inspected by the
-
Superintendent. - - -
1 7-
Floor slabs and other flat work shall recgve a finish as specified on the drawings.
2.13 CURING CONCRETE
Curing of concrete shall be controlled during the period of time necessary for hydration of the cement
and proper hardening of the concrete to ensure that it has satisfactory durability and strength, the
minimum of distribution, is free from excessive efflorescence and does not cause, by its shrinkage,
, undue cracking in the structure. To achieve those objectives it may be necessary to insulate the
concrete so that it is maintained at a suitable temperature, or so that the rates of evaporation of
moisture from the surfaces are kept to appropriate values or both.
Concrete made with ordinary or sulphate resisting portland cement shall be cured for a minimum
period of 7 days.
The temperature of the concrete during curing is to be kept as uniform as possible and the concrete ,
is to be protected from rapid atmospheric temperature changes.
3. An impermeable sheet close enough to the surfaces to prevent an excessive circulation of air, ,
or
4, A membrane curing composing approved by the Superintendent and used in accordance with
the manufacturer's instructions.
Alternate wetting and drying shall be avoided especially in the form of cold water applied to warm
concrete surfaces. In order to avoid surfaces cracking cold water shall not be applied to' relatively
large members immediately atter striking the formwork while the concrete is still warm.
After initial curing, concrete protection is to be maintained to bring the curing period to a minimum
of 7 days u-ndetamtroW mperatures and in moist conditions. ..
2. IS CURING COMPOUNDS ..
Chemical curing compounds shall comply with ASTM C-309. They shall be applied by spray or
sprinkler as soon as the formwork is removed or as soon as the free surface water has disappeared
and shall not be sprayed onto dry concrete surfaces nor into concrete which has free water standing
on the surface. The curing membrane shall disintegrate and flake off from the concrete over a period
of days commencing a minimum of seven days after application. Storage, hauling and application
shall be strictly in accordance with the manufacturer's instructions. As membrane curing systems
compounds may affect the subsequent treatment or finish of the surface of the concrete, their use shall
be approved by the Superintendent before they are adopted. k
I 2.16 PROTECTION OF FOUNDATIONS
Foundations in soil with a total sulphate content of 1.0% or more, or where so instructed, shall be
I protected as foliows:
I The foundation shall be laid on heavy duty polythene sheeting which will be laid on a mixhum of
50mm thickness of blinding concrete or as shown on the drawings using cement to ASTM C150,
1 Type 5.
The sides of foundations in contact with soil shall be protected with two coats of "Synthaprufe" or
similar approved. The "Synthaprufe" will be applied to a clean, even surface at the rate of (5 litre
per) 11 sq. m. The second coat will be sand blinded, whilst still tacky. The minimum cover to all
reinforcement shall be SOrnm or as specified on the drawings. .
2.17 EPOXY RESIN BONDING AGENTS
Fresh comete can best be bonded to oil concrete by preparing the old concrete surface to remove - .
the surface-laitkceand ta expose the aggrqaik. The surface should wetted down the previous day
and yet be free from standing water when the new concrete is applied. A 'tack coat' of cementiwater
slurry may be brushed into the surface immediately prior to concreting, hut like epoxy coats, it must
still be tacky when the new concrete is placed against-it.
Concrete shall be protected to prevent damage from weather, plant overhauling or any other cause.
Before making good any damage, the Contractor shall obtain the Superintendent's approval of the
methods and materials proposed.
Concrete shall not be cut without the prior approval of the Superintendent.
I
2.19 SURFACE HARDENING
If concrete floor slabs are to be hardened or made resistant to soils, membrane curing agents must
not be h S K n e y must be applied according to the manufactursr's recommendations. -Liquia'- "-
hardeners_-areapplied with a brush or mop, and must never be sprayed-on fresh new concrete even
diluted with water.
GROUTING
2.20.1 Wide A m
For filling uncongested areas where the least clear dimension is greater than 50mm grout in
the mix proportion I :'k :lwr (cementlfine aggregatelcoarse aggregate by weight shall be used.)
The workability shall be measured by slump cone and shall lie between 50 and 100mm. The
waterlcement ratio shall be kept to a minimum that will produce a grout capahle of being worked into
the place to be filled.
For filling areas where the least clear dimension is less than 50mm grout in the mix
proportion 1:2 (cement/sand) by weight shall be used.
The waterlcement ratio shall be kept to a minimum that will produce a grout capable of being
worked into the place to be filled.
Grout shall be cured by covering with moist hessian for a period of seven days. .
2.21 PRY PACKING MORTAR
'
Dry packingis a mixture of one pan of portland cement and two parts of sand (1:2) mixed thoroughly .
with just enough water to produce a consistency such that when a sarnple is squeezed in the hand only
enough moisture will come to the surface to moisten the hand, dry packing is accomplished by
ramming the mixture into place until rings.
Dry packing shall be cured by covering with moist heSsian for a period of 7 days.
2.22 CONCRETE TRIAL BATCH=
Two methods are used to design a trial batch mix for laboratory testing. The older of these is the
volume mix. Quantities are measured with a shovel or container. It is roughly assumed that a 1:2:4
mix will give a 28 day breaking strength of 246 kg/cm2. A mix 1:2:4 by volume means that the mix
has 1 sack (0.0283 cu. meter) of cement mixed with 0.07 cu. meter of sand and 0.147 meter of
gravel. Water is added during mixing for the desired workability; from 5 % to 7% gallons per sack
of cement. The amount of moisture in the sand and gravel will determine the amount of water to use
with volume mixes. The coarser the aggregate, the less free water it will carry into the batch.
Design batches by weight is the modem method for making trial hatch designs. The data thus
obtained can-be passed on to the hatching plant operator, who also uses
- the weight method for mixing
in bulk. -
2.23 WATERICEMENT RATIO
The essential factor in making a series of trial batches is to maintain the water-cement ratio constant.
The aggregates contain moisture since they are stored without any protection from rains. Moist sand
contains approximately 8 gallon per cubic meter when very wet, 25 to 33 gallon of water per cubic
meter. The amount of mixing water must be reduced to allow for the aggregate moisture.
I
When internal high frequency vibrators (poker type) are to be used, the concrete mix should be drier
than when external shutter vibrators, mechanical or hand tamping methods are used.
\
2.24 TESTING
2aa!xaM
The consistency of a concrete batched mix is determined by the slump test in accordance with
ASTM C143 or BS 1881. This test should be made by Superintendent's Representative in '
the field by taking concrete sample from the truck spout or from the fresh concrete of 16
gauge steel and is 30.5cm in length. The larger open end is 20cm in diameter. Two handles
for lifting are placed on opposite sides lOcm from the top. In making a slump test, the ,
foookiag pr~cgdupsmust be-followed:
2. Fill the cone from the top by placing four layers of fresh concrete.
The tamping rod is a smooth 15mm diameter rod with a length of approximately
61cm. The end used for tamping is hemispherical in shape. The rod may be steel
3 kgm.
All tamping should be uniform. The bottom layer is rodded throughout its depth.
The two top layers are rodded with rod penetrating the layer.
I
Strike-off the top layer level or and add mix until the cone is full and level.
Lift the cone from mold of mix very carefully in a vertical direction, then place it
beside the mold just formed. - --
Place a straight edge across the top of the cone extending over the mold.
Measure the difference between the height of the cone and the molded concrete. This
measurement is taken to the highest point of the concrete.
The recommended slumps and maximum water-cement ratios for various types of construction
I
are given in the following table:
Testing shall include compressive tests of molded concrete cubes with slumps test for
consistency.
a. Supply steel 15cm square x 15cm high cube mould to the jobsite.
-
Compressive test cubes shall be prep'ked in sets of six cubes for each test. Specimens for
each set shall be obtained at the same time and from the same batch of concrete. A standard
slump test shall be made each time compression test cubes are taken.
Test cubes sets shall be dated and numbered consecutively. Each cube of each set shall also
be given an identifying letter (A,B, or C) and the following data shall be recorded at the time
the cubes are prepared.
The test cube shall be 15cm x 15cm high. The concrete shall be placed into the mold in 3
layers 5cm deep and each layer shall be compacted with at least 35 strokes of a 25rnm square
I
tamping bar.
All cubes must be immediately stored under wet sand or burlap for 16 to 24 hours after
preparation. The cubes shall then be removed from the molds.
Each cube shall be indelibly marked with the information in paragraph 2.24.3 then packed
in wet sand for shipment to K.O.C. testing laboratory. At no washed free of any salts with\
water suitable for drinking.
All water used in cube storage must be suitable for drinking. All sand used to protect cubes ,
b~st--bew a s h g e e of any sdts with water suitable for drinking. -
At least six cubes shall be made Q one time. Three of the six cubes are to be tested @ 28
days. The strength of the cubes must not fall below the minimum strength specified for each
type of concrete.
The minimum crushing strength of the work test cubes acceptable by the Superintendent shall
be as shown in the following table:
The results of all tests carried out shall be recorded and kept on site.
Concrete evaluation and acceptance be in accordance with ACI-318 Section 4.3 and ASTM
C94.
Any defective concrete work shall, at the discretion of the Superintendent, bk demolished
completely and rebuilt or cut and made good with fine concrete of the same proportions as
the original. Such rectification shall be to the satisfaction of the Superintendent and at the
Contractor's expense and no extension of contract period will be granted.
2.24.9 Cleaning Eauinmen~
All mixing machines, wheelbarrows, vessels, platforms, tools and implements used for
mixing, transporting or placing concrete shall be kept clean at all times.
' 2.24.10 Classes. Proportions and S t r m Requirements of Concreti
1:3:6
20mm agg.
1:2:4
40mm agg.
1:2:4
20mm agg.
1:2:4
lOmm agg.
1:11h:3
1 20- agg.
When floors are concreted during the months June to September inclusive, no expansion joints are
required. During the remainder of the year, an expansion joint 6.5m thick composed of approved
material, shall be constructed around the periphery of the floor. I
Floors are to be compacted as specified in clause 2.9 above and shall be brought to a slightly
corrugated surface by tamping with a timber screed or by the use of vibratory screed, or shall be
wooden floated before initial set has begun and finished off wlfh-a-sted m d d m u t one hou~-afit:
setting has commenced, to give a smooth-clean surface.
Patching of a concrete surface with mortar is strictly forbidden.
The Contractor shall obtain daily temperature forecasts from a source approved by the Superintendent
I
from 1st May to 30th September inclusive and concreting shall be accordingly.
When the shade air temperature is 37°C and rising, special precautions must be taken during all
concreting operations so that the temperature of concrete when placed does not exceed 35°C.
a. The water for concreting shall be cooled to a temperature between P C and 15°C. Where ice
is introduced to a mix this shall be taken into account in computing waterlcement ratios and
-
care shall be taken to ensure that all ice has melted before concrete leaves the mixer.
c. All formwork and reinforcement shall be cooled by sprinkling of water and they shall be
protected from direct sunshine.
d. Mixed concrete shall be used without delay. Wet concrete carrying vehicles shall not be
exposed to the hot sun for more than an absolute minimum of time.
e. Steps shall be taken to maintain the temperature of the concrete below 35°C until it has
hardened.
f. Concrete is not to be mixed and placed when the ambient temperature in the shade exceeds
43°C or during heavy sand storms or during heavy rains.
Notwithstanding the above requirements, no concreting will he allowed during the months !of May to
September inclusive between the hours of 9 a.m. and 3 p.m. except with the written permission of
the Superintendent. --
- -
The Contractor shall take account of this restriction when programming his concreting. If necessary,
he shall arrange to pour outside these hours but should note that no claim for overtime payment for
the so doing will be admitted by the Superintendent.
READYMiX CONCRETE
Ready-mixed concrete shall comply with the requirements of ASTM-C94 except where clauses are
directly over ridden by this Specification in which case the Contractor shall be made aware of such
differences.
I
Unless specifically authorised by the Superintendent, concrete shall be mixed and water added to the
mixer at the depot and no additional water shall be added at any stage from batching to placing.
Should the Contractor request dry batching he will have to satisfy the Superintendent.
The quality of the materials used, the methods of mixing, placing, compaction and curing the
concrete, reinforcement and framework described in this section shall equally apply to precast
-
...concrete work. All present units must-be completely uniform in colour and texture. Therefore, all- '
unik mud-be obtained from the same manufacturer who shall obtain all his materies from one source . ,
only.
