STUDI PERBANDINGAN SLIP FORM DENGAN JUMP FORM

PADA PEKERJAAN DINDING CLINKER SILO


DITINJAU DARI SEGI BIAYA DAN WAKTU

Aris Anshoril Mahfudz1,Suselo Utoyo2, Adi Muljo3

1
Mahasiswa Program Studi Manajemen Rekayasa Konstruksi,Jurusan Teknik Sipil, Politeknik Negeri Malang
2,3
Dosen Jurusan Teknik Sipil, Politeknik Negeri Malang
1
Ariis092@gmail.com, 2sslutoyo@gmail.com, 3adi.mulio@polinema.ac.id

Abstract

Clinker silo wall concrete work can be done through slip form and jump form. Each method has its
own advantages and disadvantages,especially in terms of cost and time. Consequently, a study is made to
determine the most effective method. Shopdrawing and bill of quantity (BOQ) were used as data. PDM and
Microsoft Project program were used for calculation of duration, whereas calculation of cost was analyzed
using SNI and HSP of Banyuwangi 2013.
The slip form method can be done only in 1 zone, but jump form can be done be made per-zone, in
this study was analyzed using 1, 4, 8, 12 zones. The calculation result in slip form unit price of IDR 261,124
on 56 days, jump form unit price of 278,855 on 130 days for 1 zone, IDR 142,982 on 127 days for 4 zones,
IDR 160,272 on 151 days for 8 zones, IDR 119,874 on 151 days for 12 zones.
CPI (comparative performance index) was used for selecting the most effective formwork method.
The results are the followings.
- The most effective method of slip form with 56% more efficient workdays from the average, on condition
that the time is priority over the cost and both time and cost are priorities.
- The most effective method of jump form 12 zone with 38% more efficient cost from the average, on
condition that the cost is priority over the time.

Key words: formwork, slip form, jump form, cost, time

PENDAHULUAN perencanaan yang se-optimal mungkin yang


memperhitungkan segala faktor yang menjadi
Bekisting merupakan salah satu aspek penting pendukung atau malah menjadi kendala selama
dalam keberhasilan sebuah proyek pelaksanaan nanti (F.Wigbout 1997 : hal 3 ).
konstruksi.Mengingat pada pekerjaan beton Menurut Dr. Edward G Nawy, P. E, C. Eng.,
bekisting merupakan penentu bentuk konstruksi dalam Concrete Construction Engineering
sebelum beton selesai masa setting- time nya. Handbook, ada tiga tujuan penting yang harus
Ketepatan dan akurasi sistem bekisting secara dipertimbangkan dalam membangun dan merancang
langsung akan berdampak pada produk konstruksi. bekisting, yaitu:
Oleh karena itu manajemen pekerjaan bekisting dan - Kualitas: Bekisting harus didesain dan dibuat
metode atau jenis bekisting menjadi hal yang tidak dengan kekakuan (stiffness) dan keakurasian
bisa disepelekan. Namun di sisi lain, penyedia jasa sehingga bentuk, ukuran, posisi dan penyelesaian
konstruksi tetap harus mempertimbangkan sisi dari pengecoran dapat dilaksanakan sesuai dengan
ekonomis dari pekerjaan ini, mengingat dalam hal toleransi yang diinginkan.
penggunaan biaya, bekisting tergolong besar, - Keselamatan: Bekisting harus didirikan dengan
bahkan sampai menghabiskan 10% dari biaya total kekuatan yang cukup dan faktor keamanan yang
proyek konstruksi gedung (Sumber : Concrete memadai sehingga sanggup menahan/menyangga
Formwork System,Award S,Hanna). seluruh beban hidup dan mati tanpa mengalami
Perencanaan metode kerja sekaligus keruntuhan atau berbahaya bagi pekerja dan
penyediaan material bekisting merupakan kewajiban konstruksi beton.
sekaligus hak dari pihak pemborong, sehingga sudah - Ekonomis: Bekisting harus dibuat secara efisien,
pasti faktor kemudahan maupun resiko serta efiensi meminimalisasi waktu dan biaya dalam proses
adalah hal yang ditimbang secara matang oleh pelaksanaan dan schedule demi keuntungan
kontraktor. Tentunya hal ini dapat dilakukan dengan kontraktor dan owner (pemilik).

