Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

CONSTRUCTION PROCEDURE Doc No : 7T04-CS-00-PC-011

Rev. : 13
FOR Page : 1 of 9
ALLOY STEEL PIPING Date : 17. OCT. , 2013

CONSTRUCTION PROCEDURE

FOR

ALLOY STEEL PIPING

PROJECT NO. : 7T04

PROJECT NAME : ERC Refinery Project

COMPANY : Egyptian Refining Company (TAKRIR) S.A.E.

SITE : Mostorod, Egypt

13 17.OCT, 2013 Revised as Noted S.S.Kim B.G.Min S.M.Hong K.H.Min

12 15.MAY, 2013 Revised as Noted S.S.Kim B.G.Min S.M.Hong K.H.Min

11 09.APR, 2013 Revised as Noted S.S.Kim B.G.Min S.M.Hong K.H.Min

10 10.APR, 2009 Revised as Noted S.S.Kim B.G.Min H.J.Lee S.S.Ahn

0 25.FEB, 2009 For Approval S.S.Kim B.G.Min H.J.Lee S.S.Ahn

REV. DATE DESCRIPTION PREPD CHKD CHKD APPR REVD DATE


(P/M)

CONTRACTOR COMPANY

SEOUL, KOREA
CONSTRUCTION PROCEDURE Doc No : 7T04-CS-00-PC-011
Rev. : 13
FOR Page : 2 of 9
ALLOY STEEL PIPING Date : 17. OCT. , 2013

TABLE OF CONTENTS

1 SCOPE -------------------------------------------------------------------------------- 3

2 MATERIALS ------------------------------------------------------------------------ 4

3 GENERAL --------------------------------------------------------------------------- 4

4 FABRICATION --------------------------------------------------------------------- 4

5 WELDING --------------------------------------------------------------------------- 5

6 PREHEATING ---------------------------------------------------------------------- 7

7 POSTWELD HEAT TREATMENT --------------------------------------------- 8

8 INSPECTION ----------------------------------------------------------------------- 9

9 PRESSURE LEAK TESTING ---------------------------------------------------- 9


CONSTRUCTION PROCEDURE Doc No : 7T04-CS-00-PC-011
Rev. : 13
FOR Page : 3 of 9
ALLOY STEEL PIPING Date : 17. OCT. , 2013

1 SCOPE

1.1 This Procedure covers the minimum requirements for fabrication, inspection and testing of piping made
from C-1/2Mo, chromium-molybdenum alloy steels, 12Cr stainless and austenite stainless steels of the 18-8
type for the ERC Project job site construction, Mostorod, Egypt.

1.2 The SUBCONTRACTOR shall comply with all the specification and procedure requirements unless a
change or deviation is approved by CONTRACTOR’s and COMPANY’s representative in writing.

1.3 DEFINITION
- COMPANY ; ERC( Egyptian Refining CO.,) and PMC (Project Management Consultancy; Worley
Parsons)

- CONTRACTOR ; GS E & C ( GS Engineering & Construction CO.,)

- SUBCONTRACTOR ; The Party(s) which carry(s) out all or part of Design, Procurement, Installation,
and Testing of the piping system as specified by CONTRACTOR.

1.4 RELATED CODES AND SPECIFICATION AND PROCEDURE

The following code and specification are applicable.


ASME B31.3 : Process Piping
ANSI/ASME B 1.20.1 : Pipe Threads, General Purpose
ASME/ANSI B 16.5 : Pipe Flanges and Flanged Fittings
ASME Boiler and Pressure Vessel Code, Section V
7T04-MP-00-TS-004 : Piping Material Specification and classes
7T04-MP-00-TS-012 : Piping Support
7T04-MP-00-TS-013 : Fabrication and Installation Detail Drawings for STD Piping
Support
7T04-CS-00-TS-001 : Painting
7T04-CS-00-TS-003 : Pipe Welding and Welding Inspection
7T04-CS-00-TS-016 : Field Pressure Testing of Piping
7T04-CS-00-PC-009 : Piping Construction Works
7T04-CS -00-PC-013 : Piping Pre-Fabrication
7T04-CS -00-PC-016 : Socket and Seal Welding of Small Piping Component
7T04-QA -00-PC-007 : Field Inspection and Test plan
CONSTRUCTION PROCEDURE Doc No : 7T04-CS-00-PC-011
Rev. : 13
FOR Page : 4 of 9
ALLOY STEEL PIPING Date : 17. OCT. , 2013

13 7T04-QA-00-PC-004 : PMI Procedure

2 MATERIALS

2.1 All materials shall be as shown on the drawings and specifications. No material substitution shall be made
without written approval by CONTRACTOR’s and COMPANY’s representative.

2.2 When materials are supplied by the SUBCONTRACTOR, prior to commencement of fabrication, material
test report, chemical analyses results and material certificates shall be submitted for approval.