The Contractor shall comply with the provisions of the following codes, specifications and standards,
except as otherwise shown or specified:
The Contractor shall comply with building code requirements which are more stringent than the
above.
The exposed surfaces of precast concrete units shall be in accordance the requirements of the
I
Architectural drawings and the specifications for finishes to formed and unformed surfaces.
Curing by low pressure steam, steam vapour, radiant heat and moisture, or other similar process may
be employed to accelerate concrete hardening and to rMuce the cu_ringtime.
..
Precast concrete units which do not conform to the specified requirements, including strength,
tolerances, and finishes shall be replaced with precast concrete units that meet the requirements of this
Specifications. The Contractor shall also be responsible for the cost of corrections to any other work
effected by or resulting from corrections to the precast concrete work.
The Contractor shall be responsible for the supply, design erection stability, striking and removal of
the formwork and centering so as to preserve the concrete from damage or distortion during setting.
The maximum permissible deflection of formwork under the load of wet concrete, workmen, plant
etc., shall be 2mm, or 11600 of the unsupported span whichever is the less.
The formwork shall be constructed of sound new timber andlor metal and shall include all temporary*
mould for forming the concrete to the required shape, together with all temporary constructions
required for the supports of such moulds. All concrete forms for sharp edges shall be chamfered and
- shall be filletted as directed, unless otherwise required by the Superintendent.
all corners
-
~rou~ht.'formwoik shall be constructed of sound new timber gaming and lir;sb with either l2mm
thick new plywood, with smooth face or other equal and approved lining suitable to obtain a smooth
fair face finish on the concrete.
The formwork shall be so constructed as to leave the finished work to the dimensions shown on the
drawings with the surface finish specified.
Concrete surfaces which are to be plastered may be shuttered with sawn formwork.
The formwork shall be of such quality and strength as will ensure complete rigidity during placing,
ramming vibration, setting and curing of the concrete.
The formwork shall be so constructed as to be removable without shock to the concrete. No portion
of the wood forms shall be left in the concrete. I
The formwork shall he so constructed as to prevent loss of any liquid from the concrete. Formwork
to concrete which is to be vibrated shall have all wedges naild. to ppygslipping or distortion.
To facilitate proper curing the formwork to beams shall be so constructed as to permit the removal
of the sides before the bottoms.
All exposed edges of concrete work without exception shall be finished with a 25mm x 25mm
I
chamfer neatly mitred at intersections, or as shown on the drawings.
The minimum periods that formwork and certering will be in position before striking will normally
be as follows:
Having regard for prevailing climatic conditions, these periods may be varied at the discretion of the
Superintendent. Such variations shall in no way relieve the Contractor of his responsibility or give
him the right to request extension of contract period.
All formwork must be carefully cleaned out before concrete is poured and any necessary temporary
opening must be left to facilitate cleaning.
I
All formwork shall be inspected and approved by the Superintendent before concrete is placed. Such
approval will not relieve the contractor of his responsibility for the safety and efficiency of the
formwork.
-
Prior to the striking of any formwork, the- Contractor shall obtain the Superintendent's approval.
Such approval will not relieve the Contractor of his responsibility in respect of the concrete work.
Before placing the concrete, the internal faces of formwork shall be retreated with mould oil. Care
shall be taken that the reinforcement does not become contaminate with the mould oil. Form-treating
materials that adhere to, or discolour concrete shall .not be used.
Permanent formwork shall he constructd of slabs or hlocks of precast concrete. cement sand
blockwork or brickwork. It shall have a positive anchorage to the structure and the joints made tight
with mortar or by such means as will prevent leakage of grout from the concrete.
2.30 REINFORCEMENT
1
Reinforcement may consist of round steel bars, deformed bars or welded mesh fabrics. Bar
reinforcement shall comply with the following British Standards and American Standards.
BS 4482- (Hard drawn mild steel wire for the reinforcement of concrete)
- ..
-- .*
BS 4483 *.- (Steel fabric for the reinforcement of concrete)
All reinforcement shall be free from oil, dirt, loqse rust, scale or other deleterious matter before
placing the concrete.
Bends in reinforcement bars shall be made cold in a bending machine of approved pattern with an
evenly applied force. The cutting and bending dimensions of reinforcement shall comply with BS
4466. Bars to be connected longitudinally shall be lapped and securely wired together. Plain bars
in tension shall be bent to a minimum radius of 2 diameters. Bars which cross or are connected shall
be securely wired together with 16 s.w.g. soft iron tying wire.
Fabric reinforcement where supplied in rolls shall be flattened out on a hard level surface before
laying. Fabric reinforcement shall be lapped a minimum of one complete mesh at all sides and two
complete meshes at the ends and the lapped portions securely wired t o g e ~ e r .Fabricreinforcement
shall b e B K No. 9 unless otherwise stated p the drawings.
Tying wire shall be either 1.6mm diameter black annealed mild steel wire or any other type to the
approval of the Superintendent.
Spacers to be used shall be to the approval of the Superintendent. They shall be of such materials
, and designs as will be durable not leading to corrosion of reinforcement and not causing spalling of
the concrete cover.
Spacer blocks made from cement, sand and small aggregate shall match the mix proportions of the
surrounding concrete so far as is practicable with a view to being compatible in strength, durability
and appearance.
Care shall be taken to prevent the reinforcement from being contaminated or becoming excessively
rusty. Reinforcement shall be stored in proper racks, clear of the ground and well supported.
.
All reinforcement shall be cut and bent to the length and shape shown on the drawings and placed in
the required-positions.
- - - -. U
Reinforcement which is left temporarily projecting from the concrete at construction or other joints
shall not be bent out of position without the approval of the Superintendent.
During placing of concrete, a responsible steel fixer shall remain in attendance to perform any
necessary adjustments or corrections to the reinforcement.
All reinforcements shall be inspected and approved by the Superintendent before concrete is placed.
Such approval shall not relieve the Contractor of his responsibility. I
Generally, the reinforcement shall comply accurately with the drawings as regards diameters, lengths,
placing and- cover.
-
~einforcimentshall he stored on site in suck a manner so as to provide easy identification of the
separate bars, to avoid distortion and to prevent contamination and corrosion.
l;(UWAIT OIL COMPANY N S C I
SECTION I11
BRICKWORK
PAGE NO,
1 . .,
3.2 CEMENT
3.3. SAND
LIME
WATER
CEMENT AND SAND BLOCKS
TESTING OF BLOCKS
SAND LIME BRICKS
CEMENT MORTAR
DAMP PROOF COURSE
WORKMANSHIP OF BLOCKWORK
WORKMANSHIP OF BRICKWORK -
- -
CAVITY WALLS
EXTERNAL FACINGS AND POINTING TO WALLS
EXPANSION JOINTS
WEDGE AND PIN UP
PUTLOG HOLES
ROUGH AND FAIR CUTTING
BED CILLS
BED AND POINT FRAMES
PAGE NO.
3.21 SUNDRIES 8
I 3.22 COVERING UP OR PROTECTING FACE .BRICKWORK
3.23 CLEANING OF BRICKWORK
3.24 GLASS BRICKS
3. BRICKWORK
Materials
Cement
Sand shall be clean, sharp and coarse grained to B.S. 882 latest editions, or
A.S.T.M. C144, chemically-~nd~ructurallystable and meihanically washed
and screened free from all impurities and shall comply with the following
table of grindings. Under no circumstances shall sea shore sand he used.
- Micron
25 600
52 300
100 150
ii.
..
R~drationof l a r g u u m l m
d
-- ..
- - The quicklime should be placed in10 a diumbr barxd.caaiaiaiag,ar ,. . 4
3.5 Water
3.6.1 Cement and sand ( 1 5 ) blocks shall be manufactured on site, press moulded
- in approved vibrating pressure machines. -
3.6.2 The blocks shall be hard, souniand square with well defined edges free from
any cracks flaws or other defects and shall be 20cm high unless otherwise
approved by the Superintendent.
3.6.3 Immediately after moulding, the bricks shall be placed on clean, level non-
absorbent pallet until inspected and approved by the Superintendent.
3.6.4 The blocks shall be cured by being kept thoroughly wet by means of fresh
water applied with sprinklers or other approved means for at least three days
1
or such other period as the Superintendent shall determine. Blocks shall be
stacked in honeycomb fashion after curing, and shall be kept a further twenty
four days before moving for use. Solid stacking shall not be permitted.
3.8.1 The bricks shall be class A sand lime bricks obtained from the National
Industries Co..
. ,
3.8.2 The Contractor shall be entirely responsible for the following:
1
3.9 Cement Mortar
3.9.1 Cement mortar for use with block work shall be cement and sand (1:4) mix.
3.9.2 Gauged mortar for use with sandlime brickwork shall be in strict accordance
with the following table:
i. -
Building mortar cementhand (1:4) mix.
.11.. Mortar pointing - cementlsand (1:3) mix. !
3.9.5 All mortar shall be used before the initial set commences and shall not be
- remixed after the initial set has taken place.
Damp proof course shall be a single layer of five ply tropical quality bitumenized
fibre felt damp proof course weighing not less than 3.25kglsq meter complying with
BS 743; latest edition, type 5B. The damp proof course shall be well lapped at
corners and joints and bedded in hot bitumen and pointed both sides in cement mortar
(1:4). Damp proof courses shall be provided even if not indicated on drawings.
3.11 Workmanshin of Blockwork
3.11.1 Blockwalls 25cm thick and under shall be built in stretcher bond. All other
thicknesses of blockwork shall be in tlemish hond.
3.1 1.2 Blockwork shall be built plumb and true to line and level to the following
tolerances:
3.11.3 All blockwork shall be set out and built to the dimensions shown on the
drawings. The blocks shall he laid and jointed in cement mortar with
perfectly level horizontal joints and walls plumhd perpendicular. Each
course shall he well fused up with mortar throughout its full length and width
and joints between courses lOmm thick. The courses shall be set out in
accordance with the detail drawings. Where the hlockwork is to be plastered,
horizontal joints shall be raked out lOmm deep to form a key. I
3.1 1.4 The blockwork shall be carried up evenly and at regular stages and no one
part shall be raised more than one metre above any other part at any time.
- Blockwork which is left at different levels shall be raked back.
3.11.5 Walls should be properlj..&xl by sprinkling water for a period of not less
than 3 days after completion of laying of the courses.
3.11.6 Where block walls are to be left exposed to form a finished surface, they
shall be built with blocks specially selected to ensure uniformity in size,
shape and appearance having clean, sharp arises and free from surface
blemishes.
3.12.1 Brickwalls 1lcm thick and under shall be built in stretcher bond. All other
thicknesses of brickworks shall be in flemish bond. The 1 lcm thickness of
bricks shall be the thickness of wall unless otherwise specified.
3.12.2 All brickwork shall be set out and built to the dimensions shown on the
drawings. The bricks shall be laid and jointed in gauged mortar with .
perfectly level and horizontal joints and all walls plumbed perpendicular.
Each course shall be well flushed up with mortar and with joints between
- courses 13mm thick. The courses shall he set out in accordance with the
- - .detail drawings. Where the brickwork is to .be- plastered,
. horizontal joints
shali be raked out lOmm deep to form a key. The j o i n t s ' i ~ f a c dbrickwork
shall be raked out lOmm deep as the work proceeds for pointing.
3.12.3 The Brickwork shall be carried up evenly and at regular stages and no one
part shall be raised more than one metre above any other part at any time.
Brickwork which is left at different levels shall be raked back.
3.12.4 Walls shall be properly cured by sprinkling water for a period of not less
than 3 days after completion of laying of the courses.
3.13.1 Generally, all external walls to buildings shall be built with cavity between
the inner and outer skins. The skins shall be securely tied together with
suitable butterfly twist type ties of No. 10 S.W.G. mild steel wire-zinc coatd
to comply with B.S. 1243 latest edition, spaced 900mm apart horizontally and
400mm apart vertically staggered. In cavity walls both thicknesses shall he
- carried up together and in no case shall one thickness-be carried up more
than about 40cm in advance of the other.
Additional ties shall he provided at reveals, quoins and openings.
The cavity shall be kept clear of extruded mortar and mortar droppings by
means approved by the Superintendent and shall be left clean at completion.
The brick skin of the cavities wall shall be returned across the cavity at all
reveals to jambs of openings. A vertical damp proof course shall be provided
between the brick return and the face of the block inner skin.
galvanised metal lath minimum 75mm wide shot fired to concrete one end .
and block work other end Q minimum 1250mm centres or as shown on the
drawings. .
