Ref. No.

CKP/QC/ARCH/01/001

Description
Architectural Work Inspection Form
GENERAL: FLOORS

Name of Project : Location :

Drawing Ref. :

Date :

Acceptability
ITEMS ITEMS TO BE CHECKED Contractor JKR Remark
Yes No Yes No
1. FLOORS 1. Ponding not deeper than 3mm
a. Screed finish
2. Cracks not wider than 0.3mm

3. Hollowness should not be detected by


tapping

4. Falls in wet areas like kitchen and toilet should be in the


correct directions towards traps or discharge points

5. Expansion joints should be provided at interval


stated by Architect.

6. For staircases, the variance in lengths of threads


and risers must not exceed 5mm; nosing must be
straight

7. Eveness of surface (not more than 4mm per 1.2mm)

8. No mortar stains or paint drips

9. Surfaces should not be unduly rough or patchy

b. Tiled finish 1. Tile size should be consistent (within +/- 1%) or up


to 3mm variations

2. Surfaces are even and leveled to proper falls in wet


areas like kitchens and toilets

3. Joints are even and consistent with skirting and wall


tiles

4. Tiles should not but tightly with each other; joint size
2-4mm or otherwise stated by Architect

5. Chippings, cracks or mortar droppings should


not be present
6. Hollowness should not be detected by tapping
hard object on the floor

Ref. No. CKP/QC/ARCH/01/001

Description
Architectural Work Inspection Form
GENERAL: FLOORS

Name : Location :

Drawing Ref. :

Date :

Acceptability
ITEMS ITEMS TO BE CHECKED Contractor JKR Remark
Yes No Yes No
c. Timber strips 1. No cracks and warpage

2. Timber strips to rest firmly on joist or screed

3. No gaps in between timber strips

4. Edges of the floor to be properly sealed

d. Carpet 1. Stretched and even surface

2. Joint should not be visible

3. Proper anchoring at all edges

e. Raised floor 1. No mortar stains or paint drips

2. Eveness of surface (not more than 4mm per 1.2mm)

3. Joints should be properly aligned

4. No loose floor panels

f. Water-tightness 1. No leakages through floor slabs, water penetration


Verified by : Checked / Approved by :

Contractor COW / R. Engineer

Date : Date :

Ref. No. CKP/QC/ARCH/01/003

Description
Architectural Work Inspection Form
CEILING (BY VISUAL INSPECTION)

Name of Project : Location :

Drawing Ref. :

Date :

Acceptability
ITEMS ITEMS TO BE CHECKED Contractor JKR Remark
Yes No Yes No
3. CEILING 1. Overall surface should be even, gaps between light
(BY VISUAL fittings and ceiling should not be seen
INSPECTION)
2. Formwork joints are grounded smooth
a. Skim coats
3. No spalling, leaks or stains

4. Paint work with good opacity

5. Cracks not wider than 0.3mm and not more than


20mm long

b. False ceiling 1. Alignment of rails should be visually straight

2. No stains

3. Surface should be overall level and even

4. Chipped surfaces or corners should not be seen


Verified by : Checked / Approved by :

Contractor COW / R. Engineer

Date : Date :

Ref. No. CKP/QC/ARCH/01/004

Description
Architectural Work Inspection Form
DOORS AND WINDOWS

Name of Project : Location :

Drawing Ref. :

Date :

Acceptability
ITEMS ITEMS TO BE CHECKED Contractor JKR Remark
Yes No Yes No
4. Doors & Windows 1. Alignment / level with walls

a. Doors 2. No visible gaps between door frame and wall

3. Fire stope provided were necessary

4. Doors must be properly sanded down and good paint


finish including on top and bottom of door leaf

5. Consistent gap between door leaf and frame ant not


more than 5mm

6. No sags, warps on door leaf

7. Ease in opening and closing

8. Locksets with good fit and no stains

9. Metal door frames not dented

10. Glazing clean and evenly sealed with gasket

11. Door and frame corners maintained at right angles

12. No sign of corrosion in ironmongery or metal frame


b. Windows 1. Alignment / level with wall openings

2. No visible gap between window frame and wall

3. No rainwater leakage

4. Consistent gap between window leaf and frame not


more than 5mm

5. Ease of opening and closing

6. No mortar droppings and paint drips on frames and


glazing

7. Louvre windows with glass panels or correct lengths

8. Glazing clean, evenly sealed with putty or gasket for


aluminium windows

Ref. No. CKP/QC/ARCH/01/004

Description
Architectural Work Inspection Form
DOORS AND WINDOWS

Acceptability
ITEMS ITEMS TO BE CHECKED Contractor JKR Remark
Yes No Yes No
9. Door and frame corners maintained at right anglers