2.3 Welding electrodes, filler wire and consumable inserts shall be in accordance with Specification 7T04-CS-
00-TS-003. Use of non-conforming electrodes must be authorized by CONTRACTOR.

3 GENERAL

3.1 Alloy piping shall be fabricated, inspected and tested in accordance with ANSI B31.3 Code for Process
Piping, unless otherwise specified in this Procedure.

3.2 The reference of Procedure Carbon Steel Piping,(7T04-CS-00-PC-008), Piping Construction Works,(7T04-
CS-00-PC-009) and Specification for Field Pressure Test of Piping,(7T04-CS-00-TS-016), also apply to the
alloy materials covered by this specification, except as otherwise specified herein.

3.3 Stainless steel Pre-Fabrication including material handing and storing shall be well separated for other steel
pre-fabrication works. Tool and equipment to be used shall be suitable for stainless steel and shall not be
used on any other materials.

4 FABRICATION

4.1 Edge Preparation

4.1.1 Edge preparation for welding shall be by machine cutting wherever practicable. If flame cutting is
employed, alloy steels shall be preheated at 149-315 . After cutting, the heat-affected zone shall be
ground or machined off for a distance not less than 3mm.
Flame cutting for stainless steel is not allowed.
CONSTRUCTION PROCEDURE Doc No : 7T04-CS-00-PC-011
Rev. : 13
FOR Page : 5 of 9
ALLOY STEEL PIPING Date : 17. OCT. , 2013

4.1.2 End preparation of groove for butt welding shall be as shown in Figure 4.1.2

Figure 4.1.2 Groove Design Tolerances for Use without Consumable Inserts

4.2 Bending

Neither hot nor cold bending shall be performed on alloy steel or stainless steel piping without special
written approval by CONTRACTOR and COMPANY. Normally, approved manufactured fittings shall be
employed in conformance with the piping specifications.

5 WELDING

5.1 Qualification of Welders

5.1.1 All welders shall be qualified in accordance with Specification 7T04-CS-00-TS-003.


CONSTRUCTION PROCEDURE Doc No : 7T04-CS-00-PC-011
Rev. : 13
FOR Page : 6 of 9
ALLOY STEEL PIPING Date : 17. OCT. , 2013

5.1.2 When a welder is to be qualified to weld austenitic stainless steels, carbon steel pipe may be used for
the test, but welding must be done with the same electrodes, filler wire and inserts required for the
pipe fabrication.

5.2 Welding Process & Electrodes

5.2.1 Welding Process and electrodes shall be in accordance with Specification 7T04-CS-00-TS-003.

5.2.2 Where is no specified for filler wire, it is acceptable use wires or welding rods of the same nominal
composition as the base material.

5.2.3 In welding alloy materials with low-hydrogen electrodes, it is essential that electrodes be stored in hot
boxes and be kept dry at all times. When working on field welds, portable hot boxes shall be used at
each welding location. Only a few electrodes at a time shall be taken from the hot box for welding.

5.2.4 Extreme care shall be taken not to mix up different alloy electrodes. Each portable hot box shall
contain only one type of electrode. Before any alloy electrodes are used approval from
CONTRACTOR’s Inspector shall be obtained.

5.2.5 When alloy electrodes are placed in the large stationery hot box, each type of electrode shall be in its
original container or in a separate metal box or compartment with the electrode identification clearly
marked on it.

5.3 Welding Technique

5.3.1 When pipe is in the horizontally-fixed position, welding shall be uphill. In GTAW of the first pass, the
head of the torch shall be positioned perpendicular to the joint, and the arc shall not exceed 3.2mm.

5.3.2 To start the root pass, the electrode shall be held stationary until a white globule appears on the
surface of the pool. After this occurs, the torch shall be moved at such a speed as to maintain the white
bubble at the arc point, generally 50-75mm per min.

5.3.3 If the arc is broken while making the root pass, welding shall be started about 2.5mm in back of where
the weld was terminated to fuse the crater, which normally contains defects.
CONSTRUCTION PROCEDURE Doc No : 7T04-CS-00-PC-011
Rev. : 13
FOR Page : 7 of 9
ALLOY STEEL PIPING Date : 17. OCT. , 2013

5.3.4 When completing the root run the white bubble shall be maintained until there is an overlap of about
6mm from the start of the weld. The bubble must then the welded out of the pool by moving the torch
towards the side of the prepared joint to the outside wall of the pipe where the arc is broken.

5.3.5 The argon flow rate for the welding torch shall be sufficient to prevent oxidation and porosity. Good
protection shall be provided against wind to assure that there is no loss of the shielding gas during
welding.

5.4 Argon Back Purge

5.4.1 An argon back purge shall be used during GTAW. The pipe shall be scaled for the purge with heavy
cardboard dams unless otherwise specified. Generally a flow rate of about 4 to 6 liters per minute is
required. The required amount depends upon the sealing condition. Inadequate purging will result in
oxidation and a rough appearance of the weld internally, which are not acceptable.

