A promoter of championship boxing match must perform the task shown in the table before

the boxing match can held (all durations are in days).


 Construct the project network.
 Determine the critical path.
 Find the completion time of the project.
Activity Table
Activity Description Immediate Duration (in days)
Predecessor
A Find site - 6
B Find engineers A 7
C Hire announcer and A 3
referee
D Look for A 16
sponsorships
E Set TV and radio ads D 22
F Set up ticket agents B, C, D 4
G Print advertising E, F 3
H Set up transportation F 2
I Last minute details H 1

Project Network

B H I

Start A C F Finish

G
D

E
B 6 13 H 26 28 I 28 29
7 33 40 2 44 46 1 46 47

A 0 6 C 6 9 F 22 26
Start Finish
6 0 6 3 37 40 4 40 44

G 44 47
22 6 D
3 44 47
22 6 16
E 22 44
22 22 44

Activity ES LS EF LF Slack Critical Path


A 0 0 6 6 0 YES
B 6 33 13 40 20 NO
C 6 37 9 40 31 NO
D 6 6 22 22 0 YES
E 22 22 44 44 0 YES
F 22 40 26 44 18 NO
G 44 44 47 47 0 YES
H 26 44 28 46 18 NO
I 28 46 29 47 18 NO

Therefore, the critical path is A-D-E-G with the total project time of 47 days to finish the
project. This would mean that A, D, E, and G are the critical activities and should be done
according to schedule or else it will cause a delay in the project. On the other hand, activity B
can be extended for another 20 days, activity C for 31 days, activity F, H, and I for 18 days
because they have slack time of 20, 31, and 18 respectively.