Radian Research, Inc. makes no warranty on the accuracy of the information contained in this Operations
Manual and accepts no liability for its use.
The information contained in this Operations Manual remains the property of Radian Research, Inc. It is
provided in good faith for the operation and servicing of this Radian Research, Inc. product. We reserve
the right to take legal action where this information is divulged to third parties without our written consent
or in circumstances that may cause us commercial harm.
The operation of this equipment requires training and experience in electric meter testing. The information
in this Operations Manual is designed to supplement existing knowledge and experience already attained
and practiced by journeyman-level meter test technicians. Novice meter test technicians should not
attempt to operate this equipment without first gaining the basic knowledge of meter testing and the
application of meter testing equipment from a certified training course.
Table of Figures
The Radian Research, Inc. Bantam Plus Portable Test System is designed for fast
and accurate testing of electricity meters. The Bantam Plus combines advanced
capabilities of an automated meter socket, the accuracy of a Radian reference
standard as well as the embedded Winboard automated test software to provide a
lightweight, easy-to-use test system.
6
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
The RB-2X Bantam Plus Portable Test System consists of the main components
shown below in Figure 1.
display.
Status Indicators
Automated Meter Test Socket
7
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
1.2 Optional Accessories
Optional accessories and routine maintenance kits are available for the Bantam Plus
these include the following:
8
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
RB-MOUNT Frame mount for Mechanical meter
orientation and wall mount capability.
See Section 2.2.1 for assembly and use.
9
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
RB-KYZIO Advance I/O KYZ Breakout Cable
Connects to Bantam Plus KYZ port.
10
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
1.3 Product Features
The RB-2X Bantam Plus Portable Test System offers the following features:
Integrated automated meter test socket.
Integrated pulse sensor.
3 Phase Test Current Output: 0.1 to 50 Amps.
Phase control: 0 – 359.95 in 0.05 steps.
Synthesized Voltage Output: 69 V to 480 V.
Integrated PC controller running Winboard software.
Supported Meter Forms - 1S, 2S, 3S, 4S, 5S, 6S, 8S (electronic), 9S, 10S,
12S, 13S, 14S, 15S, 16S, 25S, 26S, 29S, 35S, 36S, 45S, 46S, 56S, 66S, 96S
Optional CT, Burden testing.
Lightweight.
The RB-2X Winboard Automated software is used to run tests, assign sensors, set
meter form test sequences and view and store test results. The RB-2X Winboard
Automated Software offers the following features:
Touch Screen interface
USB and Ethernet Interface
Create/Edit test sequences for meter forms
Align Optics
Standards Compare test routines
Storage capacity is limited by the installed 60GByte solid state hard drive.
Create/Edit test reports
Maintain customer records
11
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
1.4 Safety Information
Review the information in this section to avoid injury and prevent equipment
damage. The Bantam Plus was designed with safety in mind. The RB-2X socket will
not energize unless a meter is first installed. An Interlock switch will disable the
sources should a meter inadvertently be removed from the socket.
! WARNING
! CAUTION
Do not use this equipment for any purpose other than for which it was
designed.
Do not operate the equipment outside of the environmental conditions
specified in this manual.
Do not operate this equipment with covers or panels removed.
Keep equipment surfaces clean and dry.
Handle the RB-2X Bantam Plus Portable Test System with care; it is a
precision instrument.
12
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
Inspect the equipment before each use. Do not use the equipment if damage is
observed.
Use only cables provided by Radian Research, Inc.
The following safety symbols appear on the RB-2X Bantam Plus Portable Test
System:
Warning: Refer to
Operations Manual
The following conventions are used in this Operations Manual to highlight important
information:
13
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
1.5 Specifications
Operational
Physical
Electrical
Environmental
Temperature range −10º to 50º C (4º to 122º F) operating , −20º to 70º C (-4º to
158º F) Storage
Relative humidity 5–95% non-condensing
Shock and vibration Any which is nondestructive
Water resistance IP20
Supplied Cable
14
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
1.5.2 RB-2X I/O Connection
The I/O connection panel contains three different connectors, each suited to a
particular type of optics for external meter test.
