Professional Documents
Culture Documents
K2S-CW230907-BA6008-00005 - A01 - Manual Operated Valve Test Procedure
K2S-CW230907-BA6008-00005 - A01 - Manual Operated Valve Test Procedure
K2S-CW230907-BA6008-00005 - A01 - Manual Operated Valve Test Procedure
Originat
Originator Morpol Engineering Services Limited
DCAF Control ID NA
Month/Year January/2021
Proprietary Information: This document contains proprietary information and may not be partly or wholly
reproduced without prior written permission from Shell Petroleum Development Company.
Company
K2S-CW230907-BA6008-00005
Page 1 of 13
Revision Philosophy
All revisions for review will be issued at R01, with subsequent R02, R03, etc as required.
All revisions approved for issue or design will be issued at A01, with subsequent A02, A03,
etc as required.
Documents approved for Construction will be issued at C01, C02, and C03 respectively.
Documents or drawings revised as “As built” will be issued as Z01, Z02 Z03 etc.
Narrative sections revised from previous approved issues are to be noted in the table
below and/or highlighted in the RH margin (using the appropriate revision status) thus: |
A02
Revision History
K2S-CW230907-BA6008-00005
Page 2 of 13
Purpose .........................................................................................................................5
2. DEFINITIONS / ABBREVIATIONS........................................................................5
Definitions .....................................................................................................................5
Abbreviations ................................................................................................................5
K2S-CW230907-BA6008-00005 Page 3 of 13
Three nos. of 2.027 eMW 11KV 50 Hz gas generators with combined output of 6.081 eMW
will be installed and voltage stepped up to 33KV via a 8.0MVA 11KV/33KV transformer at the
Kolo Creek Oil & NAG Manifold into a 1.2km 33kV underground power cable feeding an
indoor 33kV, Ring Main Unit (RMU) at KCPS. An outgoing feeder from the RMU will supply
into the existing KCPS overhead transmission line. The proposed backup power is sufficient to
meet both the present combined community load of 3.75MVA (as advised by KCPS) and
K2S-CW230907-BA6008-00005
Page 4 of 13
1.2 PURPOSE:
The purpose of this statement is to ensure that all works required to be performed are
carried out following requisite standards, established and approved fundamental
principles in order to ensure high quality job delivery and from the work procedures
contained therein develop a safe method of carrying out the entire work.
2.0 DEFINITIIONS AND ABBREVIATIONS
2.1 DEFINITIONS
COMPANY - Shell Petroleum Development Company
COMPANY Representative - Means any authority or person appointed in writing
by COMPANY to witness the test to be carried out
Page 5 of 13
The scope of commissioning testing will be executed as per the following main
documents:
i. Work Schedule (See the Ms Project and/or Ms Excel)
ii. Job Hazard Analysis
iii. Work permit
iv. Check sheets & manual operation report forms
v. As-built Drawings/Documents P&ID
K2S-CW230907-BA6008-00005
Page 6 of 13
Page 7 of 13
Page 8 of 13
K2S-CW230907-BA6008-00005
Page 9 of 13
Page 10 of 13
Page 11 of 13
K2S-CW230907-BA6008-00005
Page 12 of 13
11.2 RECORDS
K2S-CW230907-BA6008-00005
Page 13 of 13