Activity Description Immediate Predecessor Duration (In Days)
Activity Description Immediate Predecessor Duration (In Days)
Project Network
B H I
Start A C F Finish
G
D
E
B 6 13 H 26 28 I 28 29
7 33 40 2 44 46 1 46 47
A 0 6 C 6 9 F 22 26
Start Finish
6 0 6 3 37 40 4 40 44
G 44 47
22 6 D
3 44 47
22 6 16
E 22 44
22 22 44
Therefore, the critical path is A-D-E-G with the total project time of 47 days to finish the
project. This would mean that A, D, E, and G are the critical activities and should be done
according to schedule or else it will cause a delay in the project. On the other hand, activity B
can be extended for another 20 days, activity C for 31 days, activity F, H, and I for 18 days
because they have slack time of 20, 31, and 18 respectively.