Professional Documents
Culture Documents
Monopole Design & Test
Monopole Design & Test
Monopole Design & Test
1. BACKGROUND:
This tender is only for the Supply, Manufacture and Delivery of Steel Monopoles required
by the PEC team for the construction of a new Marib 33kV Transmission line.
The following type of tubular towers for 220kV, 132 kV and 66kV transmission lines
b) Special Towers.
The towers are of self-supporting tubular pole (herein referred as Tower), designed to
carry the line conductors with necessary insulators, Earthwire/ OPGWs and all fittings under
all loading conditions.
2. SCOPE OF WORK:
3. CONDITION:
The monopoles are to be designed for 33KV double circuit lines with vertical formation &
one conductor of 400mm2 aluminum conductor steel reinforced 400mm2 ACSR as BS
215.2 standards Zebra and (5/3.22AL+7/3.22St) mm OPGW at the top. Monopoles shall
also be designed suitable for stringing single circuit on one side of the monopole.
1
The monopoles are to be designed conforming to reliability level 1 of ( IEC 60826 & ASCE
Manual No:72) for a ruling span of 300m for the details mentioned in following paras & as
per the general arrangement provided in the sketches enclosed (Drawing N02). The steel
sections considered for design should conform to EN 10025/1-6 Grade S355JO (Yield
Strength 350 MPa).
4. TYPE OF MONOPOLES
The two nos. monopole types proposed are as detailed below:-
5. WIND PRESSURE:
The wind load on structures shall be calculated based on basic wind speed between of 180 to
200 km/hr. at 1 Om height with importance factor of 1 .1 5.
2
5.1 Wind Span & Weight Span:
The following wind spans and weight spans shall be adopted for the design of all types of
monopole structures.
a) Climatic Loads:
These are random loads imposed on monopole, insulator string, conductor &
ground wire due to action of wind on transmission line & do not act continuously. Climatic
loads shall be determined under either of the following climatic conditions whichever is
more stringent:
1
1) 100 percent design wind pressure at every day temperature (45° C) or
2) 36 percent design wind pressure at minimum temperature (-2.5°C).
2
conductors & ground wire intact only on one side of the monopole.
a) Transverse load: These loads shall be taken under no wind condition.
b) Vertical Load: These loads shall be the sum of weight of conductor/ground wire as
per weight span of intact conductor/ground wire, weight of insulator strings and accessories.
c) Longitudinal Loads : These loads shall be the pull of conductor/ground wire at every
day temperature & no wind applied simultaneously at all points on one side with zero degree
line deviation.
PEC Engineer/ Consultant. Since the monopoles are proposed to be provided on the road
divider having approx. Width of 3 meter, the width of the foundations above ground level
shall not exceed one (0.6) meter for tangent/ straight poles & (1.0) m for the angle poles.
Further, the dimensions of the base pad of the foundations may also be kept as minimum as
possible. The bearing capacity of soil shall be taken as 15 T/Sqm.
7. Monopole Configuration:
The monopole configuration shall be conforming in general to the out line diagrams
enclosed (Drawing N02).
8. Electrical Clearances:
i) Ground Clearances:
The minimum ground clearance from the bottom of the conductor shall not be less than 12
M for 33KV Monopoles at the maximum sag condition at maximum temperature and still
air. The total height upto X-arm shall be equal to ground clearance (+) Max. Sag of 2.5 m
( as the poles are to be designed for low tension) (+) Length of Suspension String and for
3
angle monopoles ground clearance (+) max. sag of 2.5 m (as the poles are to be designed for
low tension) (+) 4% of Max sag to cover Creepage & stringing errors.
ii) Live Metal Clearance:
The following minimum clearances between the live parts, monopole & cross arm members
shall be as under:
Clearance
Swing
mm
Nil 1400
1 Single Suspension Insulator String 15 1400
45 610
Nil 1400
3 Jumpers 15 1400
20 610
Vertical 2000
4 Between conductors
Horizontal 3500
The angle of shield by the line joining the center line of the earth wire & top power
conductor in still air at monopole supports to the vertical line shall be
iv) Mid Span Clearance between Earth wire & Power Conductor is to be kept more than the
clearance at monopole. The earth wire sag shall be not more than 90 percent of the
corresponding sag of power conductor under minimum temperature condition for normal
span for the entire specified. The mid span clearance shall be reckoned as direct distance
between earth wire & top power conductor.
4
9. Design Temperature:
The following temperature range for the conductors & ground wires shall be adopted for the
line design.
11. Structure Design: Structures shall be designed so that member unit stress does
not exceed the yield point stress of the material. The ratio of major axis of tubular diameter
to wall thickness shall be such that local buckling does not govern member design.
12. Deflection: Structure deflection under maximum load condition including over
load factors shall be no more than 5 % of the structure height.