10. Neat joint between windows and wall internally and


externally
Verified by : Checked / Approved by :

Contractor COW / R. Engineer

Date : Date :

Ref. No. CKP/QC/ARCH/01/005

Description
Architectural Work Inspection Form
PLUMBING AND SANITARY FITTINGS

Name of Project : Location :

Drawing Ref. :

Date :

Acceptability
ITEMS ITEMS TO BE CHECKED Contractor JKR Remark
Yes No Yes No
5. PLUMBING AND 1. No damage or chokage
SANITARY
FITTINGS 2. Must be securely fixed

a. Gully and Floor 3. Trap's top to be lower than the surrounding floor level
Trap

b. Pipes 1. Visually aligned horizontally, vertically and parallel to


building surface
2. Inclined pipes laid to proper gradients

3. No leakage at joints

4. Plumb < 10mm / storey height

5. Brackets are firmly secured and adequately spaced

6. If painted, no drippings and with good opacity

c. Fittings 1. Firmly secured and joints properly sealed and pointed

2. No leakage at joints

3. Chipping or cracks should not be observed

4. Paint drops or mortar droppings should not be observed

5. Fittings in working conditions

Verified by : Checked / Approved by :

Contractor COW / R. Engineer

Date : Date :

Ref. No. CKP/QC/ARCH/01/006

Description
Architectural Work Inspection Form
ROOF

Name of Project : Location :

Drawing Ref. :

Date :

Acceptability
ITEMS ITEMS TO BE CHECKED Contractor JKR Remark
Yes No Yes No
6. ROOF Flat (Panel)
1. Ponding less than 3mm
a. Construction
2. No cracks or chips

3. Sealant should be straight edge

4. Joints properly filled up


5. Clean and no cement stains

Pitched
1. No sign of damage to roofing materials

2. No leaking

3. No rust or stains

4. Good painting to roof structural members

b. Waterproofing 1. Should be evenly installed, no sharp protrusion


(exposed)
2. Complete adhesion to base

3. Good laps at joints and proper vertical abutment details

4. No leaking and sign of damage to membrane / coating

5. Clean and no mortar stains

c. Gutters 1. No cheking, ponding less than 3mm

2. No cracks and chips

3. RWDP inlet should be lower than the surrounding gutter


invert level

4. Clean and no cement stains

Verified by : Checked / Approved by :

Contractor COW / R. Engineer

Date : Date :

Ref. No. CKP/QC/ARCH/01/007

Description
Architectural Work Inspection Form
COMPONENTS

Name of Project : Location :

Drawing Ref. :

Date :

Acceptability
ITEMS ITEMS TO BE CHECKED Contractor JKR Remark
Yes No Yes No
7. COMPONENTS 1. Mortar dropping should not be observed

a. Railing 2. Welding at joints must be groundedn or flushed


3. Vertically of balusters must not exceed 3mm per meter

b. Other components 1. For permanent fixtures which are not covered in the
standards, the fundamentals such evenness,
straightness vertically and consistency will still be the
basis for assessment

Verified by : Checked / Approved by :

Contractor COW / R. Engineer

Date : Date :

Ref. No. MHSB/QC/ARCH/01/008

Description
Architectural Work Inspection Form
EXTERNAL

Name : Location :

Drawing Ref. :

Date :
Acceptability
ITEMS ITEMS TO BE CHECKED Contractor JKR Remark
Yes No Yes No
EXTERNAL 1. Corners of wall maintained at right angels
Alignment

Plaster finish 1. No visible cracks across panels

2. Surfaces should be visually even; no patches due to


patching work

3. Straightness of corners

Tiled finish 1. Tile joints aligned and between 2-4mm wide unless
specified

2. Plumb tolerance and evenness of surface (3mm/1.2mm)

3. No chips, cracks and mortar stains

4. No mortar dropping or paint drip on tiles

Claddings/Curtain 1. Gaps araound openings to be properly sealed


walls
2. Joints or regular widths as specified

3. Plumb tolerance as specified

4. Evenness of surface, no dents or scratches

5. Sealant material compatible with cladding

Facing Brickwork 1. 10mm joint with pointing

2. Weepholes are provided as specified

3. No mortar droppings and other stains

4. No efflorescene

Acceptability
ITEMS ITEMS TO BE CHECKED Contractor JKR Remark
Yes No Yes No
Architectural Coating 1. Substrate - see plaster finish

2. Finished texture and colour to be uniform

3. No paint drips and other stains


Painting 1. Substrate - see plaster finish

2. Surfaces are evenly painted: no patchness due to


touch up work

3. Good opacity, no discolouring and free from peeling

Verified by : Checked / Approved by :

Contractor COW / R. Engineer

Date : Date :