Port 1
Port 2
A REDEL® connector is reserved for optical accessories
including magnetic mount and band mount optics such
as the RB-MAG and RB-IRDS
Port 3
AUX
The AUX port is designed for connection to optional socket
adapters including the RB-TSBR1 CT Ratio & Burden
adapter.
15
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
Advanced I/O
This connector is assigned for testing meters with KYZ
(Model RB-KYZ10). The Advanced I/O connector provides
many capabilities for the testing of solid state meter. It can
accommodate up to six Form A contact inputs or four Form C
and two Form A contact inputs. For outputs, it has one
programmable output allowing 0.01 to 40 seconds between
contact transitions and a quantity of pulses (1 to 4094) to
output. In addition two outputs can be software set high or
low. There is also an unregulated 12VDC output. The
following illustration depicts the connection diagram of the
advanced I/O connector.
IOIOIO
USB
Two USB connectors are available for use with peripherals
including memory drives, remote keyboard or mouse,
wireless adapters, etc.
Ethernet
10/100 Ethernet connection that can be used to connect the
Bantam Plus to a local area network.
16
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
2.0 Operation Preparation
This chapter provides information on preparing to use your RB-2X Bantam Plus
Portable Test System and contains the following sections:
2.1 Getting Started
2.2 Operational Considerations
Thank you for purchasing this quality Radian Research, Inc. product. Radian
reference standards are recognized throughout the world for their unparalleled
accuracy, precision, and stability. We have taken every effort to ensure that your
RB-2X Bantam Plus Portable Test System reaches you in perfect condition.
Your satisfaction is very important to us, and your continued loyalty is greatly
appreciated. If for any reason your Radian product does not meet your expectations
of exceptional performance, please contact your sales representative or Radian
Research, Inc.
Radian Research, Inc.
3852 Fortune Drive
Lafayette, IN 47905 USA
Tel: (765) 449-5500
Fax: (765) 448-4614
Email: radian@radianresearch.com
Website: www.radianresearch.com
17
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
2.1.2 Preparing Equipment for Use
Follow these steps to prepare your RB-2X Bantam Plus Portable Test System for
use.
1. Unpack and inspect:
Carefully remove the equipment from the packaging, and check for any signs
of damage.
18
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
3. Information about your equipment software:
Your new Bantam Plus is shipped with Winboard software installed. In
addition, the Bantam Plus will arrive with a WATT-Net PC Software
(Base Version) CD. When installed on an external PC WATT-Net can be
used for import/export data management. This base software is supplied
with generically define fields. If you wish to customize the fields or are
already using WATT-Net within your organization you may purchase
optional customization packages. For more information on customization
contact your Radian representative or Radian directly at 765-449-5500.
19
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
4. Register your equipment (see Section 2.1.3, Registering Your Equipment) to:
Activate the equipment warranty.
Receive firmware and software updates as well as product application notes
from Radian Research, Inc.
20
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
2.1.3 Registering Your Equipment
Follow these steps to register your RB-2X Bantam Plus Portable Test System:
1. Navigate to www.radianresearch.com/reg.
2. Complete the online form.
The model number is either RB-20 or RB-21 and is found on nameplate.
The serial number can be found on the nameplate as shown in Figure 3.
Figure 3 RB-2X Bantam Plus Portable test system rear panel nameplate containing
equipment serial number
21
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
2.2 Operational Considerations
To protect the RB-2X Bantam Plus Portable Test System and ensure optimal
performance, follow these guidelines:
Placement: When placing the RB-2X Bantam Plus Portable Test System for
use, avoid very wet or dusty environments.
Cooling: When placing the RB-2X Bantam Plus Portable Test System for use,
do not block the cooling vents on the front and back as shown in Figure 4.
Power: The RB-2X Bantam Plus Portable Test System requires a source
capable of providing at least 250 W of continuous power to operate correctly.
