Professional Documents
Culture Documents
Method Statement - Fabrication and Installation of Prefabricated Coodo 64
Method Statement - Fabrication and Installation of Prefabricated Coodo 64
REVISION CONTROL
DENNIS
KAVYA S KUMAR ENGELBRECHT
00 04.01.2021
QA/QC ENGINEER OPERATIONS
MANAGER
Table of Contents
1 Purpose 4
2 Scope 4
3 References 4
Prefabrication Activities 6
5.3.1 Coil loading on Gantry 6
5.3
5.3.2 Coil feeding in machine 6
5.3.3 Operation 6
Fabrication Activities
7
5.4.1 I-beam Skid Frame Fabrication
7
5.4.2 Skid, Column, and Intermediate Beam Painting
7
5.4.3 Floor Construction with LGS Floor Panel Cassette Type
5.4 7
5.4.4 Floor decking
8
5.4.5 Wall panel frame fabrication
8
5.4.6 Roof Panel Fabrication
9
Erection Activities
5.5.1 Erection of floor frame
10
5.5.2 Erection of wall panel frame
10
5.5.3 Roof Erection
5.5 10
5.5.4 Purlin fixing
11
11
Site Erection
14
5.6.1 Placement
14
5.6 5.6.2 Electrical connection between units
14
5.6.3 Heat pump installation
15
ATTACHMENT
6 15
6.1 Lifting Plan
1. PURPOSE
The purpose of this procedure is to describe & define a method for Fabrication and
Installation of prefabricated Coodo 64 units by Speed House / LTG for VW Germany.
2. SCOPE
This procedure shall be applicable for the fabrication of modular Coodo buildings and
erection of modular Coodo buildings.
3. REFERNCES
4. RESPONSIBILITIES
4.1.1 The responsibility for carrying out this Method Statement shall be that of the
Production Manager / Engineer and Operation Manager / Engineer, unless
otherwise specifically mentioned in this procedure. The Yard in-charge / Site
Engineer shall be responsible for the execution of this Method Statement. The
Quality Engineer / Yard in-charge / Site Engineer shall be responsible for the
inspection & testing.
5. PROCEDURE
5.1 Drawings
5.1.1 Prepare steel frame Layout, Wall panel layout, Wall panel details, Roof layout,
floor layout drawings as per the architectural layout. These shop drawings shall be
submitted to the Client for approval, where required.
5.1.2 Before starting the fabrication and erection work, Operation Manager and Project
Manager shall verify the wall panel and other related dimensions & other
reference points. Any practical difficulty or discrepancies shall be brought to the
notice of the Client & clarification shall be obtained.
5.2.1 Arrange the appropriate tools and instruments for the intended setting out
task according to the accuracy requirements.
5.2.2 Records for inspection, testing and maintenance shall be made available for any
verification
5.2.3 The tools and instruments required for the fabrication and erection work are as
follows:
5.3.1.6 With the box spanner adjust and tighten the three arms, check that the coil
if it is properly fitted in arms, see that the coil touches inside of the flange.
5.3.1.9 Place a safety barricade to avoid access to de- coiler and prevent people
stepping over strip feeding into machine
5.3.2.1 Machine operator will cut the strip tapered on both side
5.3.2.2 Straighten the coil using hammer
5.3.2.3 GI straps shall be properly filed, check there are no burs
5.3.2.4 Feed the coil into the machine till it passes 1st roller
5.3.3 Operation
5.3.3.1 Design department to provide data contained flash drive along with hard copy
5.3.3.2 Start machine pressing auto start and ensue collect tray is clear of from
obstructions
5.3.3.5 Steel sections coming from machine shall be of specified size & length as per
design.
5.4.1.2 Base skid shall be constructed with Mild steel I-beam 180 IPE fixed along the
periphery.
5.4.1.4 Steel sections shall be welded together by 6mm fillet and butt welds (AWS D1.1
/ ASME Sec. IX).
5.4.1.5 Lifting points will be provided at center column points along the perimeter.
And shall be welded with a 6mm fillet weld, inspected visually and recorded.
(Dye pen testing with lift testing)
5.4.1.6 When the steel structure is completed, 10% of all welds to be Dye penetration
tested.
5.4.2.2 Painting shall be done as per the specification – One coat of red oxide /
epoxy primer will be applied immediately after blasting.
5.4.3.2 LGS sections coming from machine shall be of specified size & length as per
design
5.4.3.4 Electronic drawings and data related to floor panel Design will be issued
as per approved specification. A hard copy of drawings will be issued
simultaneously for assembly of floor panels.
5.4.3.5 Electronic data will be fed into the machine by means of USB drive, to
commence the production of LGS section as per the requirement.
5.4.3.6 LGS sections produced from machine will be of specified size & length as per
design
5.4.3.7 Service holes & openings shall be provided along the LGS section as per design
5.4.3.8 All the LGS members produced from the machine will be moved to the
assembly area for further activities.
5.4.3.9 LGS floor panels will be assembled on a table allocated in assembly area. LGS
sections will be assembled, aligned, and fixed to make rigid frame. where
necessary, rubber mallet shall be used to align the sections
5.4.3.10 Cordless impact driver and suitable screws (collated or non- collated) screws
shall be used to assemble the frame
5.4.3.11 LGS floor panel shall be placed onto the I-beam skid frame by means of crane
/ forklift.
5.4.4.2 Cement Fiberboard shall be fixed to steel skid by means of suitable screws
5.4.4.3 Screws shall be provided at 400mm c/c and 15mm from edge of the
Cement Fiber board
5.4.5.3 Electronic drawings and data related to wall panel Design will be issued
as per approved specification. A hard copy of drawings will be issued
simultaneously for assembly of wall panels.
5.4.5.4 Electronic data will be fed into the machine by means of USB drive, to
commence the production of LGS section as per the requirement.
5.4.5.5 LGS sections produced from machine will be of specified size & length as per
design
5.4.5.6 Service holes & openings shall be provided along the LGS section as per
design
5.4.5.7 All the LGS members produced from the machine will be moved to the
assembly area for further activities.
5.4.5.8 LGS wall panels will be assembled on a table allocated in assembly area. LGS
sections will be assembled, aligned, and fixed to make rigid frame. where
necessary, rubber mallet shall be used to align the sections
5.4.5.9 Cordless impact driver and suitable screws (collated or non- collated) screws
shall be used to assemble the frame
5.4.6.6 Steel sections are to be aligned if necessary, a rubber mallet shall be used to
align the sections.
5.4.6.7 Cordless impact driver and suitable screws (Collated / non collated) shall be used
to assemble the frame
5.5.1.3 Base frame to be aligned, where necessary jacks and power tools shall be used
5.5.1.4 Skids shall be levelled by using a water level
5.5.6 Flooring
5.5.6.1 Cement fibre board decking shall be cleaned before starting the flooring
5.5.6.2 Any level difference in floor shall be minimized
5.5.6.3 Putty shall be applied on cement fibre board screw holes and to be levelled by
sanding
5.5.6.4 Swisstrax floor installation as per manufacturer guidelines
5.5.11.1 External façade finish shall be 5mm thick custom fabricated GRP panels
5.5.11.2 GRP façade to be fixed to the structure by screws & PU glue
5.5.11.3 Front façade molding to be fixed in same manner
5.5.11.4 Joint between front façade & walls & roof to be sealed by specified silicon sealer
5.5.11.5 Sealant to be applied around windows & the other joints to prevent the entry of
water
5.5.11.6 Workers will perform this activity by using A type ladder or mobile scaffolding
6.0 ATTACHMENT
6.1 Lifting Plan