1
Bekisting slip form didatangkan dengan
Pekerjaan beton dinding clinker silo proyek carasistem sewa yang besaranya adalah per-satuan
banyuwangi cement grinding plant dapat luasdan waktu. Tergantung dengan kebutuhan
dilaksanakan menggunakan dua metode bekisting, Platform untuk konstruksi yang akan di kerjakan.
yaitu slip form dan jump form. Pada pekerjaan Bentuk potongan penampang platformslip form
serupa untuk bangunan cement silo, kontraktor seperti pada Gambar 2.
memilih metode slip form, dan evaluasi yang besi jackrod Ø32

didapat adalah biaya pelaksanaan yang mahal dan


waktu pelaksanaan yang tidak sesuai jadwal. Oleh
karena itu, pada pekerjaan dinding clinker silo ini, selubung hidrolik(jackscrew 3 ton)
HEAD PLATE
plat tebal 5 mm 0.12/1.2

penulis tertarik untuk menganalisa perbandingan Baut Ø19/18

YOKELEG

0.15
biaya dan juga waktu masing-masing metode
hollow 150.10.5 jarak @ 2,00 m.

upper platorm
0.6
bekisting serta menentukan metode mana yang HEAD PLATE
besi tulangan diameter 18

0,15
plat tebal 5 mm 0.15/1.2

paling efektif, dengan bekisting jump form sebagai playwood 1,8 cm

0,50
aternatif. kayu kaso 5 x 7

1,2
hollow 50.50.2

platform,baja 1,2 mm,frame


hollow Ø50.50.2

PEMBAHASAN

lower platorm
SUB PLATFORM

2,80
hollow 50.50.2

Obyek Penelitian besi tulangan diameter 18

1,2
Obyek penelitian adalah pekerjaan beton hollow 50.50.2

dinding bangunan silo clinker semen proyek roller

Banyuwangi Cement Grinding Plant. Sedangkan DINDING CLINCER SILO

obyek bangunan yang di analisis yaitu bangunan


clinker yang merupakan bangunan untuk 0,7

penyimpanan bahan mentah semen. Dimensi Gambar 2. Potongan Penampang Slip form
diameter dinding dalam 60 m, ketinggian bagian
dinding 19 m dengan rincian tinggi dinding 17,804 Analisa Kebutuhan Bahan dan material
m dan selebihnya merupakan ring balok. Ketebalan Penghitungan kebutuhan material slip form
dinding yaitu 0,7 m. Secara detail dapat dilihat pada mengikuti dimensi kebutuhan platform untuk
Gambar 1. dinding clinker silo. Secara lengkap seperti pada
Tabel 1.

Tabel 1. Kebutuhan Bahan Material Slip form


No Uraian volume Sat
1 Plat baja t 1,2 mm 2357,2 Kg
2 Plat baja t 5 mm 655 Kg
3 Profil siku 50.50.2 2334,1 Kg
4 Hollow 50.50.2 13.878,1 Kg
5 Hollow 150.100.5 45 Kg
Gambar 1.Denah dan Potongan Bangunan Clinker 6 WFS 100.100.6.8.10 8744,56 Kg
7 Multipleks 1,8 mm 13.140,8 m2
Silo 8 Besi ulir Ø 19 853 Kg
Volume dan Harga Dasar Pekerjaan 9 Baut Ø 25 pj.18 cm 2275,76 Kg
Penghitungan volume pekerjaan beksiting adalah 10 Baut Ø 19 pj.10 cm 662,380 Kg
luas permukaan dinding dalam dan luar. Hasil 11 Paku 25 Kg
penghitungan sebagai berikut: 12 Kayu kelas III 3/5 19,714 m3
- Luas permukaan dinding luar 13 Jackscrews kap.2 ton 190 bh
= 3.434,28 m2 14 Mesin hidrolik 80 ton 4 bh
- Luas permukaan dinding dalam 15 Besi jack rods Ø32 23.997 Kg
= 3.355,97 m2
- Luas total Selain material diatas, juga dibutuhkan alat
= 6790,25 m2 berat yang didatangkan secara sewa guna
mendukung metode tersebut, alat tersebut antara lain
Harga satuan upah pekerja dan bahan konstruksi 2 buah mobile crane dan generator set.
mengikuti ketetapan di daerah Banyuwangi tahun
2013. Analisa Durasi Pekerjaan Dinding dengan
Slip form
Analisa Slip form