22
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
2.2.1 Operational Considerations for Testing Electro-mechanical Meters
Electro-mechanical meters will exhibit large errors if inserted into the Bantam Plus socket
while in the normal test orientation. Use of the RB-MOUNT accessory will enable correct
orientation for electro-mechanical meters. Furthermore, the RB-MOUNT can be used to
attach the Bantam Plus to a wall or truck using the key holes found on the RB-MOUNT
assembly.
Key holes for
vertical mount
Wire form meter retainer
Bubble level
To assemble the RB-MOUNT to a Bantam Plus first release the retaining nuts securing the
Tee Bar on the RB-MOUNT.
a) Fully extend the Tee Bar and mount the assembly as shown in the following
image.
b) The Tee Bar should fit snuggly into the recess above the front fan filter and the
rear of the mount should fit over the rear lip below the fan exhaust.
c) Next loosen the two screws found at the rear of the Bantam Plus meter socket.
Securely assemble the Wire form Meter retainer clip and retighten screws.
d) The retainer clip is required to prevent some large electro mechanical meters from
falling out of the Bantam Plus meter socket while in the vertical position.
e) Finally, there are two feet that can be adjusted to level the mechanical meter in a
vertical orientation for testing.
23
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
Assembled wire
form meter
retainer clip
Adjustable feet
The following is guidance on how to test electro-mechanical meters using the RB-
MOUNT.
1) Insert an ‘Adjust Optics (AO)’test step as step 1 of the test sequence. Set ‘Revs’
for 5 revolutions.
2) Create a special electro-mechanical test sequence for full load, light load and
Power Factor testing.
3) Insert the electro-mechanical meter into the test socket and position the sensor
before orienting the Bantam Plus into the vertical position.
4) Start the test sequence – while the Bantam Plus is running the first Optics Adjust
test step orient the Bantam Plus into the vertical position and level.
5) Once the Optics Adjust test has detected the programmed number of ‘Revs’ the
Bantam Plus will automatically begin the first meter test.
24
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
2.3.0 RB-BPH Optional Carry Harness Attachment
The optional RB-BPH Carry Harness assembly is available to provide a comfortable carry
position for long distance travel. The following RB-BPH instructions describe how to
attach to the Bantam Plus;
Step 1 Remove the three screws indicated below and retain in a safe place.
Remove side
mounts screws
and retain in a safe
place.
Step 2 Align the holes of the RB-BPH with the holes in the case and use the three
retaining screws and washers supplied with RB-BPH to fasten to the side of Bantam Plus
as shown below.
25
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
Step 4 Adjust any of the six strap lengths for a comfortable fit around torso and shoulders.
The unit should fit securely to the back at or above the waist line. Care should be taken
while maneuvering to ensure stability is maintained at all times.
The optional RB-TSBR1 Current Transformer Test module provides a solution to testing
metering CTs on-site. The following steps describe how to operate the RB-TSBR1.
26
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
Step 1 – The Bantam Plus can be switched OFF or ON during the installation process. If
switched ON, ensure that the CT Application is not active by switching to the Main Menu.
Step 2 - Install the RB-TSBR1 into the Bantam Plus socket and connect the AUX cable to
the Bantam Plus AUX socket.
Step 3 – A choice of primary current clamps are available from Radian Research. For CT
Ratio measurements, connect a suitable current clamp to the RB-TSBR1 Clamp-on
Transformer input.
Step 4 – Connect the Test Switch safety probe to the CT secondary via the test switch.
Step 5 – Connect the Red (fused) connector to the Service Voltage. Connect the Green
wire to a suitable ground.
After connecting the RB-TSBR1 unit to the test switch, you're ready to set up the test. At
the end of the test cycle, all the results will be saved at once. To begin:
Step 2 – Click CT Testing on the Startup screen. A screen like this appears:
27
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
You'll notice that Nameplate Ratio is already populated. This information is
pulled from the Site Information you loaded earlier. If you have not used Site
Information, you will need to perform the following steps.
Step 3 – Enter the nameplate ratio of the current transformer being tested in the Nameplate
Ratio Field.
Step 5 – Place a check in Phases A or B or C by clicking the color coded box. This
indicates that you'll be testing the specified phase of the current transformer.