Sample panels of sand-lime facing walling equal to ten square metres in area
are to be built using the materials, bond and jointing required in the
permaneht'work for .the,S,upqrintendent's approval. The accepted sample
shall be retained during construction as a standard for the permanent work.
The external walls shall be faced with approved, selected sandlime bricks. All
headers shall be whole bricks. The walls shall be pointed on completion with a
struck weather joint horizontally and flush pointed vertically in cement and sand (1:3)
mortar tinted to the approval of the Superintendent.
Expansion Joints
Expansion joints between concrete and brickwork in positions shown on the drawings
are to be 20mm thick and are to be filled with FLEXCELL bitumen impregnated
fibre board filler. Vertical joints are rebated within the thickness of the wall. 1
Wedee and Pin up
The Contractor shall leave temporarily open joints immediately under structural
members. These open joints shall be left to allow the structural members to take up
their full deflection and the open joints shall be wedged and pinned up after the
structural members have been fully loaded and before the'completion of the works.
Putloe Holes
Putlog holes shall be stopped up and finished to match the mortar and bricks.
l&%Ulls
- .,
-.-Cill'sshall bt: bedded in cement mortar and poiiitd. -.
Frames shall be bedded solid in cement mortar and exposed edges flush pointed with
an approved mastic. Fixing cramps shall be built-in as the work proceeds.
The Contractor shall execute and make good all necessary chases, holes mortices,
rebates and the like, built in lintels, cills, timbers, etc., as required and perform all
necessary attendance upon other trades and make good on completion.
The Contractor shall be responsible for covering up and protecting the face brickwork
during the progress of the work.
- -
-- cleaninn of Brickwork
the Contractor shall carefully clean down the whole of the face brickwork at
completion, make good and point up and leave all perfect.
3.24 Glass Bricks
Glass bricks will be on a position as shown on the drawings. The type to be used
will be P.B. 32 size 200 x 200 x 100mm,or 200 x 200 x 200mm or as shown on the
drawings.
Every course is to be reinforced with expanded metal and where these walls are
flanked by brickwork, the expanded metal strips will be carried into the brickwork.
The mortar to be used is to be 1 (one) part white cement 1 (one) part hydrated lime
and 4 (four) parts sand by volume. The mix must be fairly dry and fatty, and the.
sand must be clean and free from gravel and silt. The pointing is to be carried out '
by making the joint back slightly as the work proceeds. -
Clearance joints of 12.7mm are to be provided at all panels in the top and sides.
These are to be filled with fibre glass and pointed with a non-hardening compound.
KUWAIT OIL COMPANY (KSC)
SECTION 1V
4. GENERAL
4.1 MATERIALS
4.2. WORKMANSHIP
4.3 SEPTIC TANKS
4.4 SOAKAWAYS
4.5 WORKMANSHIP EXECUTION
4.6 CLEAN DRAINS
4.7 TESTING
KUWAIT OIL COMPANY (KSC)
GENERAL SPECIFICATIONS
SECTION IV
4. GENERAL .
All sewage drainage works shall comply fully with all By-Laws which may be
enforced and issued by the Drainage Division of Ministry of Public Works or
British Standad Code of Practice CP 301.
.. .: -.. _-7 . s
.
4.1.5 Pitch impregnated Fibre Pipes & Fittings shall comply with the
requirements of BS 2760 Part 1 (Pitch impregnated fibre pipes
and fittings for-drainage below and above ground (Fittings).
Pipe fittings shall be made from pitch asbestos fibre or
polypropylene.
4.1.6 Balloon Gratings:
Under Ground
The excavation work for the drainage and sewage system shall confirm
to the requirements in Section 1 "Excavator" of this specification,
except that no trench shall be backfilled until the drain run therein has
been tested and passed.
4.2.2 Beddings
-- All ground floor and outside drainage shall be laid on 150mm thick
- -- --I - b f concrete of the width shown on the drawings or described in the - - ---.'
When pipes cover is 90cm or less vitrified clay pipes shall be bedded
on and surrounded with 150mmm of concrete (1:3:6). When pipes
pass under roads and cover is 120cm or less cast iron pipes shall be
bedded on and surrounded with ISOmm of concrete (1:3:6). Where
cover exceeds 90cm under roads, the pipes shall be bedded on a
granular bedding as directed by the Superintended.
Every line of drains shall be accurately laid and true to line ahd
gradients from point to point. Every main drain shall be true to line
from manhole and any change in direction shall take place inside the
- manhole by the use of curved mimhanntls~Changein the diameters
-- - of drains shall be made in-manholes by the uie of tapered channels,
straight or curved, as nessary.
Joints in salt glazed stoneware pipes are to be carefully made by
pressing turns of tarred yarn into the socket to ensure concentricity.
The socket is then to be completely filled with mortar (1 part cement,
2 parts sand and 2% approved integral water proofer and a fillet
formed round the joint with trowel forming an angle of 45°C with
barrel of the pipe.
Mortar for jointing must be mixed only as wanted for immediate use.
Nor mortar shall be beaten up and used after it has begun to set. After
the joint is made any extraneous materials shall be removed from the
inside of the joint with a suitable scraper.
.
4.2.4 b v i n e and J
.o .~ n t i w
Impreenated Fibre,P i ~ e s
- - Prior to laying the pipes alignment pegs shall be driven in line down
. the lengthbf-.tl?t-run& 4.5M intervals, offset from the center of the
line by half the external diameter of the pipes to be laid. The pipe
shall be laid against these pegs. A back-stop of wedge shaped timber
shall be used at the start of the line and firmly fixed in position.
The first pipe with coupling attached to both ends shall be placed
against the back step. A further pipe with a coupling @ the outer end
only is then entered into the coupling of the first pipe. A dolly
consisting of a piece of timber 300mm x 300 x 20mm shall be placed
in front of the third coupling and the joint driven home. As laying
continues a peg shall be driven next to the pipe opposite each
alignment peg described above to retain the pipes position.
4.2.6 Manholes
4.4.2 Circular ring beams for soakaways pits and cover slab to same
shall be of reinforced concrete with 1:2:4 mix and formwork
to be used for soffits of cover slabs shall be wrought. Top of
cover slabs shall be trowelled smooth.
I
4.5 WORKMANSHIP EXECUTION
The Contractor shall remove all silt and foreign matter from drains and
manholes and leave the whole system in a clean, workable condition
approved by Superintendent.
4.7 TESTING
All drains, sewers and manholes shall be tested with water under a
minimum of 1.8 meter head and not more than 2.4 meter @ the
highest point of the section under test. All soil and vent pipes shall be
tested with smoke. All pipes shall be tested for water - tightness up
to the level of the rendering only by filling with water.
Drains shall be tested not less than 48 hours after laying and jointing
but before the concrete casting (where required) and the filling-in are .
done. Connection shall be fixed temporarily to obtain the requisite
head for the test. .
Any leaking joints or defective pipes shall be cut out and replaced and
-- the test .re-applied
. until satisfactory results are obtained.
-.. - -- - -
Leaks in manholes sides shall be stopped by cutting out rendering,
making good, repointing or rendering external faces.
The contractor shall provide all labour and apparatus for carrying out
the tests. In case of any default or leakage the contractor is to repair
this at his own expense as directed by the Superintendent, and the test
repeated until approved by the Superintendent in writing.
PLASTERER
INDEX
PAGENO. ,
5.0 GENERAL
5.1 MATERIALS
5.1.1 PORTLAND CEMENT
- 5 . i ~-SAND- -.
5.1.3 WATER
5.1.4 HYDRATED LIME
5.1.5 GYPSUM
5.1.6 METAL LATH
5.1.7 CORNER LATH
5.1.8 STRIP LATH
5.1.9 TIE WIRES
5.1.10 WIRE CLIPS
5.2.1 MIXING
5.2.2 PREPARATION
5.3 CLASSES OF PLASTER WORK
5.3.1 CLASS "A" PLASTER
5.3.2 CLASS "B" PLASTER
5.3.3 ROUGH CAST
5.3.4 PEBBLE DASHING
5.3.5 MACHINE APPLIED TEXTURE FINISHES
PAGE NO.
5.4 APPLICATION
5.4.1 UNDERCOAT
5.4.2 FINISH COAT
5.4.3 CURING
5.5 METAL LATH APPLICATION
5.5.1 LATHING TO GENERAL AREAS
5.5.2 CORNER LATH
5.5.3 STRIP LATH
. . .- 5 5 4 METAL CORNER BEADS AND METAL EDGE BEADS 9 .i
. --. - -- --
5 3.5 METAL'CONTROL JOINTS 9 .(
5.6 SUNDRIES 9
KUWAIT OIL COMPANY (KSC)
SECTION V
Table 5.1.2.A
5.1.3 Water
5.1.7 Comer
Shall be diamond mesh metal lath as specified above for metal lath
bent to form two 75mm wide wings.
Wire C l i a
Metal A n ~ l eBeading
-- - . - -.
mi
shall be suitable for two or three coatssworksas~sp.oCified, 1
shall be of 26 U.S. Standard, gauge (455mm), galvanized steel
for interior work, zinc for exterior work, with 4.8mm bead
maximum and expanded metal wings not less than 63mm wide.
5.2.1 Mixing
5.2.2 Preparation
--
- ' class "A" plaster shall be a retarded lime -hydrate-gy?sum
plaster and used internally for walls and ceilings on solid or
metal lathing backgrounds.
Type Coats
- '1
B 2 1 3 0.25 the 1 3
amount
of the
cement
by
volume
Class "B" Plaster shall be a cement and sand mix and used
internally for walls on solid or metal lathing backgrounds and
externally for walls and soffits on solid backgrounds. The first .
coat shall be well scratched to form a key for the second coat.
When the first coat has thoroughly dried the finishing coat may .
be applied after dampening the first coat by brushing or
spraying with water taking care to avoid excessive water.
-- Finish coat shall be approximately 3mm thick, well trowelled
- with a steel trowel -and filled.oou~toa true, even surface. The
hnish shall be allowed to dry a few minutes before well
trowelled with a steel trowel and water to produce a hard,
smooth finish.
5.4.1 Undercoat
Dampen undercoat evenly with fog spray just before finish coat
application and float finish coat 3mm thick minimum to a uniform sand
-
.-
- texture or steel trowel to a smooth, hard finish:. W2tg.qure.finish coat .,
stadng 1 2 hours after completion of application by fog spraying
lightly and then continue fog spraying for 36 hours. Thereafter,
protect against rapid drying until thoroughly cured.
5.4.3 Curing
Each full coat of plaster shall be properly cured with fresh sweet water
and kept damp by spraying with water for three days and then allowed
to completely dry out before the application of the subsequent coat.
Special care shall be taken to ensure that each layer of the work is
protected from hot sun and drying winds to prevent too rapid dry out.
I
5.5 METAL LATH APPLICATION
5.5.1
- h t h i n g to General Areas
-- - . --
Metal lath shall only be fixe'd after all services which are to be covered
by lathing have been installed and approved by Superintendent.
- - Diamond mesh and self-firring lath shall be bent into internal comers
-.- - and lapped 150mm onto adwinglath. Alternatively, lath may be butt
jointed in internal comers and comer applied "over-abwtting9attrs.
20mm rib lath shall be butt jointed at intervals corners and comer lath
applied over abutting laths.
The Contractor shall fix comer lath at all interval comers of surfaces
to be plastered, except as permitted otherwise above. The comer lath
shall be secured along with edges only at 3001nm maximum centres
with galvanized masonry nails.
The Contractor shall fix 150mm wide strip lath over cracks in masonry
- and concrete walls, and over-joirta~etwee~dissimilar backing surfaces
- - which are to be plastered- The Contractor sfiall'fix 300 x 600mm.
Strip lath set diagonally at 45 degrees. The Contractor shall secure
strip lath along outer edges only at 300mm maximum centres with
galvanized masonry nails.
5.5.4 Metal Comer Beads and Metal Edge Beads
5.6 SUMDRIES
The Contractor shall provide framing and cut and fit lath around openings and
penetrations, such as outlet boxes, piping conduits, ducts, fittings and the like
in or through all plaster work to accommodate the work of other trades.
5.7 COMPLETION AND PROTECTION
Two coat plastering shall be brought to a fair line by fixing grounds and
linings to a true plumb line. The plastered finished surface shall not show any
deviation for more than 3mm from 1.8M straight edge placed against it.
The plaster, whether finished with a wood float or steel trowel, shall be free
from blemishes resulting from the failure to close in slight depressions during
working of the coat.