2
Durasi pekerjaan meliputi perakitan, = jumlah tiap titik x kebutuhan pada luasan
pengecoran hingga pembongkaran bekisting. dinding x panjang besi x berat satuan per meter
Berikut hasil analisanya. x harga satuan
- Perkitan Bekisting = 2 x 95 x 19 x 6,62 x 32.700
Hasil analisa durasi efektif perakitan bekisting = Rp.781.147.140
yaitu 18 hari. Namun durasi tersebut belum
termasuk waktu untuk instalasi mesin hidolik yaitu Total biaya penggunaan slip form adalah seperti
4 hari, sehingga durasi perakitan platform slip Tabel 2.
form adalah 22 hari kalender. Tabel 2. Biaya Penggunaan Slip form
Pekerjaan Vol Sat Harga jumlah
- Pengecoran Dinding satuan
Durasi pengecoran mengikuti kecepatan Mob.demo 1 Unit 83.000.00 83.000.000
bekisting bergerak naik (kecepatan kenaikan b alat 0
Sewa 8 Peka 5.144.396 411.571.163
bekisting mengambil data pada pelaksanaan
bekisting n
pek.dinding silo cement), berikut analisanya: PPn 10% 8 pekan514.439,6 4.115.7116
a. setting time awal beton 8 jam Jack rods Ls 781.147.140
b. kecepatan naik slip form 5 cm/jam Operasioal 33 jam 158.518 138.768.000
c. tinggi dinding 17,804 m 6
d. tinggi bekisting kontak 1,2 m Total biaya (Rp) 1.455.643.41
9
durasi pengecoran Dibulatkan (Rp) 1.456.000.00
= setting time awal + ( (ketinggian dinding- 0
tinggi bekisting kontak) / kecepatan naik slip
form) - Analisa Biaya Alat Berat
= 8 Jam + (17,804 m -1,2 m) Biaya penggunaan alat berat mobile crane
0.05 m untuk pembongkaran slip form adalah seperti pada
= 8 + 322 Jam Tabel 3.
= 340 Jam atau ±14 Hari kalender.
Tabel 3.Biaya Mobile Crane
- Pembongkaran Bekisting Pekerjaan Vol Sat Harga jumlah
Dengan menggunakan 27 tukang dan seorang satuan
(Rp)
mandor, durasi pembongkaran adalah 17 hari dan
Mob.demob 2 Unit 35.000.000 70.000.000
durasi menunggu untuk bekisting siap dibongkar alat
yaitu 3 hari kalender. Sewa mobile 13 Jam 638.000 86.768.000
crane 6
Jadi total durasi pekerjaan dinding menggunakan PPn 10% 13 Jam 63.800 8.676.800
slip form adalah 56 hari kalender. 6
Operator 13 Jam 22.311 3.034.296
Analisa Biaya Slip form 6
Analisa biaya slip form meliputi analisa harga sewa Operasioal 13 Jam 525.017 71.042.293
6
bekisting, jack rods dan harga pemakaian alat berat
Total biaya 239.881.390
serta upah pekerja. Berikut analisanya. Dibulatkan 240.000.000

- Analisa Harga Penggunaan Bekisting - Analisa upah pekerja


Harga sewa beksiting Biaya upah pekerja meliputi pekerjaan perkitan
= Nilai Sewa per- m2 x Volume Kebutuhan dan pembongkaran bekisting seperti pada Tabel 4.
= Rp. 112.402 x 457.68 m2
= Rp. 51.446.395,4 Tabel 4.Biaya Upah Pekerja
Sa Harga Vol
Biaya operasional bekisting Uraian Jumlah
t satuan (m2)
Biaya operasional meliputi biaya pemakaian Perakitan
generator set sebagai penyuplai tenaga penggerak m2 87.991,1 40.270.913,2
bekisting
457,7
mesin hidrolik. Dimana kebutuhan biayanya adalah: Bongkar
m2 80.462,5 36.825.276
Bahan bakar 132.833 / jam bekisting
Pelumas 25.685,4 / jam+ Jumlah biaya upah pekerja 77.096.189,2
Total 158.518 / jam
Jadi total biaya pelaksanaan bekisting slip form
Biaya pengadaan jack rods adalah Rp.1.818.596.189,-
= Volume Besi x Harga satuan
Analisa Jump form

3
Berbeda dengan slip form, jump form dapat Analisa durasi pekerjaan dimulaisejak
dilaksanakan menggunakan beberapa alternatif zona perakitan bekisting sampai selesainya pengecoran di
kerja, tujuannya adalah menghemat pengadaan elevasi tertinggi dinding.
material dan bahan dalam satu waktu. Sebagai - Durasi Perakitan Bekisting
usulan dalam penelitian ini akan dibahas metode Hasil analisa durasi perakitan bekisting yaitu 14
zona yaitu 1, 4, 8, dan 12 zona.Gambar 3 adalah hari kalender .
potongan penampang jump form. - Durasi Pembesian
Hasil analisa durasi pembesian bekisting yaitu 20
hari kalender .