Again, you'll notice that Serial No., Model No., and Class are already filled. If
you didn't use site information, you would need to perform the following steps:
Step 8 – Enter the serial number of the current transformer being tested in Serial No.
Step 9 – Enter the model number of the current transformer being tested in Model No.
Step 10 – Enter the accuracy class of the current transformer being tested in Class.
Step 11 – Repeat steps 5-10 for each phase being tested. To select the current transformer
information for a different phase, select the tab for that particular phase in the Current
28
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
Transformer Information area.
For example, if you are testing Phase A, B and C, then after performing steps 1–3 for the
A phase tab you will repeat them under the Phase B tab and then again under the Phase C
tab. But since you used a site information based workflow, you can go straight to testing
the current transformer.
The Edit Current Transformer Test Results screen appears. It will look something
like the following screen:
Test results are arranged in order based on the date/time stamp and serial
number of the current transformer entered during the current transformer
test. Each burden step for each phase is saved as a separate record and
includes all the information you entered in addition to the percent change,
accuracy result, and test date.
29
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
3.0 Product Features
This chapter provides detailed information on the product features of the RB-2X Bantam
Plus Portable Test System and contains the following sections:
3.1 RB-2X Components and Controls
3.2 RB-2X Automated Software Controls
The components of the RB-2X Bantam Plus Portable Test System top panel are explained
below.
1. Line Voltage ON/OFF 5 Ampere Breaker Switch: Used to power and protect the
Bantam Plus.
2. Front Panel Power indicator: Indicator light that glows blue when the RB-2X
Bantam Plus power is on.
3. Front Panel Voltage & Current Indicator: Red and Yellow LEDs will activate
when Voltage and/or Current is applied to the integrated meter socket.
30
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
4. Pulse Detection Indicator: LED will flash green when a meter pulse is detected. A
visible pulse sensor detection LED is duplicated within the integrated sensor head.
5. Volume Control: The Volume Control Keyboard is used to control the volume of the
audible pulse the unit generates to echo pulses detected when conducting a meter test.
The keys on the left and right lower and raise the volume respectively. Pressing the
mute key will light the blue LED within the key indicating that the unit is muted.
6. Ports 1, 2 & 3: Ports 1 thru 3 are each suited to a particular type of optics. The
connector.
‘Port 1’ is reserved for an Optocom (RB-Optocom) cable. Optocom Optics allows the
operator to not only detect pulses from solid state meters, but also allows the operator
to program the meter without changing the optical head. This connector may also be
used for custom pickups as required. Contact Radian for any special needs that may
not be met by the standard set of pickups.
‘Port 2’ is a REDEL connector reserved for a wide variety of optional optics
accessories, including clamp-on, suction-cup and magnetic based reflect solid state
optics.
The red LED on the integrated Sensor ProTM optics sensor provides a visual indication
that the unit has detected a pulse.
‘Port 3’ is a BNC connector reserved for an optional click-switch adapter that is used
when other optics aren't suitable. The BNC connector is also used when conducting a
standards compare test.
During normal testing when Input 3 is not the source this connector also outputs a test
pulse for calibration purposes.
Inter
nal
fans
7. Advancedmay I/O: The Advanced I/O connector provides many capabilities for the
testing of not
solid state meter. It can accommodate up to six Form A contact inputs or
four FormactivC and two Form A contact inputs. For outputs, it has one programmable
output allowing
ate 0.01 to 40 seconds between contact transitions and a quantity of
pulses (1 towhe 4094) to output. In addition two outputs can be software set high or low.
n an unregulated 12VDC output.
There is also
swit
chin 31
5-15 944018.3 BantamgPlus Operations Manual
Radian Research, Inc.
line
volt
age
8. Serial Interface: The RS232 serial interface connector is a multi-function input
connector that can be used for a variety of accessories including a barcode scanner.
9. USB Interface: USB ports located one above the other. These can be used for
connecting an optional keyboard, mouse or other USB device.
10. Ethernet Interface: A 10/100 Ethernet connection that can be used to connect the
Bantam Plus to a local area network. This can be very useful for transferring test
results from the Bantam Plus to a central database.
