Professional Documents
Culture Documents
Comos Execution Application Vivita
Comos Execution Application Vivita
VERSUS
Mumbai -400050.
Manpada Road,
Dombivali (E)- 421201
…RESPONDENTS
(Judgment Debtors)
C. Date of Award 05th March, 2014
D. Whether any Appeal is No
preferred against
Award/Whether Application
has been preferred for setting
aside award
E. Whether any and (if No
any) what adjustment
of the matter in dispute has
been made between the
parties
subsequently to the
Award.
F. 1) The date and nature No
of any Writ issued
before or after award.
2) Whether any No
previous application is made
seeking execution of award.
G The amount of debt or Decreetal amount inclusive of cost
Rs.17,12,04,311.68/-
4
SCHEDULE
Mumbai- 400705.
Mumbai
Date This day of October, 2016
Applicant/Decree holder
THE COSMOS CO-OP. BANK LTD
VERIFICATION
Before me,
Identified by
Applicant/Decree holder
THE COSMOS CO-OP. BANK LTD
THE LAUREATE
ADVOCATES FOR THE APPLICANT
7
15.Bank of Baroda
Industrial Finance Branch
Baroda House, 42, Cawasji
Patel Street, Fort, Mumbai- 4000 …RESPONDENTS
(Judgment Debtor)
10
AFFIDAVIT
2. I say that certain disputes had arisen between the Decree holder and
Judgment Debtor under a contract which was ultimately referred to the learned
Arbitrator Mr. M.M. PARILKAR.
3. Inspite of intimation/ notices, except for the Respondent Nos. 1,2 and 8,
the other Respondents failed to appear before the learned Arbitrator therefore
the learned Arbitrator was pleased to make and publish his Award on 5th
March, 2014.
5. I further say that the said award is duly served upon the Respondents and
appealable period of 90 days from the service of award is 03rd June, 2014 as
provided under Section 34 of Arbitration and Conciliation Act 1996 has expired.
I say that till date the said award has not been challenged by any of the
Respondents. Therefore, the Applicant i.e. the Claimant can execute the said
award as decree of the Court under section 36 of the Arbitration and
Conciliation Act, 1996.
6. I say that the sole arbitrator was please to make and published Award
against respondent on 5th March, 2014 in the matter. The Learned Arbitrator
please pass on award for recovery of amount of Rs. 18,22,18,401.05/- plus
interest at rate of 14% p.a. from 1st April, 2010
till payment of whole amount to the Claimant Bank i.e. till date of filing of the
Execution Application which in this case is 16/12/2016. Cost of the Arbitration
11
7. I say that the Claimant has not taken out any execution proceedings or
made any application prior to the date of filing of this affidavit for execution of
the award and as of today neither any appeal nor any proceedings is pending in
the above matter.
8. I say that Respondents have not filed Petition under Section 34 of the
Arbitration and Conciliation Act, 1996 for setting aside the award. The
Respondent have not challenged the award before any court. The execution has
not be stayed be any court. As per the provision of Arbitration and Conciliation
Act, 1996 the award dated 05/03/2014 has become more a decree.
9. I say that the award has been passed on 5th March, 2014 and the
Claimants filing the present application after the period of period of two years
from date of award as provided under order XXI, rule 22 of CPC 1908,
therefore the present execution is within time.
10. I further say that as per knowledge of the Claimant property mentioned
in the column “J” of the above execution application are belonging to the
Respondents and same are situated within the jurisdiction of this Hon’ble Court
therefore this Hon’ble Court has jurisdiction to try and entertain the present
execution application.
11. I say and submit that it is normal procedure of the claimant Bank to visit
and verify addresses of Respondents at the time of granting loan to
Respondents. I further say and submit that before granting loan to Respondent
Nos. 1 to 4 above the claimant Bank had visited commercial premises of the
Respondent No.1 and residential address of Respondent Nos. 2 to 4 and has
verified that furniture, fixture and other movable articles belong to Respondent
Nos. 1 to 4 above named.
13. I further say that the Applicant has not taken out in Execution
Proceedings or made in any application prior to this date. I further say that the
Claimant, i.e., the Applicant hereinabove has not received any amount from the
Respondent Nos. 1 to 4 after the Award dated 5 th March, 2014 is passed and
pending these proceedings.