1500
1200

- Durasi Pengecoran
Durasi penegcoran dapat dihitung dengan
menganalisa produktifitas concrete pump:
3000

Kap.alat(v) 8 m3
Faktor efisiensi (fa) 0,83
1200

Waktu siklus (ts) 40 menit


Q = V x Fa x 60
1600

Ts
70 1700 = (8 x 0,83 x 60) / 40
Gambar 3. Potongan Melintang Jump Form = 9,96 m3 / jam
Dengan volume beton 397,4 m3, dengan
Kebutuhan Bahan Material Jump form menggunakan 4 alat concrete pump, maka durasi
kebutuhan material sesuai dengan volume luas penegcoran yaitu 10 jam (1 hari)
permukaan dinding per-tinggi 3 meter yaitu - Durasi Pergeseran Bekisting
1.144,17 m2. Kebutuhan material jump form ukuran Perhitungan waktu mobilisasi dengan satu mobile
3 x 3 meter adalahseperti pada Tabel 5. crane panel bekisting yaitu 0,061 menit.
Sedangkan waktu untuk bongkar muat panel
Tabel 5 Kebutuhan Bahan Material Jump form sebagai berikut
No Uraian Volume Sat Pelepasan angkur 8 menit
1 Plat baja t 2 mm 51 Kg Pemasangan angkur 16 menit
2 Profil siku 50.50.4 40,59 Kg Waktu tunggu 2 menit +
3 Pelat strip 40.4 40,59 Kg Total 26 menit
4 Walling vertikal 360 Kg Jumlah panel adalah 130 buah dengan alokasi
5 Walling horizontal 432 Kg waktu total pergeseran tiap panel 26,061 menit,
6 Konsol width 1,72 m 291 Kg dan pergeseran menggunakan 4 buah mobile crane
7 Konsol width 1,2 m 121,7 Kg maka durasi total adalah 14 jam ( 2 hari )
8 Pipe support 3 m 3 bh
9 Pipe support 1,78 m 3 bh Jadi durasi total pengerjaan dinding dengan jump
10 Rel steger 0,75 m 72,9 Kg form 1 zona untuk satu siklus adalah 37 hari
11 Base coupling 6,9 Kg sedangkan secara total adalah 130 hari kalender.
12 Wall connector 33,6 m3
13 Angkur 7,38 bh Analisa Biaya Jump form 1 Zona
14 Wing nut 64 bh biaya pelaksanaan jump form 1 zona sebagai
15 Baut 32 bh berikut:
16 Papan kayu 20 mm 0,18 m3 - Biaya Alat
17 Pipa galv ¾ “ 6 m Biaya penggunaan alat berat mobile crane untuk
pergeseran jump form adalah seperti pada Tabel 6.
Selain material diatas, juga dibutuhkan alat berat
yang didatangkan secara sewa guna mendukung Tabel 6. Biaya Mobile Crane
metode tersebut, alat tersebut antara lain mobile Pekerjaan Vol Sat Harga jumlah
crane. satuan
(Rp)
Mob.demob 4 Unit 35.000.000 140.000.000
Jump form 1 Zona (tanpa zona) alat
Metode ini mengharuskan penyediaan material Sewa mobile 84 Jam 1.277.600 107.318.400
beksiting sepanjang keliling dinding dengan crane
ketinggian 3 m. Yang nantinya pergerakan PPn 10% 84 Jam 127.760 10.731.840
pengerjaan vertikal keatas secara bersama-sama. Operator 84 Jam 44.622 3.748.248
Operasioal 84 Jam 1.102.645,7 92.622.239
Analisa Durasi Pekerjaan Dinding Total biaya 354.420.727
Dibulatkan 355.000.000