32
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
3.1.2 Touch Screen Display
The Bantam Plus touch screen allows you to make selections in the software without
the need for a keyboard or mouse. Touch the display to make selections, or even type
in data using the touch screen keyboards (see Figures 6,7,8).
34
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
4.0 Operations Overview
This chapter provides general instructions for using the RB-2X Bantam Plus Portable
Test System and contains the following sections:
4.1 Connecting the Bantam Plus
4.2 Conducting a Meter Test with the Bantam Plus
4. Plug the black cable coming from the Field Power Cord into the black
connector on the rear panel of the Bantam Plus.
5. Clamp the Field Safety Ground Cable to the meter block ground lug.
6. Clamp one lead from the Field Power Cord onto the neutral lower side test
switch. Clamp the other lead from the Field Power Cord onto the phase A
lower side test switch.
7. When the last connection is made and the switch/breaker is turned on the unit
will power up and the Bantam Plus software will automatically launch.
36
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
4.2.1 Conducting a Meter Test with the Bantam Plus Integrated Socket
Follow these steps to conduct a Form 2S Meter test with the RB-2X Bantam Plus
Portable Test System:
1. Power the Bantam Plus using the instructions described in section
4.1.1 or 4.1.2. You will hear an audible tone three times from
internal RD Reference Standard during power-up this indicate the
internal reference standard is operational.
2. See Figure 9 for a Bantam Plus screen tour.
3. For the purpose of this exercise we will assume no ‘Profiles’ have
been created. Select ‘METER TEST’
Profile TAB – accesses
addition profile pages. A
Select Main Menu Tab to view
maximum of 30 profiles can
additional ‘Administration’
be assigned by the operator.
and ‘Utilities’ Application
Icons
37
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
4. Bantam Plus will implement an initialization sequence. Before
proceeding with a meter test verify the Kh is correct for the meter
under test. The optics should now be aligned.
Adjust Optics
Review ‘Status line’
information before and
during a meter test
ensures Bantam Plus is
ready and operating
correctly. 5. Figure 10 Bantam Plus Meter Testing Screen
38
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
A secondary Pulse LED can also be viewed on the
NOTE display bezel. Pulses are also registered using an
audible beep. Un-mute and increase the volume
using the Bantam Plus keypad found below the
display. For high Kh the sensor pulse duty cycle
may be long.
8. Verify the Meter form and Kh value is correct. Review the test
sequence for appropriate steps before selecting the ‘Start’ soft key.
9. Select start and validate the Voltage and Current LEDs on the front
display bezel are active.
Indicate source
Revolutions or Pulses
Voltage, Current and
remaining in current
Phase applied to meter
test Step.
39
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
If a run is repeated the data from a second test will
NOTE populate the “AS LEFT” field.
10. To cancel a meter test at any time select “CANCEL” from the display softkey.
11. Results may be viewed from the Administration Application see section 5.1
40
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
4.2.2 Meter Test using Meter Test Adapter RB-MTA, RB-MTA-BN or RB-
MTA-DB option
Before using the RB-MTA Adapter set the Meter base to ‘T’ (T Base) in the Test Sequence
screen as seen in Figure 13 below. T Base is unique to using the RB-MTA Adapter. The correct
Voltage routing for the T base can be configured for any specific meter form by selecting the
Administration Icon followed by ‘Edit Meter Setup’ and ‘Socket Power Setup’ icon as
shown in Figure 14.
1. Connect the Bantam Plus Ground connection to a suitable ground at the Meter housing
assembly or test panel.
2. Connect the RB-Field Power cable to the service voltage, ensure not to exceed 300V.
3. Before powering on the Bantam Plus ensure that the Meter Test Adapter is inserted into
the Bantam Plus meter socket. Orientation of the MTA to the socket is important. The
MTA adapter cables facing to the rear of Bantam Plus.
4. Connect the RB-MTA to the meter test switch. Care should be taken to ensure the
elements are correctly matched for the meter under test and the meter test switch used.
For more details on the different meter forms and their pin outs refer to the ‘MTA
Connection Guide’.