KUWAIT OIL COMPANY (KSC)
SECTION VI
CARPENTER
PAGE NO.
-
6.0 INTRODUCTION DESCRIPTIC~N- . - ' -
6.1 MATERIALS
6.1.1 NOMENCLATURE OF TIMBER
6.1.2 TIMBER FOR TEMPORARY WORKS
6.1.3 FIBERBOARD
6.1.4 HARDBOARD
6.1.5 HARDWOOD
6.1.6 TEAKWOOD
6.1.7 PLYWOOD
6.1.8 BLOCKBOARD
6.1.9 PLASTIC SHEETING
-
- 6. I. 10 COMPOSITION - WARD
..-
6.1.11 FIXINGS
6.2 WORKMANSHIP
6.2.1 CARPENTER
KUWAIT OIL COMPANY (KSC)
I SECTION VI
CARPENTER
Carpenter's work shall include all structural and temporary timber work and 1
shall be carried out as shown on the drawings and in accordance with the
principles of good construction. All sizes shown on the drawings shall be
ficished
- sizes.
- -.. _-. - -
~ 1 timber=
1 shall be the best of its kind, perfectly dry, thoroughly well
seasoned and sawn die square. All timber shall be free from sap, splits,
shakes, soft pith, cracks, wavey edges, checks exceeding 300mm long, 1'Amm
wide or exceeding in depth one half of the timber thickness, knots exceeding
30mm mean diameter or exceeding one half of the width of the surface,
decayed, loose or dead knots or knot holes unless cut and plugged, pitch
pockets, decay and insect attack.
6.1 MATERIAL
Fiberboard shall comply with BS 1142: latest edition (Insulating board type).
I 6.1.4 Hardboard
6.1.5 Hardwood
Hardwood carpentry shall be carried out using Ahmar, Faini, Zan, ~bulhaz
or Montaig or other hardwood approved by the Superintendent. .
--
-. Teak shill. be of good quality and-from Siam or Burma or equally approved. '
.:
..
6.1.10 ComposltIon - Board
6.1.11 Fixings
Workmanship shall comply with B.S. 1186 Part 11. All architectural
woodwork shall be accurately set out, cut and framed at an early stage, but
shall not be glued or wedged until the building is ready to receive it. All
timber shall be treated with anti-termite solution, as described in Painter
section in this Specification, or one coat of Solignum or other equal and
approved wood preservative.
6.2.1 Caroenter
6.2.1.2 Jointing
6.2.1.3 Frames
Every post, plate, stud, beam, binder, joist, rail, rafter
and purlin, shall extend in one piece between its
supports or fixings, or shall otherwise be joined in an
approved manner to ensure the necessary structural
stability.
KUWAIT OIL COMPANY (KSC)
SECTION VII
INDEX .
PAGE NO,
7,0 - G~$%ML- - 1
7.1 DIMENSIONS 1
7.2 EXPOSED SURFACES 1
7.3 NATURAL FINISH 1
7.4 SHRINKAGE AND TOLERANCE 1
7.5 WORKMANSHIP 2
7.6 SCRIBING 2
7.7 FINISHING 2
7.8 DOORS 3
7.9 WINDOWS AND SASHES 3 '
7.10 HATCHES AND SHUTTERS 3
- 3
.--.
7.1 f FLYSCREENS
7:12 JOINERY COMPONENTS-- 3
7.12.1 DOOR FRAMES AND LININGS 4
7.12.2 JOINERY FITI'INGS 4
7.12.3 ARCHITRAVES 4
7.12.4 SKIRTINGS 5
7.12.5 PLUGGING NAILS AND SCREWS 5
I .
KUWAIT OIL COMPANY (KSC)
SECTION VII
JOINER
Joiner's work shall include all finishing and non-structural timber work and .
shall be carried out in accordance with the particular Specification, the
principles of good joinery and to the satisfaction of the Superintendent.
The arrangements jointing and fixing of all joinery work shall be such
that shrinkage in any part, and in any direction, shall not impair the
strength and appearance of the finished work and shall not cause
damage to continuous materials or structures.
I
Reasonable tolerance shall be provided at all connections between
joining works and the building carcass so that any irregularities
settlements or other movements shall be adequately compensated.
7.5 WORKMANSHTP
Where joints are not specifically indicated they shall be the recognised
form of joints for each position. .
All glued joints shall be cross tongued or otherwise reinforced.
All joinery shall be cut and framed at any early stage but shall not -
'
-
finally assembled, glued or wedged until the building is ready to
receive it.
All screws for fixing joinery shall be brass screws in accordance with
BS 1210: latest edition.
The use of nails for fixing any item of joinery shall not be permitted.
Springs may be used for glazing beads only.
I
SCRIBING
Windows and fanlight sashes shall be framed to the sizes shown on the
drawings. Sashes hung folding shall have meeting beads screwed on
glazing bars if required shall be of twice rebated section.
FLYSCREENS
- .. --
Flyscreen to doors shall be framed and braced with rails stiles and
braces and filled in with appioved copper or galvanized steel fine wire
mesh of 0.70mm beaded on.
Flyscreens to windows shall be framed with rails and stiles and filled
in with approved copper or galvanized steel fine wire mesh of O.42mm
beaded on.
7.12 JOINERY COMPONENTS
Frames shall be built into walls and each leg secured with a
6.35 mm diameter conosion resistant dowels let in to concrete
floor and three hold fasts. Each hold fast shall be of corrosion
resistarit metal plate size 220 x 30 x 5mm thick once bent, one
end twice screwed to leg of frame and the other-end bhded in
wall.
J o i n e ~Fittinu
Architraves
SECTION VIII
IRONMONGER
INDEX
PAGE NO,
8.0
- MATERIAL
8.1 -.,@ORKMANSHIP
8.2 PROTECTION
8.3 SAMPLES
KUWAIT OIL COMPANY (KSC)
SECTION VIIE
JRONMONGER
8.0 MATERIAL
All ironmongery such as hanging and locking devices, stays, closing and
check mechanism for doors and windows, door and window furniture, bolts
.
and catches, finger and kicking plates, remote control gear for windows and
ventilation and the like shall, unless otherwise stated on the drawings or
iranmongery schedule, be of-equivalentstyle and quality normally used by the .,
Company; The ironmongery-sEdl besupplied -with%properscrews or other 4
All screws used for fixing ironmongery shall be of the correct type, material,
finish, size and shape for the item. The use of nails for fixing ironmongery
will not be permitted.
8.1 WORKMANSHIP
8.1.1 On completion all locks, catches and similar items of ironmongery
shall be properly cleaned oiled, tested and adjusted and left in a sound
working order.
8.1.2 All keys shall be provided in duplicate and clearly labelled with m e h
or hardboard tags size approximately 5Omm x 20mm securely fixed to
the keys and handed to the Superintendent.
- - I -_ .
"'d
8.1:3 All fittings shall be removed before the cotnmencement of painting
operations and shall be re-fixed after all painting works are completed
and approved by the Superintendent.
8.2 PROTECTION
8.2.1 All ironmongery shall be individually wrapped and protected in such
a manner that no marking or damage to the finish will be incurred.
8.2.2 All ironmongery shall, at all times, be stored in a clean, dry and safe
place.
8.3 SAMPLES
The Contractor shall submit samples of every different item of ironmongery
to the Superintendent for approval of quality design and finish. .
KUWAIT OIL COMPANY (KSC)
SECTION IX
ROOFER
JNDEX
PAGE NO,
.
9.1 GENERAL 1
9.2 MATERIAL 1
ASBESTOS CEMENT: SHEETS - 1
GALVANIZED SHEETS 1
CORRUGATED ALUMINIUM ROOF 2
PLASTIC CORRUGATED ROOFING 2
FLAT ROOF 2
LIGHTWEIGHT CONCRETE 2
9.2.6.1 LIGHTWEIGHT CONCRETE SCREED 2
9.2.6.2 PLACING 3
VERMICULITE SCREED 3
TILES 6 I
EXPANSION JOINTS 6
9.2.9.1 ASBESTOS CEMENT SHEET 6 * - - -
9.4.1 LAYING
9.4.2 FIXING
I SECTION IX
ROOFER
9.1 GENERAL
On completion, all roofs are to be left sound and water-tight and in a neat and
clean condition before handing over. All roof finishes shall be carefully '
I
9.2 TERIAL . .
.- . . ._
. --.- -..* -- ..
..
9.2.2 Galvanized Sheets '
-
GRADING DETATLS VERMI CULlTE
Gauge boxes shall be used for the measurement of vermiculite and the
following mixing table shall be strictly observed:
Vermiculite - m3
Nominal Cement kg. Water
- Mix -Grade-l$.- ,Grade
- .ti Litres
Mixing shall be carried out by approved machine. The machine used
shall be counter-current rotating paddle type mixes operating at the
speed recommended by the manufacturer. The water shall be placed
in the mixer followed by the vermiculite and mixing shall be carried
out until the water has been distributed amongst the vermiculite. The
cement shall take place until all the materials are uniformly distributed.
Alternatively, the cement and sand under topping may, with the
approval of the Superintendent be applied immediately after trowelling
the vermiculite screed and cured with it.
If roofing felt is to be laid on, the surface of the topping shall be
finished flat and true.
The screeds and topping shall be allowed to dry out thoroughly before
subsequent roofing operations are camed out. .
Vermiculite screeds and cement and sand topping layers shall not be
laid during rain.
-
9.2.9 Expansion Joints
- ... . ..-..
-.
- . -, . , . .-- .
9.2:g.l ' Asbestos Cement Sheets
The felt shall be carried up to walls, etc., over fillets and walls
and shall be not less than 15cm in vertical height. The felt
shall be dressed and bonded into rain-water outlets and under
flashings.
9.3.1 General
9.3.2.1 uh
The profiles normally used are 7.5cm standard sheet or
15cm sheet.
-- -.
. &,% - --. - - > + -- The sh'ixts shall be laid with an end lap of not less than
15cm and side lap of half a corrugation 7cm for 15cm
sheets and one and a half (1%) corrugations 11Scm for
7.5cm standard sheets.
The sheets shall be laid witti'an end lap of not less than l5cm and a side lap
of one cormgation 7.5cm and with corrugation end and side laps on straight
lines.
At abutments, the sheets shall be cut as necessary and finished with a rising
edge.
All fixing holes can be drilled or punched from the internal side of the sheet.
Capping shall be fixed along ridges together with finials-sideof the! sheet.
9.4.2 Fixing
No hook bolt or screws shall be nearer than 4cm to the end of a sheet.
All bolts and screws shall be fitted with a galvanized sheet curved
-diamond
- - -, shapd washer 'and asbestos felt under washer except for .
Sheets shall be secured at eaves, ridge and through ends, and laps and
intermediate purlins at 23cm centres. Except for fencing, sheeting side
laps shall be seam bolted at 23cm centres.
s"At comers of sheeted buildings a galvanized flashing 45cm girth shall
be bent and seam bolted at 23cm centres on both edges.
Where apron, cover, stepped and other flashings are fixed as described
in External Plumber the flashing shall be seam bolted to the sheeting
at 23cm centres.
I
9.4.3 Bedding Sheets
INDEX
PAGE NO,
10.3 WORKMANSHIP
10.3.1 GLAZED WALL TILES
10.3.2 TERRA20 FLOOR-TILq --
10.3.3 CERAMIC FLOOR TILES -
10.3:4- CERAMIC WALL T I E S
10.3.5 QUARRY FLOOR T I ~ S
10.3.6 MARBLE FLOOR TILES
10.4 CUTTING OF TILES
10.4 CUTTING OF TILES
10.5 CLEANING OF TILES
10.6 EXPANSION JOINTS
KUWAIT OIL COMPANY (KSC)
SECTION X
FlOOR AND WALL TILER
10.1 GENERAL
Floor tiles shall be cut to ensure that edges at walls are fully covered by
skirtings. Exposed edges of floor tiles shall be scribed neatly against adjacent
surfaces.
Where different colour floor tiles occur in adjoining spaces colours shall meet
on the centre line of doors separating these spaces.
Making good etc., - the contractor shall perform all necessary cutting and
fitting tiles around all pipes, sanitary fittings, openings,-etc., M - e ---
good -after all trades. -
.-.
10.2 MATERIALS
The tiles shall be trueto shape, flat and free from flaws, cracks
and pittings and have a fine smooth textured finish. Where
specified, non-slip or abrasion resistant additives shall be
incorporated in the wearing surfaces.