4
- Biaya Material Bekisting Dari asumsi dengan metode jump form dengan 4
Kebutuhan sewa bekisting adalah sebagai berikut: zona didapat;
= Nilai Sewa per- m2 x Volume Kebutuhan - Volume Bekisting persegmen = 286,04 m2
= Rp. 60.590 x 1.144,17m2 - Volume pengecoran Beton = 99,36m3
= Rp. 69.313.819 - Volume pembesian persegmen = 19.706,7 Kg
- Jumlah segmen =2
Rekapitulasi biaya total material bekisting adalah - Jumlah pergeseran bekisting = 24 Kali
pada Tabel 7.
Analisa Durasi Pekerjaan Dinding
Tabel 7. Biaya Pengadaan Material Jump form Analisa durasi pekerjaan dimulaisejak perakitan
Pekerjaan Vo Sat Harga Jumlah bekisting sampai selesainya pengecoran di elevasi
l satuan tertinggi dinding.
Mob.demob 1 Uni 30.000.000 83.000.000 - Durasi Perakitan Bekisting
alat t Hasil analisa durasi perakitan bekisting yaitu 3
Sewa 19 Pek 69.313.819 1.316.962.553
hari kalender .
bekisting an
PPn 10% 19 Pek 693.138 131.696.255 - Durasi Pembesian
an Hasil analisa durasi pembesian bekisting yaitu 5
Total biaya (Rp) 1.478.658.808 hari kalender .
Dibulatkan (Rp) 1.479.000.000 - Durasi Pengecoran
Durasi penegcoran dapat dihitung dengan
- Biaya Upah Pekerja menganalisa produktifitas concrete pump:
Biaya upah pekerja meliputi pekerjaan perkitan, = 9,96 m3 / jam
pergeseran dan pembongkaran bekisting seperti Dengan volume beton 99,36 m3, maka durasi
pada Tabel 8. penegcoran yaitu 10 jam (1 hari). Untuk curing
dilakukan selama 6 hari.
Tabel 8. Biaya Upah Pekerja - Durasi Pergeseran Bekisting
Sa Harga Volume Jumlah panel adalah 32 buah dengan alokasi
Uraian Jumlah
t satuan waktu total pergeseran tiap panel 26,061 menit
Perakitan
m2 87.991,1
1.144,17
16.346.379
(dari analisa sebelumnya), dan pergeseran
bekisting menggunakan 1 buah mobile crane maka durasi
Pergeseran 6790,25 total adalah 14 jam ( 2 hari )
m2 1.763,6 12.106.997
bekisting
Bongkar 1.144,17
m2 80.462,5 31.042.430 - Alur Pekerjaan Dinding
bekisting
Jumlah biaya upah pekerja 59.495.806
Alur pengerjaan tiap zona adalah dengan
membagi wilayah keliling dinding menjadi dua
Jadi total biaya pelaksanaan bekisting jump form 1 bagian atau setengah lingkaran. Pada wilayah
zona adalah Rp.1.895.595.806,- setengah keliling lingkaran tersebut pengerjaan di
bagi dalam dua zona (zona 1 dan zona 2) dan
Jump form 4 Zona secara bergantian pekerjaan dikerjakan naik
Alternatif lain penggunaan bekisting jump form sampai ketinggian maksimal. Baru setelah selesai
adalah dengan menerapkan sistem zoning. Asumsi panel bekisting akan dipindah di bagian setengah
yang penulis tawarkan adalah dengan membagi lingkaran selanjutnya (zona 3 dan 4).
menjadi 4 zona kerja, dengan pengadaan panel
adalah 2 zona (setengah luasan keliling dinding). Dengan menggunakan Ms.Project, didapat total
Artinya urutan pengerjaan adalah secara bergantian. durasi pekerjaan dinding yaitu 127 hari kalender.
Gambar 4 adalah pembagian zona dinding clinker
silo. Analisa Biaya Jump form 4 Zona
biaya pelaksanaan jump form 4 zona sebagai
START
berikut:

ZONA ZONA - Biaya Alat


4 1 Biaya penggunaan alat berat mobile crane untuk
DINDING CLINCER pergeseran jump form adalah seeperti pada Tabel 8
SILO CEMENT
ZONA ZONA berikut ini:
3 2
Tabel 8. Biaya Mobile Crane
Pekerjaan Vol Sat Harga Jumlah
satuan
Gambar 4. Denah Pembagian Zona Kerja (Rp)
Mob.demob 1 Unit 35.000.000 35.000.000

5
alat
Sewa mobile 38 Jam 319.400 122.649.600 ZONA ZONA

crane 4
8 1

PPn 10% 38 Jam 31.940 12.264.960 ZONA


7
ZONA
2

4 DINDING CLINCER
ZONA SILO CEMENT
Operator 38 Jam 11.155,5 4.283.712 ZONA
6
3

4 ZONA
5
ZONA
4

Operasioal 38 Jam 262.161,4 100.669.978


4
Total biaya 271068.250 Gambar 5. Pembagian Zona Kerja
Dibulatkan 272.000.000
- Biaya Material Bekisting Dari asumsi dengan metode jump form dengan
Kebutuhan sewa bekisting adalah sebagai berikut: 8zona didapat;
= Nilai Sewa per- m2 x Volume Kebutuhan - Volume Bekisting persegmen = 143,02 m2
= Rp. 60.590 x 572m2 - Volume pengecoran Beton = 49,7m3
= Rp. 34.657.480 - Volume pembesian persegmen = 9.853,3 Kg
Rekapitulasi biaya total material bekisting adalah - Jumlah segmen =2
pada Tabel 9. - Jumlah pergeseran bekisting = 48 Kali

