Professional Documents
Culture Documents
Otc 13997
Otc 13997
Otc 13997
and cleaning pumps, piping systems, ventilation number of ballast tanks and need to ballast the bottom
equipment and piping system, etc. spaces, tank layout, piping arrangement, ballast plan, etc.
If the costs of the loading and offloading operations for
The difference in cost for DS-SB and DH configurations the two candidate configurations are also significantly
varies from shipyard to shipyard, depending on past different, these costs must also be taken into account in
experience and set-up of the shipyard. The authors have the cost comparison.
not found statistical comparison of construction costs
directly for DH and DS-SB hulls. However, references [6] G. Maintenance, On-site Repair and Structural Inspection.
and internal research indicates that construction of a DH For tankers, DH configuration generally costs more on
tanker can be 10% to 20% more expensive than a same these factors than the DS-SB configuration. Compared to
size SH tanker. Reference [5] gives some more detailed DS-SB hull, the DH can increase the number of structural
comparison of construction cost between DH and SH connections by about 10% to 15%. The connections
tankers. The difference in cost varies from 9.9% to 17% between stiffeners and transverse floors can be prone to
for various taker sizes. For the Aframax, Suezmax, and cracking and thus require more attention (inspection,
VLCC tankers, DH configuration can increase the maintenance, and/or even repair). The inner hull knuckles
construction cost by 16.7%, 17%, and 15%, respectively. may have similar problems. The double bottom requires
Because the difference between DH and DS-SB is less increase of exposed steel surfaces in the double bottom
than the difference between DH and SH, the difference in ballast tanks, which significantly increases coating area.
construction cost of DH and DS-SB hulls should also be The current coating technology can ensure quality of
less. A simple survey of the shipyards in the Far East coating for only about 10 years. For a FPSO to be
indicates the cost difference may fall in about 5%. Most operated for 20 to 30 years without dry-docking,
shipyards have experience in design and construction of inspection, maintenance and repair of the coating of the
both configurations but slightly prefer DS-SB. double bottom surface are really a heavy and costly task.
E. Costs Associated with Crude Oil Washing, Tank On the other hand, the double bottom also brings some
Cleaning, and Tank Stripping. In general, such operations benefits to maintenance and repair, especially when
for a DH are easier than those for a DS-SB hull. considering hot work at the cargo tank bottom. For
Although there is no data that shows significant cost instance, the smooth upper surface provided by the double
increase for a DS-SH hull, care should be taken in the bottom reduces steel surface area exposed to the lower
design of the Tank Cleaning system to assure it will layer of cargo liquid, which reduces the corrosion area on
adequately clean the tank to minimize or eliminate the inner surface of the cargo tank bottom and eases the
need for manual demucking. There may be a slight associated inspection and maintenance. In case some
increase in the cost to increase the number and efficiency repair work is required on the cargo tank bottom or the
of he tank-cleaning guns. Modification to the hull bottom near areas, the work can be relatively easily done as long
for a sump to improve the tank stripping operation is as the contaminates in the double bottom and other
recommended for both the DH and DS-SB hulls. . adjacent tanks are removed and the tanks are ventilated.
Compared to a DH vessel, a DS-SB vessel has more However, if a similar repair work is needed at the cargo
shadow areas, more exposed surfaces, and more tank bottom of a DS-SB hull, high cost wet welding
obstructions at its single bottom. Washing and stripping techniques or cofferdams need to be applied, which
the smooth surface of the cargo tanks of a DH vessel are increases not only the cost but also the difficulties in
obviously easier. Cost affected by these factors covering adequately performing the repairs and may negatively
both CAPEX and OPEX may vary from vessel to vessel. affect production. The cost due to such difficulties and
So far no comparable statistics have been found. associated risks is accounted in Factor K.
Designers should estimate the cost for the two
configurations based on cost of equipment, frequency of Another item associated with the inspection and
such operations, and manpower required for the vessel to maintenance costs is the ventilation of the double bottom
be designed. space of DH vessels. In the case of oil leakage, the double
bottom spaces may contain some pockets of flammable
F. Ballasting, Loading and Offloading Operations Cost, gases that can cause fires and/or explosions. Even without
Including equipment Cost and the Operation Cost. oil leakage, the double bottom space may contain some
Compared to a DS-SB hull, the double bottom spaces of a pockets lacking of oxygen and/or H2S rich environments
DH vessel require more pumps and associated piping due to decaying marine life in the moist environment.