All tiles shall be properly cured after removal from the mould
- - :
by total immersion after initial set, in clean water for,.24-.hours.
. -- . 1
All tiles shall be true to shape, flat and free from flaws, cracks
and pittings and be polished to a grit finish to avoid
slipperiness.
Ceramic floor tiles shall be non-slip vitrified ceramic tiles size -.. -
-
lOcm x lOcm x 9mm thick (or as indicated on the drawings or
- in the particular Specification) & shall be as manufactured by
RICHARD GINORI or any similar approved manufacturer,
conforming with B.S. 1286, latest edition for "Floor Tiles Type
B".
Glazed wall tiles shall be uniform in colour and of the colour specified
and comply with the approved sample 150 x 150 x 6.4mm thick or as
indicated on the drawings or in the particular specification and shall be
as manufacturer glazed on face as B.S. 1281 latest edition (Dimensions
and Workmanship only).
External angles and top edges of glazed wall tiling shall be formed
with rounded edge as B.S. 1281 latest edition, Figure 2 Ref. R.E.X.
-- if required.
.- . - - -
Where required, the external angles, sides and to edges shall be
formed with angles beads as B.S. 1281 latest edition, Figure 6
including special fittings at intersections. Tiles shall be laid in
patterns as requested by the Superintendent.
Ceramic Wall Tiles shall be durable and stain proof with fine grain
and colour throughout. They shall be impervious with less than lh%
water absorption.
Tiles shall be 150 x 150 x 12mm thick and with internal comers, sides
and top edges of tiling formed with the Manufacturer's special tiles
produced for each location. Tiles shall be manufactured by "Buchtal
or Bail" or other equal and approved Manufacturer.
- -
- -.-.-."- *_- C
al Marble Tiles
Tiles shall be of a uniform colour with straight edges and right angles
apd on absolutely smooth true surface free from air bubbles or
scratches or any other discolouring.
10.3 WORKMANSHIP
Where the tiles are to be bedded in cement and sand mortar the floated
coat shall be scratched to afford a key.
Where cement based or mastic adhesives are to be used for fixing the -
tiles the floated coat shall be finished with a wood and s t d float
respectively.
--
- .Floated coats mustbe-plumb aad any unevenness must be such that a
correction of no more than 3.2mm in any distance of 3M is required
to bring the finished tiles face to the required plane.
The floated coat shall be completed at least one week before tile fixing
begins and in addition should be thoroughly dry.
The surface of the floated coat shall be well wetted with fresh sweet
water before tiling is applied.
All tiles shall be immersed in fresh sweet water for at least six hours
prior to fixing until saturated. After soaking the tiles shall be removed
from the water and stacked on edge to drain the surface water only.
I
The starting course on surface to be tiled, shall be established with a
level line set out to ensure that the joint gap between each tile will be
- 1.6mm. Before tiling begins, the dry floated a t s W b e urettdjurt-
sufficiently to prevent it from absorbing witer 'from the fixing bed.
..
Tiles shall be bedded in cement and sand (1:3) mix 6mm thick to a
true vertical face with continuous horizontal and vertical joint.
The use of cement based and mastic adhesives for fixing shall be
approved by the Superintendent. The instructions of the manufacturers
on the use of the adhesive must be observed.
The joints of the wall tiling shall be raked out, while green and after
a period of at least one day after completion of the tiling, the joints
shall be wetted and grouted with a mix composed of 1 part white
cement and 3 parts hydrated lime, brushed then be lined out with a
piece of wood, of the thickness equivalent to the joint and surplus
grout adhering to the face of the tile shall be wiped off with a clean
damp cloth before it sets hard and shall be removed from the tiles.
Joints between tiles shall be regular and not less than 3mm or greater
than 4mm. The joints shall be grouted upon completion of the laying
with neat white coloured cement sluny composed of 1 part cement to
1 part of sand, otherwise required by the Superintendent or specified
on the drawings, spread over with a squeegee and the surfaces wiped
clean immediately after grouting. The grouting shall be coloured to
match the tile if required.
I
The tiles shall be neatly laid, square and true to level. Expansion
joints shall be provided in floor tiles as specified in the drawings or
- ---- --- directed by the Superintendent. Cuttings up to abutments and around-
projections shall be neatly done.
- -_
...
All terrazzo surfaces shall be polished on completion of laying. Large
areas shall be wet polished by machine using a No. 140 carborundum
abrasive. Areas too small for machine polishing shall be polished by
hand using a No. 140 carborundum stone and clean water.
After grouting, the tiles shall be protected by spreading saw dust or
polythene sheets laid in close contact with the floor which shall be kept
damp for not less than seven days, during which time, the floor must
be allowed to mature undisturbed.
The protection shall be cleared away before handing over the work.
Ceramic tiles shall be laid and bedded on a cement and (1:4) mortar
5mm thick on a cement and (1:4) sand screed with a 5cm overall total
thickness. Where floors are laid to falls, cross-falls and current, the
average overall thickness shall be 5cm.
All tiles shall be neatly laid square true to level with straight regular
'
joints inclpding.@@ cutting up to abutments and around projections
and.white cement and one part sand. Joints shall be completely filled
and surplus grout removed on completion.
Ceramic tiles skirtings shall be lOcm high and 5mm projection beyond
the plaster face, unless otherwise shown on the drawings or directed
by the Superintendent. Skirtings shall be tiled with bevelled edges,
polished on face and exposed edges and with all angle pieces internal
and external and bedded in the same manner as for paving using a
1:2% mix.
The backing coat must be plumb and any unevenness must be such that
a correction of no more than 3.5mm in any distance of 3M is required
to bring the finished tile face to the required plane.
The backing coat shall have been completed at least one week before
tile fixing begins and in addition, should be thoroughly dry.
The tiles shall be completely immersed in clean fresh water for at l&t
one hour prior to fixing. After soaking the tiles shall be removed
from the water and stacked on edge to drain the surface water only.
Tiles shall be evenly buttered and firmly into position. The resulting
base thickness should geneially be 6.5mm. Uniform spaces between
tiles shall be obtained as specified above.
A glass cutter must be used to cut and fit glazed tiles up to abutments
and round projections.
The joints of the wall tiling shall be raked out, while green and after
a period of at least one day completion of the tiling, the joints shall be
wetted and grouted with a mix composed of one part white cement and
three parts hydrated lime, brushed and worked well into the joints.
The joints shall then be lined out with a piece of grout removed from
.. .--- tm riles: Upon completion of the grouting,
- - the tiled areas shall be
wiped clean.
10.3.5 Q u a y Floor Tiles
Quarry floor tiles shall be laid with square joints finished to a true flat
surface and shall be laid with approximately 3mm wide straight and
regular joints unless otherwise indicated on the drawings.
Before the bedding mortar sets, joints between tile shall be raked out
to a depth of approximately lOmm and cleaned of mortar particles.
After the bedding mortar has set, the joints shall be filled fl'ush with
ordinary or coloured cement (as specified by the Superintendent) and
sand.
Marble Floor Tile~
Before laying tiles, the sub-base shall be cleaned to remove dirt, dust,
debris and loose particles and saturated with clean water several hours
before placing setting bed. About one hpur prior to placing setting
bed, surface water shall be removed.
Mortar for the setting bed shall be gauged 1:3 by volume of cement
.
and sand using only enough water to produce a moist surface when the
setting bed is ready for setting of stone. The screed shall be spread to
a uniform thickness, except for minor variations required to produce -
a h e surface level in plane. Only the amount which can be covered
with stone prior to initial set of the bed shall be mixed and placed and
material which has reached initial set prior to placing of stone shall be
used.
Stone shall be thoroughly wetted before setting and set before initial
set of cement bed occurs. A thin layer of neat cement paste 0.8mm
to 1.6mm thick shall be applied by brushing or trowelling over setting
bed, or a bottom of stone. Each stone shall be tamped for complete
contact with setting bed and levelled immediately.
Tiles abutting against wood, aluminium of metal frame, or tiling at angles, and round
brackets, pipes, etc., shall be carefully cut and fitted to form a close neat joint. Open
irregular joints filled with cement and sand or plaster shall not be permitted.
10.5 CLEANING OF TILES
All tiling shall be thoroughly cleaned down or washed off on completion and all
surplus plaster and pointing cement removed. All paint splashes shall be removed
I immediately after painting.
10.6 EXPANSION JOINTS
Expansion joints shall be formed where shown on the drawings or as specified and
shall be constructed to the satisfaction and approval of the Superintendent.
KUWAIT OIL COMPANY (KSC)
SECTION XI
INDEX
PAGENO. .
11.1 GENERAL 1
11.2 MATERIALS .. 1
11.2:1 ROLLED MILD STEEL JOISTS,
CHANNELS, ANGLE & TEES 1
11.2.2 WROUGHT IRON BOLTS, NUTS AND WASHERS 1
11.2.3 MILD STEEL 2
11.2.4 PLANNING TO PLATES AND BARS 2
11.2.5 STACKING 1
11.5 WORKMANSHIP
11.5.1 FABRICATION
11.5.2 WELDING
11.5.3 WELDING
1]t:spA *'+% - '.
WARKING
115.6 SHOP COAT PRIMER
11S . 7 ERECTION
11.5.8 GROUTING
11.6.1 HARDWARE
11.6.2 ANODIZING
11.6.3 SEALING
KUWAIT OIL COMPANY (KSC)
I
SECTION XI
10.1 GENERAL
'
All materials supplied shall be free from scale, rust, damage and defects. All
steel work be provided and fixed complete with all plates, cleats, bolts, etc., .
cut to lengths and sizes and drilled not punches. All steel members in contact
with the soil shall be painted with two coats of protective asphalt paint. All
doors, windows, gable frames, runway girder or any other steel item shall be
g&in at least-ohe c o of-rust-inhibiting
~ paint of an approved bragd before
delivery to the Ate. All welding, brazing or hot forging shall be carried out
by approved processes. All metal works shall be approved by the
superintendent before starting painting works.
Rolled steel, mild steel joists, channels, angles and tees shall
comply with B.S. 4360, latest edition: "Weldable smctural
steel" or ASTM A36, a "Structural steel."
11.2.2 Wraueht
- Iron Bolts. Nuts and Washers
All bolts and nuts shall be metric standards. Black bolts shall
be in accordance with B.S. 916 latest edition or ASTM A307.
Bolts shall be of sufficient length to show at least one full
thread beyond the nut after tightening.
I
The plates and bars shall be truly straight and bent to exact .
forms required and the ends planed so as to form true joints.
The following remarks relating to metal -windows shall cover also metal
casement doors and where applicable partitions as well:
11.4 MmAmQl)S
- -
wrought steel balustrades shall be:provided to staircases and balconies as
shown on the drawings. Burglar bars and safety bars shall be provided to
windows where shown on the drawings.
Cramps for fixing wooden door and window frames shall be 20cm long x 3cm
x 3mm section and shall have one end bent and twice drilled for screwing to
frame and other end fishtailed for building into walling. Cramps shall be
galvanized or dipped in bitumen before fixing.
Opening sashes shall be fitted with steel hinges having brass pins. Pivoting
sashes shall be fitted with bronze ring centres. Side hung or vertically
pivoting sashes shall be fitted with sliding stays and handled fasteners with
two-point noses as shown on the drawings or as specified in the particular
specification. Top hung or horizontally pivoting sashes shall be fitted with
steel side arms each.
All steel parts shall be accurately set out, cut, framed and
executed using proper rivets, bolts or welding electrodes. All
cut parts shall be as sawn. No oxygen burning shall be
permitted unless approved by the Superintendent. All cut parts
and welded section shall be ground even and filed smooth with
round edges. I
11S.2 Holes
- -,-
Holes through more than one thickness -of material for
-
members, shall, where possible, be drilled after the members
are assembled and tightly clamped together. Punching will be
permitted before assembly, provided the holes are punches
3mm less in diameter than the required size and reamed after
assembly to the full diameter. The thickness of material
punched shall not exceed 1Omm. Holes for bolts shall be
1.5mm larger than the nominal diameter of the bolts.
The diameter for all sub-punched holes and drill for all sub-
drilled holes, shall be at least 1.51nmsn~allerthan the nominal
diameter of the bolt.
All matching holes for bolts shall register with each other so
that a gauge 1.6mm less in diameter than the hole, will pass .
freely through the assembled member sin a direction @ right
angles to such members.
.
Holes for bolts shall not be formed by a gas cutting process.