Tabel 9.Biaya Pengadaan Material Jump form Analisa Durasi Pekerjaan Dinding
Pekerjaan Vo Sat Harga jumlah Analisa durasi pekerjaan dimulaisejak perakitan
l satuan bekisting sampai selesainya pengecoran di elevasi
Mob.demob 1 Uni 15.000.000 15.000.000
tertinggi dinding.
alat t
Sewa 17 Pek 34.657.480 589.177.160
bekisting an - Durasi Perakitan Bekisting
PPn 10% 17 pek 3.465.748 58.917.716 Hasil analisa durasi perakitan bekisting yaitu 2
an hari kalender .
Total biaya (Rp) 663.094.876 - Durasi Pembesian
Dibulatkan (Rp) Hasil analisa durasi pembesian bekisting yaitu 3
663.100.000 hari kalender .
- Durasi Pengecoran
- Biaya Upah Pekerja Durasi penegcoran dapat dihitung dengan
Biaya upah pekerja meliputi pekerjaan perkitan, menganalisa produktifitas concrete pump:
pergeseran dan pembongkaran bekisting seperti = 9,96 m3 / jam
pada Tabel 10. Dengan volume beton 49,68 m3, maka durasi
penegcoran yaitu 5 jam (1 hari). Untuk curing
Tabel 10. Biaya Upah Pekerja dilakukan selama 6 hari.
Sa Harga Volume
Uraian Jumlah
t satuan - Durasi Pergeseran Bekisting
Perakitan 572 Jumlah panel adalah 16 buah dengan alokasi
m2 14.286,7 8.171.993
bekisting waktu total pergeseran tiap panel 26,061 menit
Pergeseran 6790,25 12.095.04 (dari analisa sebelumnya), dan pergeseran
m2 1.762
bekisting 0 menggunakan 1 buah mobile crane maka durasi
Bongkar 572 15.518.93
bekisting
m2 27.131
2
total adalah 7 jam ( 1 hari )
Jumlah biaya upah pekerja 25.785.96
5 - Alur Pekerjaan Dinding
Alur pengerjaan tiap zona adalah dengan
Jadi total biaya pelaksanaan bekisting jump form 4 membagi wilayah keliling dinding menjadi dua
zona adalah Rp.983.885.965,- bagian atau setengah lingkaran. Pada wilayah
setengah keliling lingkaran tersebut pengerjaan
Jump form 8 Zona dilakukan secara berurutan mulai dari zona 1
Alternatif lain penggunaan bekisting jump form sampai 4. Kemudian setelah zona 4 selesai maka
adalah dengan menerapkan sistem zoning. Asumsi zona 1 akan bergerak naik satu segmen (3 meter)
yang penulis tawarkan adalah dengan membagi dan diikuti kembali oleh zona berikutnya. Hingga
menjadi 8 zona kerja, dengan pengadaan panel sampai pengerjaan dinding di setengah lingkaran
adalah 4 zona (setengah luasan keliling dinding). selesai baru panel pada zona 1 akan di turunkan
Artinya urutan pengerjaan adalah secara bergantian. dan di gunakan pada zona 5, untuk selanjutnya
Gambar 5adalah pembagian zona dinding clinker langkah pengerjaan sama dengan alur di setengah
silo. lingkaran sebelumnya. Lebih jelas Gambar 6
sebagai ilustrasi pembagian zona.

6
777.500.000
START' START

ZONA
8
ZONA
1
- Biaya Upah Pekerja
ZONA
ZONA
2
Biaya upah pekerja meliputi pekerjaan perkitan,
pergeseran dan pembongkaran bekisting seperti
7

DINDING CLINCER
ZONA
6
ZONA
3
SILO CEMENT
pada Tabel 13.
ZONA ZONA
5 4

Tabel 13. Biaya Upah Pekerja


Sa Harga Volume
SETENGAH LINGKARAN PERTAMA Uraian Jumlah
t satuan
Gambar 6. Alur Kerja Menggunakan 8 Zona Perakitan 572
m2 14.286,7 8.171.993
bekisting
Dengan menggunakan Ms.Project, didapat total Pergeseran 6790,25 12.095.04
m2 1.762
durasi pekerjaan dinding yaitu 151 hari kalender. bekisting 0
572
Bongkar
Analisa Biaya Jump form 8 Zona m2 27.131 15.518.93
bekisting
biaya pelaksanaan jump form 8 zona sebagai 2
berikut: Jumlah biaya upah pekerja 25.785.96
5
- Biaya Alat
Biaya penggunaan alat berat mobile crane untuk Jadi biaya pelaksanaan bekisting jump form 8 zona
pekerjaan pergeseran jump form adalah seperti adalah Rp.1.088.285.965,-
pada Tabel 11.