5. Connect a suitable external pulse sensor to either Port 1, 2 or 3.
6. Power ON the Bantam Plus and wait for initialization.
7. Select the appropriate Meter Form and test sequence.
8. Begin ‘Adjust Optics’ Test from within the Meter Test Application to align the external
pulse sensor to the meter.
9. Select ‘Start’ to begin meter test.
10. On completion of meter test power down the Bantam Plus and remove the cables from
the meter test switch.
11. Finally remove the ground cable from the meter test box.
42
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
Figure 14 Socket Voltage routing for the RB-MTA Adapter Form
43
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
Each sequence will have voltage, current, and phase angle in the sequence. Every Sequence must
have voltage for reference purposes. Add current and phase angle only as needed.
There will be three tabs at the top of the page: Setup, Testing, and SCADA.
Fill out the information on the Setup tab from the faceplate of the transducer.
This information can be preloaded using Site Information.
As an example set up a single element Watt test with a transducer with the following faceplate
information — Output: 0 to 1.2 mA, Max input: 120V, 5A, and Scale: 0 to 600W.
3. From the Type box select Watts - 1 elm.
4. In Output enter 0 and 1.2.
5. In Metric Scale enter 0 and 600.
6. Leave the CT and PT Ratios set to 1 and 1.
7. In Serial # enter 123456
8. In Company # enter RADIAN.
9. In Manufacturer enter (xxxxxxxx).
10. In Model enter 2206C.
45
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
RADIAN
12. Click on the Test Sequence box and select the test sequence you wish to run. In this case,
select the test sequence created earlier.
13. To customize the test sequence, use the scroll bar at the bottom of the screen, scroll to the
right and make any necessary changes. All of these fields can be edited on this screen or
in the test sequence editor. See "Creating a Transducer Test Sequence" on Page 40.
14. Click Options to open the Transducer Test Options window.
46
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
15. Choose a test mode. Selecting Normal Mode runs the test through the entire test sequence
before stopping. Selecting Pause Mode will stop the test after each step with voltage and
current still applied. It will not continue to the next step until you click Start. If you need
to document the SCADA readings we suggest you select Pause Mode.
16. Select delay rates. There may be some delay time necessary for the transducer to begin
outputting valid data before each test step. Start Delay is the amount of time before the
first test step begins. Settle Delay is the amount of time between subsequent test steps.
Note that 1000ms = 1sec. In this example we have set the Start Delay to 0, and the Settle
Delay to 3000.
17. Select how you want the transducer test results displayed by selecting one of the options
in the Results Display area. In this example we've selected % Error of Reading.
18. Click OK to confirm your options.
19. Now connect the cables to the transducer.
20. Using the Bantam Plus with RB-MTA adapter voltage and current leads, connect voltage
and/or current to the transducer as needed.
21. Connect the analog sense cable to the transducer output. Black to +. White to -. Connect
the other end of the analog sense cable to Pulse Input 1 on the Bantam Plus.
47
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
22. At the top of the screen click Start to run test. The transducer test will run. Notice that
a. Accuracies inside the defined limits show up highlighted in green, and
b. Accuracies outside the defined limits show up highlighted in red.
23. Click Save at the top of the screen to save the test data. The data will be saved by site
name and by serial number.
48
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
If you need to document any SCADA (Supervisory Control
NOTE and Data Acquisition) follow the steps below
If you need to document any SCADA (Supervisory Control and Data Acquisition)
readings, use the pause mode. This will pause the test after each test step. Voltage and
current will still be applied when paused. Then click the SCADA tab.
The instantaneous results continuously update every 0.5 seconds. These readings can be
compared to the SCADA readings and documented. If a value is entered into the SCADA
readings area, it will be saved when Start is clicked, and the test moves on to the next step. These
values are optional, and you do not have to enter a value into this field. If no value is entered,
nothing will be saved in the SCADA fields for that test step.
Another use for the SCADA tab can be to adjust your transducer. You can select a test step, click
Adjust Optics, and then go to the SCADA tab to see the instantaneous input and output values.
Then the transducer can be adjusted (with a trim pot) to desired values. You can also return to
the Testing tab, select another step, and click Adjust Optics again, and it will automatically
adjust the values for that row. You do not need to cancel the test each time you want to update
the values.