13. Pole Shape : Cross section of the pole shall be 12 sided polygon and
shall be tapered from top to the base of minimum three sections shaft. Cross arm member
shall be of polygonal cross section with taper and shall conform to PEC's general
arrangement drawings. The strength of the attachment of cross arms to the columns shall be
sufficient to develop the full capability of the cross arm. Members requiring more than one
length of tubular section shall be constructed by telescoping the sections together with
sufficient overlap to develop the full strength of the member. Minimum overlap shall be 1.5
times the maximum inside diameter of outer section at the telescopic joint. Rigging
accessories, insulator attachment plates, ladder, lugs for bolted steps and lighting brackets,
and hand line attachment shall be welded to the structure.
14. Structural Analysis.
Elastic methods of analysis shall be used. Stability shall be provided for the structure as a
whole and for each structural element. The load effects resulting from the deflected shape of
the structure and individual elements shall be considered during design.
The analysis shall include all structural members in their actual manufactured geometry and
sizes.
The structural design of the pole shall be done using proper design software.
5
15. TESTING OF MONOPOLES
15.1 General: All standard tests, including quality control tests in accordance with relevant
ASTM / ASCE shall be carried out. The black monopole of each type shall be subjected to
design and destruction tests by applying tests equivalent to the specified maximum, in
manner approved by the purchaser (i.e PEC). The monopoles shall withstand these tests
without showing any sign of failure or permanent distortion in any part. Thereafter the
monopoles may be subjected to destruction by increasing the loads further in an approved
manner till they fail. No part of any monopole subject to test shall be allowed to be used in
the work. The price will be quoted after allowing rebate for the scrap value for the
monopole material which will be retained by the supplier.
In case of premature failure, the monopoles shall be retested. The supplier shall
provide facilities to the owner or their representatives for inspection of materials during
manufacturing stage and also during testing of the same.
The supplier shall submit to the owner for approval, his detailed program and
proposal for testing monopoles showing the methods of carrying out the tests and manner of
applying the test loads. After the owner has approved the test procedures and programs, the
contractor will intimate the owner about carrying out of the tests at least 10 day in advance
of the scheduled date of tests during which the owner will arrange to depute his
representative to be present at the time of carrying out the tests. Six copies of the test reports
shall be supplied.
6
the before load, 'load on' and 'load off' conditions.
15.4 TESTING PROCEDURE DETAILS:
The testing procedures shall be in accordance with the relevant ASTM / ASCE codes &
standards.
15.4.1 SEQUENCE OF TEST LOADING CASES:
Sequence of test loading cases shall be pre-determined. The choice of the test sequence shall
largely depend upon simplification of the operations necessary for carrying out the test
program.
15.4.2 DETAILS OF TESTS:
Test 1 :(Broken wire Condition) Security and Safety Conditions as well as Ant cascade
condition.
A) Each type of monopole to be tested shall be a full scale proto type black monopole and
shall be erected vertically on rigid. The monopole erected on test bed shall not be out of
plumb by more than 1 in 360.
B) CALIBRATION OF MEASURING INSTRUMENTS
Under these conditions (all conditions involving longitudinal loads in addition to the
transverse and vertical loads) all the transverse and vertical loads are first increased to about
100%. Longitudinal loads are then increased in steps of 50%- 75%90%-95% of the ultimate
loads. At all stages of loading it shall be ensured that the transverse and vertical loads are not
less than the values for corresponding step of the longitudinal load. At each step the loads
are maintained for two minute and the deflections are noted. All loads are then increased to
100%. At this final 100% loading stage, monopole is observed for 5 minutes and deflections
are noted. the monopole is required to withstand these loads without showing any failure.
After every test the loads are brought down and deflection readings are taken for no load
condition.
7
in step of 5% till the failure occurs. The point of failure is detected from the sudden drop of
load indication in the instrument dials in the Control Room.
8
I) In the case of failure:
i) a table showing the maximum loads applied to the structure, just before the collapse.
m) A certain number of photographs, showing the whole of the structure and, possibly,
details of the failure.
9
furnished.
C) After Monopole Testing:
After the successful monopole testing the following details/drawings have to
be submitted for approval:
10
Technical Particulars of Monopoles
11
2. GENERAL PARAMETERS
Length 4 Km
Number of circuits Double
Number of conductors per phase 1
Number of OPGW
Number of earth wire
Monopoles
Surface treatment Hot dip galvanized as ASTM A 123
Standard
Number of Monopoles Min 28
Span 150 m
Thickness 18-22 mm
12
Length 18 m
Octagonal, Polygonal
Shape
Joint with insert mode, flange mode
Joint
22mm
bolt diameter
3m Coated above ground
Painting
Concrete foundation pits
Foundation Not embedded
Against earthquake of 8 grade
Design of poles
High strength cross arms
Cross arms
2.0 – 2.5
Factor of safety
CONDUCTOR
400mm2
ACSR
Zebra
Designation
Standard BS 215.2
Material ACSR
13
Continuous current rating (80°C) A
OPGW
Voltage Level 33 KV
Sectional area -
Aluminum alloy 88.7 mm
Steel 57 mm
14
15