RATE ANALYSIS FOR CONCRETE CLASS 'A-3'(1:1½:3)

Unit: Cubic Meter

Rate Amount
Breakdown of Item Unit No. Quantity
(Rs) (Rs)

A) MATERIAL

Cement bags 1 8.50 378.00 3,213.00


Sand Cft 1 16.00 41.00 656.00
Crush Aggregate Cft 1 33.00 39.00 1,287.00
Admixture Ltr 1 3.50 46.00 161.00
Water Ltr 1 175 2.00 350.00
Ice No 1 2 260.00 520.00

B) EQUIPMENT

Batching Plant (30 CM) Hr. 1 0.50 5,000.00 2,500.00


Forms / Shuttering Sft.week 2 43.00 -
Vibrator (Poker 1.5 ") Hr. 1 0.50 90.00 45.00
Transit Mixer (6 CM) Hr. 1 0.50 710.00 355.00
Loader (2.5 CM) Hr. 1 0.50 625.00 312.50
Generator (350 KVA) Hr. 1 0.50 -

C) MAN POWER

Foreman Hr. 1 1.00 62.50 62.50


Skilled Labour Hr. 2 1.00 75.00 150.00
Helper Hr. 6 1.00 37.50 225.00

D) DIESEL

Vibrator (Poker 1.5 ") Hr. 0.50 8.00 78.00 312.00


Transit Mixer (6 CM) Hr. 0.50 20.00 92.10 921.00
Loader (2.5 CM) Hr. 0.50 15.00 92.10 690.75
Generator (150 KVA) Hr. 0.50 35.00 92.10 1,611.75

SUB TOTAL: 13,372.50

Add Contractor's overheads & Profit & Income Tax @31% (15+10+6) 4,145.00

UNIT RATE PER CUBIC METER 17,517.50

SAY: 17,520.00