--
- - + -.----.-- _.
- - . The component parts shall be assembled in such a-manner tha; ---< -- -
they are neither twisted nor otherwise damaged and shall be so
prepared that the specified cambers, if any, are provided.
The threaded portion of each bolt shall project through the nut
at least one thread and not more than 13mm when the nut is
spanner tight.
115 . 3 Welding
- v - r
-
Surfaces to be welded -shall be free from loose scale, slag, rust,
grease, paint imd anl'other foreign material except that mill
scale which withstands vigorous wire brushing may remain.
Joints surfaces shall be free from fins and tears.
11.5.5 Welders
.----
.----11.5.6-:$hop
4.-:
Coat Primer
1 1.5.7 Erection
Crane rails;
Girders & Brackets 3mm 21nm -
During erection, the work shall be securely bolted or otherwise
fastened and if necessary temporarily braced, so as to make
adequate provision for all erection stresses and conditions,
including those due to erection equipment and its operation.
Neither permanent bolting nor welding shall be done until
proper alignment has been obtained.
Hardware
Anodizing
sealing
SECTION XI1
GLAZTER
INDEX
I?mixL
12.1 GENERAL 1
12.2 MATERIALS
- . - . - . ..
12.2.1 CLEARSHEETGLASS
12.2.2 CLEAR PLATE GLASS, NUTS AND WASHERS
12.2.3 CLEAR FLOAT GLASS
12.2.4 TRANSLUCENT GLASS
12.2.5 TRANSLUCENT ABSORBENT AND
INSULATING GLASS
12.2.6 WIRED GLASS
12.2.7 HEAT - ABSORBING PLATE GLASS
12.2.8 MIRRORS
12.2.9 PUTT'Y AND OTHER MATERIALS
12.5 WORKMANSHIP
12.3.1 REBATES
12.3.2 BEADS AND WASH LEATHER
12.3.3 CU'ITING ALLOWAWE -- - -
12i3.3 GLAZING TO WOOD WITHOUT BEADS-
12.3.6 GLAZING WITHOUT PUTTY
12.3.7 GLAZING TO METAL
12.3.8 GLAZING T O ALUMINIUM
12.3.9 FIXING MIRRORS
12.3.10 CLEANING DOWN AND PAINTING
KUWAIT OIL COMPANY MSC1
SECTION XI
The Contractor shall replace all cracked or broken glass and clean all glazing
on both sides and all mirrors prior to handling over.
-
L
- _ , --_ -The ~ o ~ t r a c t shil
o r submit samples of all glass to be used on thi! works to + -- -
the Superintendent for approval.
12.2 MATERIALS
The types and quality of glass used shall not be in any case inferior to the
following:
2.90 - 3.50 8
-
4.50 5.15 11
6.35 - 7.00 16
Limits of
Thickness (mm)
- ~ o u g Cast
h (square
mesh)
Heat absorbing glass shall comply with B.S. No. 952 Section
23, either. 'a' with a high light transmission not less than 70
percent,. or 'b' "55-60% light transmission with 25 percent
restriction of Solar Radiation", as called for in the particular
Specification or shown on the drawings and as follows:
4-6 11 4.76
5.5 - 7.5 16 6.35
Minor glass shall be silvering quality polished plate glass
silvered on one side, copper-backed varnished and painted to
the satisfaction of the Superintendent.
Mirror glass shall be rectangular and of the size stated with bevelled
edges and four times drilled for fixing with chromium plated false
dome headed screws into prepared plugs let into walls.
Putty for glazing to soft wood other than non-absorbent hard woods
shall conform to type 1 of B.S. 544, and shall be of tropical grade
wood glazing.
Metal glazing beads shall be supplied with metal windows, doors and
partitions and shall be sprung or screwed on as shown on the drawings
or according to the manufacturer's instructions.
12.3 WORKMANSHIP
12.3.1 Rebates
The rebates of old or new timber or metal sashes shall be thoroughly
cleaned and painted with one coat of oil paint, except the rebates of
hardwood sashes, in other than painted joinery which shall be
moistened with linseed oil. - - * _ . _..
-- 1 L
Glass to doors and screens and other places where vibration may
occur, shall be bedded in wash leather, or putty, with timber beads
fixed with panel plus or brass caps and screws as described.
The rebates shall be previously treated with one coat of priming paint
and the bedding putty inserted. The glass shall be embedded in the
putty and secured by the beads. The bedding putty shall be trimmed
off level with the sight line to form a neat back putty and the painting
shall be carried out.
The rebates shall be previously treated with one coat of priming paint
and the bedding putty inserted. The glass shall be embedded in the
. putty and secured"sprigs. The front putty shall be-inserted to form a
- triangular mitred filling from the edge of the rehates to 2mm back
from the sight line. The bedding putty shall be trimmed off level with
sight line to form a neat back putty. When the putty has hardened
sufficiently the painting shall be d e d out and care shall be taken to
seal the joint between putty and glass by painting up to the sight line.
12.3.7 Glazing To M e a
- ---., - , - -
Only glazing to metal with beads shall be permitEd. The rebates shall
be previously treated either by rustproofing or priming as described
elsewhere and the bedding putty inserted. The glass shall be
embedded in the putty and secured by the beads. The bedding putty
shall be trimmed off level with the sight line to form a neat back putty
and painting shall be carried out.
Glazing-
Fixine Mirrors
SECTION XI11
INDEX
PAGE NO,
GENERAL 1
MATERIALS 1
13.2.1 WATER VALVES 1
13.2.2 WATER MAINS 2
- -
WORKMANSHIP 2
13.3.1 EXTERNAL SERVICES 2
13.3.1.1 GUTTERS, RAINWATER 2
PIPES AND FITTINGS
13.3.1.2 FLASHINGS 2
13.3.1.3 PIPE SLEEVES 3
13.3.1.4 JOINTING OF PIPES & GUTTERS 3
13.3.1.5 FIXING 4
13.3.2 INTERNAL SERVICES 5
INTERNAL PIPEWORK 5
13.3.2.1 GENERAL 5
13.3.2.2 COLD WATER SUPPLY
13.3.2.3 HOT WATER SUPPLY --
1
13.4.1 SINKS
13.4.2 LAVATORY BASINS
13.4.3 BATHS
13.4.4 SHOWER TRAYS
PAGE NO,
URINALS 11
SUNDRIES 11
ELECTRIC WATER HEATERS 11
BUILDER'S WORK 12
TESTING 13
G-AS FllTER - 14
CLEANING - 14
KUWAIT OIL COMPANY (KSC)
SECTION XITI
GENERAL
The Contractor shall provide all materials, labour, equipment, plan and
incidental required to execute complete and maintain the works. The
Contractor shall carry out the tests required under the supervision of the
Superintendent, and shall make good and replace any defective work. The
Contractor shall be responsible for protection of all plumbing from any
damage whether due to the con-current work of the other trades or otherwise
and shall clean up upon completion leaving all works in perfect working order
and to the satisfaction of the Superintendent.
MATERIAL
Draw off taps and stop valves shall comply with the
requirements of B.S. 1010 (Draw off taps and stop valves for
water service (screw 'down pattern).
The taps and valves shall be of brass of gun metal, the castings
in all respects round good free from laps, blow holes and
pitting and both internal and external surfaces clean and
smooth. The bodies, heads, spindles and other parts shall be
truly machines. The area of the waterway throughout the body .. -
shall be not less than 'the area of a' circle of diameter equal to
the nominal size of the tap or valve.
Special fittings for either the asbestos cement or cast iron pipe shall be
to B.S. 78 Grade "C".
13.3 WORKMANSHIP
13.3.1.2 Flashings
13.3.1.5. Fixing
Internal Pipework
13.3.2.1 General
All pipework shall be planned so that the piping is
accessible for inspection, replacement and repair.
Where it is necessary for a pipe to pass through a wall
or floor a sleeve shall be fixed therein to receive the
pipe.
In industrial buildings, where means of identifying pipe
& necessary, the decoration of water supply or gas
pipework shall be in accord&e with the Standard
colours for Company use.
Lead pipes shall comply with B.S. 602 and B.S. 1085.
The cold water feed pipe shall leave the storage tank at
a distance of not less than 25mm above the bottom of
the cistern and connect into the hot water cylinder near
its bottom. It shall be not less than 25mm bore and
shall not deliver water anywhere but to the cylinder.
An expansion pipe shall be installed of not less than
19mm bore from the hot water cylinder to a point of
15cm above the overflow level of and to discharge into
the cold water storage tank. The pipe shall be of a
length to include an allowance of 13mm for each 30cm
in the height of the overflow level above the bottom of
the hot water cylinder.
The distribution pipe shall leave the top of the hot water
cylinder and be of not less than 25mm bore branch pipe
to appliances shall generally be: wash basin 13mm,
baths 19mm, sinks 1.3mm. . -
--
Joints Between Pipes
13.4.1 Sinks
Sinks shall be either white glazed fireclay complying with B.S. 1206
of stainless steel-complyingwith BS 1244 with two 12.7mm diameter
- chromium plafed bibcocks, combined overfl~w and 38.100mm
diameter trapped waste, plug and chain. Sinks-shall be fixed on pair
. of cantilever brackets built into wall or on frame and supports of
25.400mm diameter galvanized steel pipe or on blockwork piers as
detailed on the drawings, or directed by the Superintendent. Sinks
shall be 60cm x 76cm x 45cm unless otherwise it is shown on the
drawings or indicated in the Particular Specification.
-
Baths
Bath tubs shall be white porcelain enamelled cast iron complying with
B.S. 1189 with rectangular tops and side and end panels where
required, fitted with two 19.00mm diameter chromium plated pillar
valves, 31.75mrn overflow and 40mm diameter trapped waste, plug
and chain. Where baths are fitted with a shower this shall be of either
the overhead type or the telephone type with flexible tubing complete
with supporting arms for spray and having a directing valve assembly
fixed to the bath.
In all cases, the show hose and exposed piping shall be chromium
plated and the connections to such shovels shall be through a
chromium plated mixing valve. The baths and showers shall be fixed
as detailed on the drawings or directed by the Superintendent.
Baths shall be size 168cm long x 71cm wide. The bath panel with
appropriate for the bath and shall be fitted in accordance with the
manufacturer's instruction.
Both bath and panel shall be neatly pointed with mastic or neat white
cement where in contact with wall finishings.
13.4.6 Urinals
Urinals shall be either wall fitting bowl type of white glazed fireclay
or stall type of white glazed fireclay. The bowl type shall be
supported on steel brackets cut and pinned to wall and shall have
chromium plated flat grating and outlet. The stall type shall comprise
back slabs, divisions returned ends, floor treads, channel with returned
ends and chromium plated removable domical grating and outlet.
Flushing cisterns of sufficient capacity shall be connected through flush
pipes and sparge pipes of copper, chromium plated where required.
Where required seawater resisting flushing shall be used.
- . 13.4.7 . Sundries - -- .
--
The following fittings shall be provided:
The water heater shall consist of an inner and outer container, thermal
insulation between the containers and immersion heater, thermostat,
pipe fittings and safety valve.
...
- . The inner contaker shall be of heavy gauge cop$r sheet with double
lap longitudinal and circumferential shell joints. All joints shall be
brazed. The inner container shall be tinned internally and fitted with
B.S.P.T. water connections.
The inlet pipe shall enter from the bottom and shall be fitted with a
non-return valve. Outlet pipe can enter the container from the top or
bottom. The arrangement of inlet and outlet pipes inside the inner
container shall not permit, emptying the inner container of water under
any condition except through the drain connection.
The outer container of high grade sheet steel rust proofed with two
coats of anti-rust paint inside and outside, and finished in stone
enamel. The space between the inner and outer containers to be
padded with efficient thermal lagging. -
a - .
Water heaters of up 'to 76 litres-capacity shall be provided with
substantial lugs, for wall mountings; water heaters of greater capacity
, shall be foot mounted.
The outer case shall be provided with a suitable entry for 19mm or
25.4 electric conduit for the electric connections.
Water heaters of up to 76 litres capacity shall be suitable for operation
from a 240 volt 50 C.P.S. electric supply; heaters of greater capacity
shall be suitable for operating from a 415 volt, 3 phase 4 wire 50
C.P.S. electric supply.
Builder's Works
Where pipes are. fixed on the surface of walls, the Contractor shall
perform all cutting and pinning for holderbats or plugging and
screwing for pipe clips. Where pipes are conce&d in the walls, etc.,
the Contractor shall perform all cutting and subsequent making good.
