Attachment A: Omv (Pakistan) GMBH Miano-17 (Nfo-01) Wellhead Development Project
Attachment A: Omv (Pakistan) GMBH Miano-17 (Nfo-01) Wellhead Development Project
ATTACHMENT A
INPUT DATA:
rsub = Submerged Soil Density lb/ft3 60.000 (Taken from 2024 -11-13-16-
CL-001- D1 Bearing Pressure &
Buoyancy Calculation for
Miano-16)
KN/m3 9.424
KN/m3 76.970
KN/m2 29.420
6" FLOWLINE
Outer Dia (D1) mm 168.275
Outer Dia (D1) m 0.168
Coating Thickness (t1) mm 2.500
Thickness of Pipe (t2) mm 9.500
Outer Dia with coating thk. (D2) m 0.173
Inner Dia (D3) mm 149.275
Inner Dia (D3) m 0.149
Empty Pipe Weight / Length (W1) KN/m 0.365
Water Filled Pipe Weight / Length (W2) KN/m 0.536
B- Buoyancy Check
= h1 < H2 1
Hence "OK"