12
The Laureate
Advocates for the Applicant/
Decree Holder
VERSUS
…RESPONDENTS
(Judgment Debtors)
Rs.50,06,762.40/-
SCHEDULE
Fixtures, Furniture’s, fittings and all other
attachable moveable articles belonging to and in
possession of the Respondents above named, lying
and being in their commercial premises of
Respondents at the registered office at
65, 2nd Floor, Bombay Samachar Marg, Mumbai
400 023.
Mumbai
Dated this day of June, 2017
Applicant/Decree holder
THE COSMOS CO-OP. BANK LTD
17
VERIFICATION
Before me,
Identified by
Applicant/Decree holder
THE COSMOS CO-OP. BANK LTD
THE LAUREATE
ADVOCATES FOR THE APPLICANT
18
VERSUS
…RESPONDENTS
(Judgment Debtors)
AFFIDAVIT
having its Regional office At 36 A, Maru Niketan D.L. Vaidya Road, Dadar
(West), Mumbai 400028, do hereby solemnly affirm and state as under;
2. I say that certain disputes had arisen between the Decree holder and
Judgment Debtor under a contract which was ultimately referred to the learned
Arbitrator Mr. V.G.Indrale.
5. I further say that the said award is duly served upon the Respondents and
appealable period of 90 days from the service of award was till ___________ as
provided under Section 34 of Arbitration and Conciliation Act 1996 has expired.
I say that till date the said award has not been challenged by any of the
Respondents. Therefore, the Applicant i.e. the Claimant can execute the said
award as decree of the Court under section 36 of the Arbitration and
Conciliation Act, 1996.
6. I say that the Sole Arbitrator was pleaseed to make and publish Award
against Respondents on 22nd January, 2016 in the matter. The Learned Arbitrator
has been pleased to pass an Award for recovery of amount of Rs. 42,67,612/-
21
(Rupees Forty Two Lac Sixty Seven Thousand Six Hundred and Twelve only)
plus interest at rate of 16% p.a. from 1st February, 2010, till payment of whole
amount to the Claimant Bank. The amount due and payable by Respondents till
31st May, 2017, i.e., the amount of Award and the interest @ 16% p.a. from 1 st
February, 2010 to 31st May, 2017 is Rs. 92,74,374.40/- (Rupees Ninety Two Lac
Seventy Four Thousand Three Hundred and Seventy Four Paise Forty only)
alongwith cost of the Arbitration of Rs. 56, 176/- (Rupees Fifty Six Thousand
One Hundred and Seventy Six only). Thus, total amount due Rs. 93,30,550.40/-
(Rupees Ninety Three Lac Thirty Thousand Five Hundred and Fifty Paise Forty
only) and further interest @ 16% p.a. on Rs. 42,67,612/- (Rupees Forty Two
Lac Sixty Seven Thousand Six Hundred and Twelve only) from 1 st June, 2017
till payment due.
7. I say that the Claimant has not taken out any execution proceedings or
made any application prior to the date of filing of this affidavit for execution of
the aforesaid award and as of today neither any appeal nor any proceedings is
pending in the abovesaid matter.
8. I say that Respondents have not filed Petition under Section 34 of the
Arbitration and Conciliation Act, 1996 for setting aside the award. The
Respondents have not challenged the award before any Court. The execution
has not be stayed be any Court. As per the provisions of the Arbitration and
Conciliation Act, 1996 the award dated 22nd January, 2016 has become a decree.
9. I say that the award has been passed on 22nd January, 2016 and the
Claimants filing the present application within a period of two years from date
of award as provided under Order XXI, Rule 22 of CPC 1908, therefore the
present execution is within limitation.
11. I say and submit that it is normal procedure of the Claimant Bank to visit
and verify addresses of Respondents at the time of granting loan to
Respondents. I further say and submit that before granting loan to Respondent
22
Nos. 1 to 4 above the claimant Bank had visited commercial premises of the
Respondents and residential addresses of Respondents and has verified that
furniture, fixture and other movable articles which belong to Respondents above
named.
13. I further say that the Applicant has not taken out in Execution
Proceedings or made in any application prior to this date. I further say that the
Claimant, i.e., the Applicant hereinabove has not received any amount from the
Respondents after the Award dated 22nd January, 2016 is passed and pending
these proceedings.