Pipes through walls or floors shall pass through approved sleeves and
covers at points of emergence shall be provided. All builder's work
by the plumber shall be finished in a neat and workmanlike fashion
and the satisfaction of the Superintendent.
The entire system of hot and cold, brackish and fresh water shall be
slowly filled with water allowing any trapped air to escape and
avoiding all shock or water hammer.
-
All 6urlets shall then be closed and the $stems checked for
watertightness.
Finally, after the test pressure is released, each outlet shall then be
checked for rate of flow and correct operation.
The Contractor shall provide all facilities for the testing and make
good any defects to the satisfaction of the Superintendent.
Testing
-
When a gas installation is c o m p k k , it shall be tested
by applying a strong solution of soapy water to each
joint after allowing gas pressure to build up to normal
operating pressure against each appliance. Each joint
shall then be examined for leaks and each appliance
shall be ignited and tested for proper functioning.
The Contractor shall carefully clean out all cold water and hot water
tanks, service pipes, sanitary fittings throughout, traps and wastes.
The Contractor shall also overhaul and make good all flushing valves,
check regulating vaIves, check taps including rewashering as necessary
and leave all works in perfectly clean and working condition.
KUWAIT 011 COMPANY (KSCL
SECTION XIV
INDEX
PAGE NO.
14.1 GENERAL
14.2 MATERIALS
KNOrrlNG :
STOPPING
FILLER
PUl-rY
PETRIFYING LIQUID
PAINT REMOVER
CELLULOSE PAINT
VINYL PAPER
WOOD STAIN
WOOD VARNISH
14.3 WORKMANSHIP
14.4 PREPARATION OF SURFACES
I 4.5 PLASTER, CEMENTISAND RENDERING,
BLOCK WORK & CONCRETE
14.12 PAINTING 8
I!
14.1 2 . 4 TIMBER SURFACES 13
SECTION XIV
I!
13.1 GENERAL
14.2 MATERIALS
14.2.1 Knotting
Filler
&ax.
Putty shall be best
.. . tropical'quality.
Paint Remover
Cellulose Paint
Vinvl Paoer - - _ . --
--
Vinyl paper shall be heavy duty vinyl faced wall-paper by
an approved manufacturer.
Wood Stain
Wood Varnish
PREPARATION OF SURFACES
To be ready for painting a surface shall be clean, dry and sound, not
friable or unduly absorbent and as far as is possible, have reached a
stable condition. the surface should also be smooth enough to make
it possible to produce the particular quality of paint finish required.
The preparation work shall include, hacking out all loose or defective
putties to glazing, cleaning rebates applying one coat of primer and
making good with putty, including those rebates where the old putty
has fallen out. Power assisted cleaning processes shall be used if
specified, and shall be in the form of power driven hammers, or
grinding machines.
All iron and steel surface, (excluding the internal surface of fresh water
-.
-tanks and structural steelwork to be protected for rhelfirsf time-or re-
protected with flinkote, cola tar epoxy paint or the like).
g n ~ a i n t e dSurfaces
Chip and scrape loose mill scale. Remove oil and grease from
the surface with approved solvent and thoroughly wire brush,
run down and leave the surfaces clean free from all dirt, dust,
oil, grease, rust, residue of previous treatments, chemical
pollution and abrasive residue.
Previouslv Painted Surfaces
Thoroughly rub down with wet and dry paper t o remove loose
paint and rusted areas, bring forward worn or bare parts with
cellulose filler, dented or damaged areas with approved filler.
Run down and leave the surface free from all dirt, dust, oil,
grease and abrasive residues, including cleaning with approved
solvents ~ h e r e ~ n e c e s s aand
r y leave ready to-receive cellulose
- ,. spray finish. -
All soft-timber shall be treated with approved anti-termite paint
prior t o fixing.
Galvanized steel surfaces shall be cleaned t o remove grease and dirt before
priming. Where rusting has occurred through damage t o the galvanizing,
such rust shall be removed by wire brush t o clean the surface then apply
one coat of wash primer followed by one coat of phenolated alkyd with zinc
chromate followed by t w o coats of alkyde enamel.
14.8.1 U n ~ a i n t e dSurfaces
Chip and scrape rusted areas, thoroughly wire brush and clean
surfaces and also remove loose paint and apply one coat of
zinc chromate primer t o internal surfaces and t w o coats of zinc
chromate t o external surfaces of bare metal. Bring forward
worn or bare pans with undercoating. Run down and leave the
remaining surf5ces free from all dirt, dust; oil, grease and
'' abrasive residues including cleaning with approved solvents
where necessary.
All surfaces of parts t o be joined, but not glued, shall receive one coat of
priming paint and wherever practicable should be brought together while the
paint is still wet.
Where joinery timber units which have been shop primed are
subsequently cut or the primer damaged during building
operations the area so exposed shall be primed.
Cracks and holes shall be stopped with a suitable filler. the whole
surface shall be left smooth free from dust, loose or powdery
material and left clean.
Surfaces shall be brushed down t o remove all dirt loose or powdery material
and left clean.
All paint pots and kettles used on the site shall be clean. They
shall be thoroughly cleaned before being used for a different type
o f a colour of paint and emptied and cleaned with a suitable
solvent each day after use.
Ready mixed paints shall be well stirred and strained free from
skins and other foreign matter before application through a
phosphor bronze wire sieve of 60 and 120 gauge.
14.12.1.5 Pi~e
and Identification Colour
14.12.2.1 Un~aintedSurfaces
-
Apply one coat alkali resistent plaster sealer,
one coat undercoating and one coat oil gloss
finishing paint.
OR
14.12.4.1 Yn~aintedSurfaces
OR
OR
..
Stain to approval.
SECTION X V
CORROSION MITIGATION
COATING & WRAPPING FOR BURIED PIPEWORK
...
- INDEX -
- - PAGE NO.
15.1 GENERAL 1
' 15.2 TYPE OF METHODS OF COATING & WRAPPING 1
15.3 ALIGNMENT OF PIPE PRIOR TO COATING & WRAPPING 2
15.4 WEATHER CONDITIONS 2
15.5 SURFACE PREPARATION OF PIPE 2
15.6 PRIMING 3
15.7 APPLICATION OF PLASTIC TAPES 3
15.8 MACHINE APPLICATION OF HOT ENAMEL COATINGS 4
15.9 HOLIDAY DETECTION 4
15.10 HANDLING OF COATED PlPE .-
10
15.1 1 CORROSION PROTECTION-FOR STRUCTURAL STEE~WORK
I N A MARINE ENVIRONMENT 7
15.12 TANKAGE 8
KUWAIT OIL COMPANY (KSC1
SECTION XV
CORROSION MITIGATION
15.1 GENERAL
All buried METAL pipework shall be coated and wrapped t o the satisfaction of
Standards & Inspection Department representative before backfilling takes place.
Coating and wrapping may take place using hot or cold materials. For
lines of 203mm in diameter and above any of the following coatings
may be applied by mechanical method except for pipeline of less than
5 0 0 metres in length where manual methods may be applied.
-
In the case of minor lines application of tape may be made by
hand. Care should be taken t o avoid wrinkles, puckers or
voids and t o maintain a correct overlap.
The coated and wrapped pipe shall not be rested upon the
ground until the enamel is set.
HOLIDAY DETECTION
b. Old Coatinas
15.10.1 Taped pipe may normally be lowered directly into the ditch for
backfill. If it is necessary t o rest the taped pipe temporarily on skids
they shall be wide and padded with resilient peds to prevent damage
t o the tape.
15.10.3 The ditch bottom shall be free of stones, etc., and consolidated sand
not less than 150mm thick shall be placed as a pad.
15.10.4 Coated pipe shall be raised, lowered or suspended by using rubber
or leather or canvas slings. The sling width shall be equal t o or
greater than the pipe diameter.
GENERAL NOTES
The Contractor shall sandblast, clean off and coat with coal tar epoxy paint as
specified below:
After priming each successive coat must be applied within the period
of 1 2 to 72 hours. In all, three coats will be applied using spray
equipment or nylon brushes, each coat to a uniform thickness of
125-1 75 microns with a colour sequence black brown black. The
nominal minimum thickness of the coating shall be 400 microns.
...
15.1 1.4 Reoairs To Coating
-
The damaged areas shall be washed with sweet water, after drying
thoroughly, the surface of the good adjacent coating roughened by
wire brushing. One coat of black coal tar epoxy will immediately be
applied followed at 1 2 to 2 4 hours intervals with one coat of brown
coal tar epoxy and a final coat of black coal tar epoxy.
15.1 2 TANKAGE
All tank base plates shall, before final positioning for welding, be cleaned, primed
- and coated with a hot applied 708 enamel in .a manner &2&tly
pipelines except where the context is inapplicable.
- as specified for
To avoid contamination of the subsequent welding coating shall not be continued
beyond or shall be removed from within 76mm of where any welding shall
ultimately take place in construction.
The coated plates shall be transported into their final position in a manner resulting
,1
in the minimum damage t o the coating.
Alternatively, the base plates may be sand blasted t o SA 2 '/2 and locked with coal
tar epoxy as in Clause 15.1 1.
KUWAIT OIL COMPANY (KSCL
SECTION XVI
WELDER
INDEX
PAGE NO.
16.1 GENERAL
16.2 PROCESS
-
SECTION XVI
INTRODUCTION
This Specification applies t o general practice only and must be read in conjunction with
the detailed welding procedure specification applicable t o the particular work.
Any departure from the specification such as change of electrodes alteration of welding
gaps and weld profile must first be approved by the K.O.C. Standards & lnspection
Department or any inspection authority nominated by Standards and lnspection Department.
This specification refers generally t o the manual welding of low carbon steels. When
welding of alloy steels is called for, separate specification sheets on procedure,
techniques tests, etc., shall be issued.
Welding shall normally be done by the manual arc process. Semi-automatic and
submerged arc processes may be used. All requirements affecting the quality of the
completed weld shall apply equally t o shop m d site welding.
Welding sets shall be of size and type suitable for the work and shall be
maintained in good condition t o ensure acceptable welds, continuity of
operation and safety of personnel. They shall be operated at the
recommended amperages and voltages for each size and type of
electrode.
Weldina Electrodes
16.4 WELDERS
The Contractor shall submit t o KOC the welding procedure which it is intended t o use
. in connection w i t h equipment construction for approval b e f o r q h e welding qualification
test are conducted. --
16.6 WELDING QUALIFICATIONS
16.6.1 The welding procedure qualification and welders qualification tests shall
be undertaken in accordance with API standard 1104 for pipeline
construction or with ASME Boiler and Pressure Vessel Code Section IX
for tank and pressure vessel construction.
16.6.2 Tests for the welding procedure qualification and welders shall be
conducted at KOC Inspection and Corrosion Workshop.
16.7.1 All welding operations shall be carried out in accordance with API 1104.
Preparation of joints reinforcements welding of field branch connections
shall be in accordance w i t h the relevant ANSI Code k g . 831 -4 or
831.8) and welding plant, instruments, cables and accessories shall be
adequate for (he welding procedure t o be followed and shall be
- maintained in good order. -
16.7.2 Contractor shall use only competent, skilled and qualified workmen.
Each welder employed by the contractor shall be required t o
satisfactorily pass the welding tests as set out in API Standard 1104
witnessed by KOC or any inspection authority nominated by KOC.
16.7.3 Before welding any joint, the bevelled edge preparation shall be cleaned
free from any rust and/or oil deposits and any 'burrs' shall be removed
by filing or grinding. Each joint of pipe shall be cleaned of all those
materials immediately prior t o laying.
16.7.4 The bevel shall be sufficiently smooth and free from tool marks, oxides
and foreign matter t o enable proper inspection for laminations. The
removal of fins or burrs on the inside must be undertaken with care not
t o remove excess metal and form an inside bevel. Removal of excess
bevel shall be a cause for re-bevelling.
. . - .- - -
" 16.7.5 Bevelling shall be performed w i t h -a rnachink teh. All f&ld cuts shallbe -
normal t o the axis of the pipe. Mitre welds are prohibited.
The joints bevel angle, perpendicular to the pipe axis shall be 30" with
tolerance of +5-0". The root face of 2mm at the bevel ends is to be
kept to a minimum within the specified tolerance of 0.80mm. If less
than 0.8mm the root face shall not be brought into tolerance by filing or
grinding, the entire bevel must be re-machined.