Tabel 11. Biaya Mobile Crane


Pekerjaan Vol Sat Harga jumlah Jump form 12 zona
satuan Alternatif lain penggunaan bekisting jump form
(Rp) adalah dengan menerapkan sistem zoning. Asumsi
Mob.demob 1 Unit 35.000.000 35.000.000 yang penulis tawarkan adalah dengan membagi
alat menjadi 12 zona kerja, dengan pengadaan panel
Sewa mobile 38 Jam 319.400 122.649.600 adalah 4 zona (sepertigakeliling dinding). Gambar
crane 4 7 adalah pembagian zona dinding clinker silo.
PPn 10% 38 Jam 31.940 12.264.960
4
START
Operator 38 Jam 11.155,5 4.283.712
4 ZONA
ZONA
12
ZONA
1

Operasioal 38 jam 262.161,4 100.669.978 11 ZONA


2

4
ZONA
ZONA 3
10

Total biaya 271.068.250 ZONA ZONA DINDING CLINCER


dibulatkan 272.000.000
9 4 SILO CEMENT

ZONA ZONA
8 5
ZONA
7 ZONA

- Biaya Material Bekisting


6

Kebutuhan sewa bekisting adalah sebagai berikut:


= Nilai Sewa per- m2 x Volume Kebutuhan
= Rp. 60.590 x 572m2 Gambar 7. Pembagian Zona Kerja
= Rp. 34.657.480
Dari asumsi dengan metode jump form dengan
Rekapitulasi biaya total material bekisting adalah 12zona didapat;
pada Tabel 12. - Volume Bekisting persegmen = 95,3 m2
- Volume pengecoran Beton = 33,1m3
Tabel 12.Biaya Pengadaan Material Jump Form - Volume pembesian persegmen =6.623,75 Kg
Pekerjaan Vo Sat Harga jumlah - Jumlah segmen = 12
l satuan - Jumlah pergeseran bekisting = 72 Kali
Mob.demob 1 Uni 15.000.000 15.000.000
alat t Analisa Durasi Pekerjaan Dinding
Sewa 20 Pek 34.657.480 Analisa durasi pekerjaan dimulaisejak perakitan
bekisting an 693.149.600 bekisting sampai selesainya pengecoran di elevasi
PPn 10% 20 pek 3.465.748 69.314.960 tertinggi dinding.
an
Total biaya (Rp)
- Durasi Perakitan Bekisting
777.464.560 Hasil analisa durasi perakitan bekisting yaitu 1
Dibulatkan (Rp) hari kalender .
7
- Durasi Pembesian Mob.demob 1 Unit 35.000.000 35.000.000
Hasil analisa durasi pembesian bekisting yaitu 2 alat
hari kalender . Sewa mobile 36 Jam 319.400 114.984.000
- Durasi Pengecoran crane 0
PPn 10% 36 Jam 31.940 11.498.400
Durasi penegcoran dapat dihitung dengan
0
menganalisa produktifitas concrete pump: Operator 36 Jam 11.155,5 4.015.980
= 9,96 m3 / jam 0
Dengan volume beton 33,1 m3, maka durasi Operasioal 36 Jam 262.161,4 94.378.176
penegcoran yaitu 3,3 jam (1 hari). Untuk curing 0
dilakukan selama 6 hari. Total biaya 259.876.556
- Durasi Pergeseran Bekisting Dibulatkan 260.000.000
Jumlah panel adalah 10 buah dengan alokasi
waktu total pergeseran tiap panel 26,061 menit - Biaya Material Bekisting
(dari analisa sebelumnya), dan pergeseran Kebutuhan sewa benkisting adalah sebagai
menggunakan 1 buah mobile crane maka durasi berikut:
total pergeseran tiap zona adalah 4,5 jam (1 hari) = Nilai Sewa per- m2 x Volume Kebutuhan
= Rp. 60.590 x 381,4m2
- Alur Pekerjaan Dinding = Rp. 23.109.026
Alur pengerjaan tiap zona adalah dengan
membagi wilayah keliling dinding menjadi tiga Rekapitulasi biaya total material bekisting adalah
bagian. Pada wilayah masing-masing sepertiga pada Tabel 15.
keliling lingkaran tersebut pengerjaan dilakukan
secara berurutan mulai dari zona 1 sampai 4.
Kemudian setelah zona 4 selesai maka zona 1 akan
bergerak naik satu segmen (3 Meter) dan di ikuti
kembali oleh zona berikutnya. Hingga sampai
pengerjaan dinding di sepertiga lingkaran pertama Tabel 15. biaya pengadaan material jump form
selesai, baru panel pada zona 1 akan di turunkan Pekerjaan Vo Sat Harga jumlah
dan digunakan pada zona 5 (sepertiga lingkaran l satuan
selanjutnya), untuk selanjutnya langkah Mob.demob 1 Uni 15.000.000 15.000.000
pengerjaan sama dengan alur di sepertiga alat t
Sewa 20 Pek 23.109.026 462.180.520
lingkaran sebelumnya. Secara lebih lengkap dapat bekisting an
dilihat pada Gambar 8. PPn 10% 20 pek 1.304.884 46.218.052
an
START
Total biaya (Rp) 518.398.572
ZONA
12
ZONA
1
SEPERTIGA
LINGKARAN
1
Dibulatkan (Rp) 520.000.000
ZONA
11 ZONA
2