49
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
5.0 RB-2X Administration Application
This chapter describes the Administration Application structure of the RB-2X and
contains the following section:
5.1 Administration Overview
5.1.1. Edit Form Defaults: Bantam Plus is supplied with all ANSI forms
already defined. ‘Edit Forms’ allows you to customize settings for
specific meter forms.
5.1.2 Edit Test Sequences: to view, add, edit, delete, import or export test
Sequences.
50
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
5.1.3 View/Edit Test Results: allows the operator to access test results that
have previously been saved to the Bantam Plus.
5.1.4 Edit Customer List: allow you to build a customer list to keep track of
test results for multiple meters with different ownership. Only test results
saved for the current customer will appear in the View/Edit Test Results
screen.
5.1.5 Edit DataView & Import Export Options: allow you to customize the
data view screen and establish how to define custom field names for
imported or exported data. Data import/export is performed using the
supplied WATT-Net software.
5.1.6 Edit Drop Down Code: is used to customize the valid values associated
with a field defined in the Edit DataView and Import/Export Setting
screen. An example of codes defined in the Edit Drop Down Codes
screen would be a list of valid manufactures that can be selected at the
test time from a drop down list.
5.1.7 Edit Barcode: screen provides access to the editors necessary to set up
the Bantam Plus barcode reading functionality. From the Edit Barcode
screen you can edit the barcode table, define custom barcode labels, and
edit manufacturer codes.
5.1.8 Edit Meter Setup: screen allows you to customize many important
power generation functions.
5.1.9 Options: screen allows you to change the displayed color scheme and
Network Options including TCP/IP address.
51
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
6.0 RB-2X Utilities Application
This chapter describes the Utilities Application structure of the RB-2X and contains
the following section:
6.1 Utilities Overview
52
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
6.1.1 Standards Compare: allows the operator to perform an automated comparison of the
Bantam Plus internal reference with an external reference standard. Option RB-SCA will
be required for this function. For more detail on how to perform a Standards Compare
view the video posted at www.radianresearch.com/videos and section 8.3.4.
6.1.2 Run Sinewave Editor: Bantam Plus generates sine waves with low THD. To simulate
real world phenomena the source is capable of generating voltage and current
waveforms with harmonic content.
6.1.3 External RD Comm: enables an external PC to communicate directly with the internal
Reference Standard.
6.1.4 Remote Control Desktop Settings: enables a remote desktop to control the Bantam
Plus via Ethernet.
6.1.5 Remote Assistant: enables operator to request remote assistance.
6.1.6 Updates Back-up and Restore: enables the operator to check for software & firmware
update, restore Windows settings, back-up files.
53
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
7.0 RB-2X Site Information Application
This chapter describes the Site Information Application structure of the RB-2X
and contains the following sections.
7.1 Site Information Application Overview
54
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
7.1.1 Edit Site Information: allows the operator to add or edit site information.
7.1.2 Load Site Information: allows the operator review, edit previously saved site
information.
7.1.3 Site Report: allows the operator to select, review and print a site report.
Figure 18 View of the Meter Test screen with the Data View
enabled to view or edit Meter information.
55
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
8.0 Routine Maintenance and Service
This chapter contains the following sections:
8.1 Contact Information
8.2 Routine Maintenance
8.3 Service
8.4 Helpful Documentation and Resources
For questions related to maintenance and service, contact Radian Research, Inc.:
Radian Research, Inc.
3852 Fortune Drive
Lafayette, IN 47905 USA
Tel: (765) 449-5500
Fax: (765) 448-4614
Email: radian@radianresearch.com
Website: www.radianresearch.com
The RB-2X Bantam Plus Portable Test System is requires the following routine
maintenance:
Frequency Activity
Before each use Inspect the test cable for damage.
Check the air filter is clean.
Before storing the Wipe exterior surfaces with a dry, soft cloth to
equipment remove dust and dirt. Do not use solvents to
clean plastic surfaces.
Yearly Calibrate the Bantam Plus.