5.4.2 When GTAW is used for field welds, where it is not practical to purge the entire line, a small opening
shall be made in the fusible insert at the top of the weld to permit argon purge gas to enter the pipe.
The dams shall be positioned prior to fitting up the pipe, and they shall be located about 150mm from
the weld to prevent burning, melting, or other damage to dams from the heat of welding. Whenever
preheating is used, this distance should be increased to keep the metal temperature at the dam no
higher than 150 .

6 PREHEATING

6.1 Unless otherwise specified, molybdenum or chromium-molybdenum steels and 12Cr stainless steels shall be
preheated at 200-315 for all welding, including tacking and repair welding. Preheating shall be performed
by torch heating with propane burners is acceptable provided that the temperature is maintained properly.
Any preheating shall be applied as all round as possible, avoid hot spot. The preheat temperature shall be
kept the same as preheating temperature during welding. Thus, when torch heating is used, there must be
available for each weld either two burners with their own gas supply or one burner connected to a manifold-
gas-supply system.

6.2 The preheat temperature shall be checked with temperature indicating crayons, such as Tempilsticks. The
welder or welder's helper shall have the crayons with him at all times during welding, and he shall check the
temperature frequently to ensure that the preheat temperature requirements are met. In addition, the
SUBCONTRACTOR shall assign one person the sole responsibility of ensuring that preheat requirements
CONSTRUCTION PROCEDURE Doc No : 7T04-CS-00-PC-011
Rev. : 13
FOR Page : 8 of 9
ALLOY STEEL PIPING Date : 17. OCT. , 2013

are met at all times. It is essential that preheating be carried out faithfully to avoid cracking and other
problems which could result in failure.

7 POSTWELD HEAT TREATMENT

7.1 The post-weld heat treatment shall be in accordance with Specification 7T04-CS-00-TS-003.

7.2 Alloy Steels and Ferritic Stainless Steels

7.2.1 Molybdenum or chromium-molybdenum steels and 12Cr stainless steels shall be heat treated after
welding, as indicated in ANSI B31.3. Heating and cooling rates shall be 167 maximum per hour
from, or to 316 .

7.2.2 Heat treating shall be done with electric resistance or induction coils. The complete heat-treating cycle
shall be indicated on a chart from a multipoint recorder. For temperature measurements, at least two
thermo-couples shall be attached to each weld 180 degrees apart using an Inconel-type electrode, such
as Incoweld A, or Inconel filler wire with GTAW.

7.2.3 Preferably, the welded joint shall be heat treated immediately after welding without allowing the
metal to cool below the minimum preheat temperature.

7.2.4 After welding 5Cr-1/2Mo Steel or higher ferritic alloy steels, the weld shall be allowed to cool to the
13
200-315 preheat temperature range before final postweld heat treatment is applied.

7.2.5 When the intermediate treatment is used, temperature indicating crayons shall be used to ensure that
heating is within the specified range.

7.2.6 Prior to hydrostatic testing, the full postweld heat treatment shall be performed with exception of
13
hydro test vents and drains shall be postweld heat treatment after hydro test.
CONSTRUCTION PROCEDURE Doc No : 7T04-CS-00-PC-011
Rev. : 13
FOR Page : 9 of 9
ALLOY STEEL PIPING Date : 17. OCT. , 2013

8 INSPECTION

8.1 All Non-Destructive Examination shall be in accordance with Specification 7T04-CS-00-TS-003 and
Reference Procedure 7T04-CS-00-PC-009.

13 8.2 NDE

8.2.1 Welds shall be radiographed shall be as specified for specification 7T04-CS-00-TS-003 Table 1 extent
of NDE of pipe work welds.

13 8.2.2 Normally radiographic examination of alloy steels shall be performed after the completion of weld to
permit repairs to be made prior to the final heat treatment. All repaired areas shall also be
radiographed.

8.3 Hardness Testing

The hardness of all alloy steels shall be checked by CONTRACTOR for conformance with ANSI B31.3.
The maximum Brinell Hardness of the weld or heat-affected zone shall be 225 for C-1/2Mo and 1-1/4Cr -
1/2Mo steel and 241 for higher alloy steels.

8.4 PMI (Positive Material Identified)

13 8.4.1 PMI shall be performed in accordance with PMI Procedure (7T04-QA-00-PC-004).

8.4.2 PMI is intended to avoid the risk of receiving incorrect materials and missing material in fabrication
shop or construction site and ensure the correct materials used in the proper places.

9 PRESURE LEAK TESTING

9.1 Prior to initial operation, all installed piping system shall be pressure leak tested in accordance with
Specification 7T04-CS-00-TS-016.

You might also like