ZONA

- Biaya Upah Pekerja


ZONA 3
10
SEPERTIGA
LINGKARAN
3
ZONA
9
ZONA
4
Biaya upah pekerja meliputi pekerjaan perkitan,
ZONA
8
ZONA
5 pergeseran dan pembongkaran bekisting seperti
pada Tabel 16.
ZONA
7 ZONA
6

SEPERTIGA
LINGKARAN
Tabel 16. Biaya Upah Pekerja
Sa Harga Volume
2

Gambar 8. Alur Kerja Menggunakan 12 Zona Uraian


t satuan
Jumlah
Perakitan 381,4 5.448.947,
Dengan menggunakan Ms.Project, didapat total m2 14.286,7
bekisting 3
durasi pekerjaan dinding yaitu 151 hari kalender. Pergeseran 6790,25 18.180.67
m2 2.647
bekisting 5
Analisa Biaya Jump form 12 zona 381,4
Bongkar
biaya pelaksanaan jump form 12 zona sebagai bekisting
m2 27.131 10.347.76
berikut: 3
- Biaya Alat Jumlah biaya upah pekerja 33.977.38
Biaya penggunaan alat berat mobile crane untuk 5
pekerjaan pergeseran jump form adalah seperti
pada Tabel 14. Jadi total biaya pelaksanaan bekisting jump form 12
zona adalah Rp.823.177.385,-
Tabel 14. Biaya Mobile Crane
Pekerjaan Vol Sat Harga jumlah Analisa Perbandingan Metode Bekisting
satuan
(Rp)
8
Metode CPI (comparative performance index) masing-masing alternatif zonabekisting secara
digunakan untuk membandingan dan mengambil berurutan adalah
keputusan metode bekisting paling efektif. Langkah Rp.1.893.495.806,Rp.970.885.965,
pertama yaitu membuat skenario bobot alternatif Rp.1.088.285.965 dan Rp.813.977.385.
seperti pada Tabel 17. Sedangkan durasi pekerjaan dinding clinker
silo secara berurutan yaitu 130, 127, 151 dan
Tabel 17.Skenario Bobot Alternatif 151 hari kalender.
skenario Bobot Jumlah
waktu Biaya 3. Pengambilan keputusan bekisting yang paling
1 0,7 0,2 1 efektif dilakukan dengan membuat beberapa
2 0,6 0,4 1 kondisi antara lain sebagai berikut:
3 0,5 0,5 1 a. Asumsi waktu lebih penting dari pada biaya
4 0,4 0,6 1 Slip form paling efektif,efisiensi durasi sampai
5 0,3 0,7 1 56% (69 hari) dari durasi rata-rata alternatif
. bekisting yaitu sebesar 123 hari,dengan harga
Selanjutnya mentransformasikan harga satuan satuan Rp.261.124 / m2 atau lebih mahal 36%
dan durasi masing masing alternatif bekisting dari biaya rata-rata alternatif bekisting yang
menjadi satuan nilai seragam dan menjumlahkan besarnya Rp.192.621 / m2.
hasil nilai masing-masing nilai untuk mengetahui b.Asumsi waktu dan biaya sama-sama
rangking alternatif di tiap skenario yang dibuat.Dari pentingnya
hasil analisis diketahui metode jump form 12 zona Bekisting slip form paling efisien untuk
paling efektif untuk kondisi biaya lebih kondisi ini.
diperioritaskan dari pada waktu dan slip form paling c. Asumsi biaya lebih penting dari pada waktu
efektif jika kondisi waktu lebih diperioritaskan atau Jump form 12 zona paling efektif,efisiensi
waktu dan biaya sama-sama penting. biaya sampai 38% (Rp.72.747 / m2 ) dari harga
satuan rata-rata alternatif bekisting yaitu
sebesar Rp.192.621/m2. Durasi 151 hari atau
lebih lama 28 hari dari durasi rata-rata
alternatif bekisting yang besarnya yaitu 123
SIMPULAN hari kalender.

Dari analisis diatas dapat diambil kesimpulan DAFTAR RUJUKAN


sebagai berikut:
1. Pelaksanaan bekisting slip form membutuhkan F. Wigbout, Ing. 1997. Bekisting (Kotak Cetak).
biaya sebesar Rp.1.773.096.189 dengan durasi Jakarta : Erlangga.
pekerjaan dinding yaitu 56 hari kalender. G Nawy, Edward, P. E, C. Eng., Dr.,1997. Concrete
Construction Engineering Handbook.
2.Pelaksanaan bekisting jump form di lakukan New York : CRC Press Bocaraton.
dengan empat alternatif,yaitu 1, 4, 8 dan 12 S Hanna, Awad. 1998. Concrete Formwork System.
zona. Kebutuhan biaya pelaksanaan dari Madison : University of Wisconsin.