56
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
8.3 Service
8.3.1 Service
The Bantam Plus equipment is designed for testing meters and used as part of your
organization's quality control system. The procedure below outlines the limited parts
that are customer replaceable.
Over extended use, the current carrying socket jaws may foul with contaminates
such as oil or grease and no longer produce the contact necessary to operate to
specification. The following procedure describes how to periodically clean or
replace these jaws.
Step 1. Ensure the Bantam Plus is switched off and isolated from line voltage.
Step 2. Remove the five Torx drive screws from the socket cover.
Step 3. Remove the socket cover to expose the socket assembly.
Step 4. Note that each current conductor has a replaceable liner. Clean each liner
using compressed air being careful that all loose debris is removed. Should oil or
grease be present, remove the liner from the Bantam Plus before using oil based
solvent for cleaning.
57
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
Step 5. If necessary liners can be replaced using of RB-SMK Socket Maintenance
Kit available from Radian Research.
Step 6. Before replacing the socket assembly cover, ensure that the socket assembly
dividers found on the base of the socket assembly cover sit either side the voltage
conductors. Failure to do so could result in bending the voltage conductors
preventing a meter insertion. Replace the socket assembly cover and retighten the
five Torx screws.
Step 7. Perform a Standards Compare to validate the performance using Standards
Compare information found in section 6.1 and 8.3.4.
Removable socket
liners
Radian Research, Inc. warrants that each product is free from defects in material and
workmanship. Our obligation under this warranty is to repair or replace any
instrument or component therein that, within two years after shipment and with
58
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
normal use, proves to be defective upon examination.
60
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
Each current cable is color coded in pairs and terminated with a Red or Black 6mm
locking banana plug. Connect each pair to the external Reference standard paying
attention to the phase orientation. Connect the current cables marked with the Red
band to the RD Phase A Input, connect the Yellow band cables to the B phase and
the Blue band cables to the C phase inputs on the RD. The red and black 4mm
banana plugs to the RD-2X Potential inputs. Connect a BNC cable between the
Bantam Plus Optics Port 3 and the RD-2X Port 2. Finally connect Line Voltage to
the RD-2X AUX Input to power the RD standard.
Standards Compare
To configure the Bantam Plus for Standards Compare go to the ‘Main Menu’ and
select the ‘Utilities’ Icon. Within the Utilities screen select the ‘Standards Compare’
icon and select ‘Run Standards Compare’
The Bantam Plus is supplied with a default Standards Compare test sequence. Note:
the default test sequence is developed for a RB-20 (0.04%) Bantam Plus. Before
running a Standards Compare with RB-21 (0.02%) Bantam Plus the test sequence
must first be edited to change the test tolerance upper and lower limits to + 0.02%/-
0.02%. To do this select ‘Utilities’ and select ‘Edit Standards Compare’
Enter the external RD serial number into the Ext. Standard SN field. Select Ext.
Standard: to ‘1 Phase’. Select Start to begin the standards compare. When the test
sequence is complete select Save to save the test results. To view the test results
61
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
select ‘View Standards Compare Results’ icon and load the appropriate results
that are date and time stamped for convenience.
Once connected to the network select, ‘Utilities’, ‘Update Backup & Restore’.
To confirm and update the Bantam Plus software version relative to the latest
available, select ‘Check For Updates’ Then follow the onscreen prompts to update
the software.
62
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
Once the software update process is complete, rerun the ‘Check For Updates’ feature
to confirm that the software versions installed match the latest available.
63
5-15 944018.3 Bantam Plus Operations Manual
Radian Research, Inc.
8.4 Troubleshooting
Question: I’m trying to measure a GE KV2c meter accuracy using the Bantam Plus integrated
pulse sensor. The first result is inaccurate, yet I know my meter reads correctly when using other
test methods.
Solution: It sounds like the meter might be pulsing before or during the first test. This may be
due to fact that the meter is delivering communication data to the adjacent optical output port
after being powered on. A solution, is to add an ‘Optics Adjust’ or ‘Creep Test’ as the first
sequence test point. This will cause the meter to complete its power-up cycle and cease