For pipe of the same nominal wall thickness, the maximum offset or
misalignment of the abutting pipe ends shall not exceed 2mm. If the
pipe ends are damaged or dented beyond 1.6mm, the acceptance table
limit, they shall be cut and re-bevelled in accordance with 7.5, 7.6 and
7.7 above. If the line is flame cut, the heat effected zone shall be
removed by machining before producing the required bevel profile. The
heat affected zone is considered to be 3mm from the minimum flame cut
edge.
When joints of unequal thickness are jointed, the pternal offset shall not
exceed 1.6mm and the internal offset not exceed 2.4mm. If these
values are exceeded the excess, thickness of the heavier end shall be
machined or ground back from the bevel on 1:4 taper.
Each joint shall be lined up using an internal line up clamp for pipes
40.60mm 0.0.and over. The alignment shall be in accordance with API
standard 1104 except as otherwise stated herein. The clamps shall not
be removed until at least 50% of the "Root" run is completed. External
line-up clamps shall be used where internal clamps are impractical.
Under no circumstances shall the line be moved until the second or hot
pass is completed.
Before any pipes are welded they shall be lined up with longitudinal pipe
seam staggered by at least 20"and confined to the top two quarters of
the lined up ends of the pipe.
- -_ _-_
-
-,-4 - --
- I .
The start and finish point of each weld hot pass shall overlap by at least
25mm. The finished weld shall be finally wire brushed to remove all
weld slag.
The Root Run shall be deposited t o give complete fusion of the abutting
pipe ends with full penetration and minimum inside reinforcement of
2mm and a maximum of 3mm. Immediately on completion of the Root
Run it shall be thoroughly ground to show clean metal and be free from
all evidence of trapped slag. -
-
The hot pass shall be made immediately after <he grinding of the Root
Run is completed. It shall be completely fused to the Root Run and the
adjacent pipe.
Each filler pass shall be completed before the next Filler Pass is started.
The start of Filler Passes shall be staggered with complete overlapping
of the previous bead. On completion it shall be cleaned by wire brushing
and chiselling or grinding as deemed necessary to remove all trapped
slag.
The cover pass shall not be concave finish and shall have a bund up of
not less than 1mm or more than 2mm. The width of this pass shall not
be less than 2mm or more than 3mm on either side of the weld bevels.
Surface pinholes and surface under-cutting may be repaired immediately
by welding. The completed weld shall be thoroughly brushed and
cleaned for inspection.
Each finished weld shall be clearly marked with water proof crayon or
paint to identify the portion of the weld 'made by each welder. Die
stamping shall not be permitted.
16.7.22 No repair welding shall be performed on the longitudinal seam of the
pipe. Such defective length of pipe shall be completely removed from
the line.
16.7.23 Any defects in the pipe outside the weld area shall be reported t o K.O.C.
I t
or the inspection authority nominated by K.O.C. who shall specify a
"
16.7.24 All open ends of the line shall be securely capped when being worked on
and at the end of each day's work.
16.8.3 The proportion of welds t o be radiographed shall be not less than 10%
taken at random after welding quality has been established as described
below.
16.8.4 Where a defective weld is found, all welds between the defective weld
and nearest acceptable welds (before and after) will be radiographed.
16.8.5 In order t o define the quality of the weld, at the start of any project, the
first 30 welds of each welding gang will be examined 100% by
radiography. Failure t o meet requirements in these welds shall be a
cause for welding work t o stop until faulty workmanship has been
rectified and causes identified. It is not the intention that the Contractor
shall be restricted in his work progress by first proving test welds as
described, but rather t o eradicate any initial faulty techniques.
16i8.6 ‘ Each welding gang shall identify their: welds by a&stinctive mark in
suitable coloured paint. No die stamping will be permitted.
The examination of welding will be carried out by K.O.C. - Standards &
lnspection Department or any inspection authority nominated by KOC
who will be responsible for radiography of welds, interpretation of
radiographs and issuing written instructions to the Contractor in respect
of any necessary repairs.
On completion of the pipeline welding, it shall be pressure tested using air or water as
laid down in the relevant Codes of Practice. Any weld showing an air or water leak
will be cut out and the pipe rewelded by the Contractor. The entire joint of pipe will
be replaced where an air or water leak is found in the longitudinal weld.
16.10 TANK WELDING
16.10.1 All welding operations shall be carried out in accordance with API
standard 650 (latest edition) for Welded Steel Tanks for Oil Storage.
16.1 0.2 Contractor shall use only competent, skilled and qualified workmen.
Each welder employed by the Contractor shall be required to
satisfactorily pass the welding tests as set out in ASME Boiler and
Pressure Vessel Code Section IX, witnessed by KOC or any inspection
authority nominated by KOC.
16.10.3 Welding shall not be performed when the surfaces of the parts to be
welded are wet from rain or during periods of high winds unless the
welder and work are properly shielded. Welding shall not be performed
when the base metal temperature is below the freezing point or the
thickness is in e x ~ e s sof 31.75mm. The base metal within 76mm of the
- - place where welding is t o be started shall be tiea-ted to a temperature
warm to the hand.
16.10.4 Each layer of weld metal or multi-layer welding shall be cleaned of slag
and other deposits before applying the next layers.
16.10.5 The edges of all welds shall merge with the surface of the plate without
a sharp angle. There shall be no under-cutting of the base metal, except
that on the horizontal butt joints under-cutting not to exceed 0.80mm
in depth is permissible.
16.10.6 The weld metal on both sides of all butt joints except the offset faces
of horizontal joints, shall be built up in the form of a reinforcement so
that all of the finished face in the area of fusion shall extend above the
surface of the adjoining plates preferably not more than 1.6mm.
16.10.7 The method proposed by the Contractor to hold the plates in position for
welding shall be submitted to KOC for approval. ...
. r
16.10.8 Tank welds used in the assembly of "ertical joinc b f tank shells shall be
removed and shall not remain in the finished joint when the joints are
welded manually. When such joints are welded by the submerged arc
process, the tack welds shall be thoroughly cleaned of all welding slag
but need not be removed provided they are sound and are thoroughly
fused into the subsequently deposited weld metal.
Tack welds in the bottom, and the circumferential joints of the tank does
not need t o be removed provided the joints end and the subsequently
applied weld shall be thoroughly fused into the tack welds.
The size of each fillet weld between the bottom edges of the lowest
course of the plate and the bottom plate shall be not more than 12.7mm
and not less than the normal thickness of the thinner of the t w o plates
joints i.e. the shell plate or the bottom plate in assembly under the shell.
In completed horizontal butt joints, the shell upper plate shall not project,
and face of the thickness of the upper plate with a g a x i m u m of 2.30mm
except that a projection of 1.60mm is permissible for upper plate with
less than 7.9mm thick.
The tank welding inspection shall be carried out in accordance with API
standard 6 5 0 (latest edition) for Welded Steel Tanks for Oil Storage.
The film used for radiography shall be Kodak Crystallex or its direct
equivalent and the intensifying screens will be of lead.
.-,
:
All repaired welds in joints shall be checked by repeating the original test
procedure.
The inspection of tank bottom and roof fillet welds shall be made by
visual examination undertaken by KOC or any inspection authority
nominated by KOC.
. 6 . 1I S Where visual inspection indicted unsatisfactory fillet welds, acceptance
or rejection shall be based on sectioning such areas by grinding or by
chipping w i t h a driven round nosed chipping tool.
'> 6.12.7 The tank bottom, shell and roof shall be tested according t o API
Standards 6 5 0 (latest edition) for Welded Steel Tanks for Oil Storage.
All tests shall be witnessed by KOC or any inspection authority
nominated by KOC. Upon completion of the whole construction of the
tank, it shall be subjected t o a combined hyd-Ipnuematic test as
described in API 620.
' 6.ltL Repairs t o defective welds shall be carried out after the approval of
K.O.C.'s representative. Completed repairs shall be subject t o the
approval of KOC's representative.
5.12.4 All defects, cracks, or leaks in shell joints or in the shell-to-bottom joint
shall be repaired as shown in paras 11.6 and 1 1.7 above.
6.12 E Isolated pinhole leaks in roof joints may be caulked mechanically; but for
any indication of considerable porosity in the joints, or of cracking, an
add~tionalbead of weld metal shall be laid over the affected sections.
Mechanical caulking is not permitted for any other repairs.
6.12.6 Repairs of defects discovered after the tank has been filled with water
for test shall be made w i t h water level at least 300mm below the point
being repaired or w i t h the tank empty, if repairs are on or near the tank
bottom.
6.12 ' Upon completion of the whole construction of the tank, it shall be
subjected t o a combined hyd-/pneumatic test as described in API 620.
6.13.7 All welding operations shall be carried out in accordance w i t h the latest
edition of ASME Boiler and Pressure Vessel Code Section VIII.
6.13.2 Contractor shall use only competent, skilled and qualified workmen.
Each welder employed b y the Contractor shall be required t o
satisfactorily pass the welding tests as set out in ASME Boiler and
Pressure Vessel Code Section IX witnessed by Standards and Inspection
Department or any inspection authority nominated by the company and
accepted by Standards & Inspection Department.
The welding procedure and welders qualifications tests in accordance
with the ASME Boiler and Pressure Vessel Code Section IX shall be
approved by Standards & lnspection Department or any inspection
authority nominated by the Company and accepted b y Standards &
lnspection Department. The Contractor should note that he is
responsible for having the necessary facilities available and that a
change in procedure or welder requires re-qualification.
Shell plates shall be laid out so that there will be a minimum of welded
seam.
Vessels shall be designed on the basis that pressure holding seams shall
normally be full penetration double welded butt joints. Single welded
butt joint with backing strip may be used where double welded butt
joints are impractical.
Single pass, submerged arc welding from one side only is not
acceptable.
When welding is called for carbon steel parts t o allow steel parts, the
contractor shall submit t o Standards & lnspection Department a suitable
-
welding procedure in accordance with A S M E Code Section IX for
approval.
16.1 5.1 Vessels shall be designed for stress relieving in accordance with the
requirements of the ASME Boiler and Pressure Vessel Code Section VIII.
Stress relieving other than required by the ASME Code shall be as
specified on the vessel drawings.
16.15.2 Consideration of stress relieving shall be given in the design of vessels
of unusual configuration or component design such that high stress may
be developed in welds because of restraint.
16.1 5.4 When stress relieving a vessel with attached alloy liners, the liner shall
be vented.
16.1 5.5 On field welded stress relieved vessel service, insulation shall not be
applied over welded seams until hydrostatic test had been performed.
16.1 5.6 Flange facings must be protected against oxidation during heat
treatment. ..
16.1 5.7 -. Cold formed heads shall be normalised or a&aled except the single
piece heads less than 9.5mm thick need not be heat treated unless
required by ASME Boiler and Pressure Vessel Code Section VIII.
16.15.8 Heads that are "heat treated" for any reason shall be freed of any mill
scale by sand blasting or picking prior t o inspection.
16.1 5.9 In addition to the provision of the code covering stress relieving
requirements, a pressure vessel shall be thermally stress relieved i f i t will
be exposed to caustic or oil streams in which caustic has been injected
at temperature which exceed the formula:
Where Ts = 170-"Be
Ts = Stream Temp. O F
"Be = Density of the caustic water solution, in degrees
Baume.
Only the portion of the vessel that will be expos9d to caustic is required
to the stress relieved.
:
- --
16.16 PRESSURE VESSEL TESTING
For vessels tested in vertical position caution shall be taken so that the
test pressure in any section does not exceed 1.5 times its pressure
capacity based on the total thickness of the plate the applicable joint
efficiency and the design stress at test temperature.
The stress in any section of the vessel during the hydrostatic test shall
not exceed the 90% of the minimum yield point for the material used,
times the joint efficiency.
Bolting and ring type joint gaskets to be supplied by the Contractor with
the vessel may be w e d for the pressure test but must be replaced if
damaged. Gaskets other than those for ring type joints to be supplied
by the Contractor with the vessel shall not be used for the pressure test.
The test pressure shall be held for at least t w r t t y five minutes per one
cm of thickness but in no case for less than 25 minutes.
16.1 6.1 0 Pressure vessels for which the contractor submits test certificates shall
not be pressure tested at site. But if any damage occurred
transportation t o site, then pressure testing may be required.
During all shop and site welding operations, care shall be exercised t o ensure the strict
compliance w i t h relevant clauses in the KOC Safety Regulation Section 5.8 and 25
w i t h regard t o Protective Operation.