The Laureate
Advocates for the Applicant/
Decree Holder
23
VERSUS
…RESPONDENTS
(Judgment Debtors)
Rs.48,50,414.73/-
SCHEDULE
Fixtures, Furniture’s, fittings and all other
attachable moveable articles belonging to and in
possession of the Respondents above named, lying
and being in their commercial premises of
Respondents at the registered office at
65, 2nd Floor, Bombay Samachar Marg, Mumbai
400 023.
400 023.
Mumbai
Dated this day of June, 2017
Applicant/Decree holder
THE COSMOS CO-OP. BANK LTD
28
VERIFICATION
Before me,
Identified by
Applicant/Decree holder
THE COSMOS CO-OP. BANK LTD
THE LAUREATE
ADVOCATES FOR THE APPLICANT
29
VERSUS
…RESPONDENTS
(Judgment Debtors)
AFFIDAVIT
having its Regional office At 36 A, Maru Niketan D.L. Vaidya Road, Dadar
(West), Mumbai 400028, do hereby solemnly affirm and state as under;
2. I say that certain disputes had arisen between the Decree holder and
Judgment Debtor under a contract which was ultimately referred to the learned
Arbitrator Mr. V.G.Indrale.
5. I further say that the said award is duly served upon the Respondents and
appealable period of 90 days from the service of award was till ___________ as
provided under Section 34 of Arbitration and Conciliation Act 1996 has expired.
I say that till date the said award has not been challenged by any of the
Respondents. Therefore, the Applicant i.e. the Claimant can execute the said
award as decree of the Court under section 36 of the Arbitration and
Conciliation Act, 1996.
6. I say that the Sole Arbitrator was pleaseed to make and publish Award
against Respondents on 22nd January, 2016 in the matter. The Learned Arbitrator
has been pleased to pass an Award for recovery of amount of Rs. 41,34,346/-
32
(Rupees Forty One Lac Thirty Four Thousand Three Hundred and Forty Six
only) plus interest at rate of 16% p.a. from 1st February, 2010, till payment of
whole amount to the Claimant Bank. The amount due and payable by
Respondents till 31st May, 2017, i.e., the amount of Award and the interest @
16% p.a. from 1st February, 2010 to 31st May, 2017 is Rs. 89,84,760.73/-
(Rupees Eighty Nine Lac Eighty Four Thousand Seven Hundred and Sixty Paise
Seventy Three only) alongwith cost of the Arbitration of Rs. 54, 843/- (Rupees
Fifty Four Thousand Eight Hundred and Forty Three only). Thus, total amount
due Rs. 90,39,609.73/- (Rupees Ninety Lac Thirty Nine Thousand Six Hundred
and Nine Paise Seven Three only) and further interest @ 16% p.a. on Rs.
41,34,346/- (Rupees Forty One Lac Thirty Four Thousand Three Hundred and
Forty Six only) from 1st June, 2017 till payment due.
7. I say that the Claimant has not taken out any execution proceedings or
made any application prior to the date of filing of this affidavit for execution of
the aforesaid award and as of today neither any appeal nor any proceedings is
pending in the abovesaid matter.
8. I say that Respondents have not filed Petition under Section 34 of the
Arbitration and Conciliation Act, 1996 for setting aside the award. The
Respondents have not challenged the award before any Court. The execution
has not be stayed be any Court. As per the provisions of the Arbitration and
Conciliation Act, 1996 the award dated 22nd January, 2016 has become a decree.
9. I say that the award has been passed on 22nd January, 2016 and the
Claimants filing the present application within a period of two years from date
of award as provided under Order XXI, Rule 22 of CPC 1908, therefore the
present execution is within limitation.
11. I say and submit that it is normal procedure of the Claimant Bank to visit
and verify addresses of Respondents at the time of granting loan to
Respondents. I further say and submit that before granting loan to Respondent
33
Nos. 1 to 4 above the claimant Bank had visited commercial premises of the
Respondents and residential addresses of Respondents and has verified that
furniture, fixture and other movable articles which belong to Respondents above
named.
13. I further say that the Applicant has not taken out in Execution
Proceedings or made in any application prior to this date. I further say that the
Claimant, i.e., the Applicant hereinabove has not received any amount from the
Respondents after the Award dated 22nd January, 2016 is passed and pending
these proceedings.
The Laureate
Advocates for the Applicant/
Decree Holder