systems. The ballasting operation for DH vessels is also Adequate ventilation must be provided to all the double
somewhat more costly although it may provide a bit more bottom spaces before inspection, maintenance, or repair
flexibility in trim and heel control. The actual difference work can be done in the areas. In contrast, DS-SB vessel
in cost of ballast system and operations depends on actual and SH vessel do not require that because they do not
OTC 13997 A RATIONAL APPROACH TO FPSO HULL CONFIGURATION SELECTION 5
have a double bottom space. However care must still be I. Asset Loss and Oil Leakage or Spill due to Side Collision
maintained in inspecting these spaces as pockets, which Damage: Collision energies necessary to cause hull
are oxygen depleted, can still exist when moving between penetration and cargo tank breach vary between hull
spaces and bulkheads. The direct cost associated with the configurations. Various sources have shown that a typical
inspection, maintenance and repair operations is SH vessel can be penetrated with an energy of
accounted here but the potential cost due to the risks of approximately 15 MJ. On the other hand, a typical DH
potential explosion and/or fire is accounted in Factors J wing tank of 2m in width would require approximately
and K for the potential asset loss and health and safety 170 MJ to penetrate the longitudinal bulkhead storing the
risks, respectively. oil (approximately 205 MJ for a 2.5m wing tank width).
Various vessels can produce such energies based on their
The difference in cost of maintenance and repair between mass and typical speeds while maneuvering near the
SH and DH tankers is significant. Reference [6] shows FPSO or when errant and underway. Because both DH
that cost for DH tankers can be 10% to 20% higher than and DS-SB configurations have double side structures, the
SH tankers. Reference [5] indicates that it is 11% for comparison of advantages of these two configurations
VLCC class and 28% for Suezmax class. Because no requires consideration of tank layout and structural
comparison of cost has been reported for DS-SB and DH design. For a given size FPSO, the DS-SB hull can have
FPSOs, the above information may be used as a reference wider wing tanks that can considerably increase the
for estimation of such costs. energies required to penetrate its longitudinal bulkhead,
which can significantly reduce the probability of oil
Category 3: Potential Asset Loss, Health, Safety and leakage and/or spill. An extreme example is a recently
Environment Related Factors designed DS-SB FPSO hull that has wing tank width
The factors grouped within this category also strongly affect wider than the MARPOL required limit side collision
decision for hull configuration selection but the associated cost damage assumption of 11.5m. In theory, the energies
cannot be estimated in the same way as that applied to the pure required to penetrate the longitudinal bulkhead are so high
expenditure related factors listed in Category 2. The cost that the penetration is hardly to occur in reality. However,
impact of these factors is associated not only with the such increase in wing tank width may negatively impact
consequence of the events but also the probability of vessel damage stability [7], i.e., it may increase maximum
occurrence of such events as well. As shown later, cost due to heel and in the case of a side collision damage occurred.
these factors can be estimated using a risk analysis approach. Therefore, these two effects must be both taken into
consideration in the design phase to optimize the wing
H. Asset Loss and/or Oil Leakage or Spill due to Bottom tank dimensions as part of hull configuration selection.
Damage: Factor A covers the cases in which the
possibility of grounding or other causes of bottom damage J. Cargo Tank Bottom Cracks and/or Corrosion and
is high. For such cases, a DH configuration is a natural Associated Problems. As discussed above under Factor G,
and logical choice. However, in most cases the probability the cargo tank bottom of a DH configuration can be prone
of occurrence of grounding or bottom collision is not to cracks. The main cause to the cracks is structural
high, or even very low. Judgment of the effect of this fatigue. DH configuration tends to have a structure, which
factor should be made based on risk analysis results. In is stiffer than a DS-SB hull configuration, which may
general, consequence of grounding for a DS-SB hull is result in higher residual stresses induced during
more severe than that for a DH vessel because the fabrication and the local stresses due to the loads
double bottom structure provides more resistance to in operations [7].
bottom damage.
Compared to the bottom of a DS-SB hull, the cargo tank
There are many factors affecting the possibility of bottom of DH configuration can also be more prone to
grounding, raking and the ensuing bottom damage. Major corrosion, for same level coating quality maintenance.
factors include the reliability of the vessel's mooring The main factors contributed to this include:
systems, metocean conditions and the nature of prevailing • The increase in the steel surface area exposed to
winds following a potential mooring damaging event, the corrosive liquid due to the existence of the double
associated amount of surrounding land mass density and bottom space can result in more extensive corrosion
structures within proximity to the site; marine traffic, problems [8],
especially the traffic posing a threat to the integrity of the • Higher temperature of crude oil loaded in cargo tanks
mooring system and/or its station keeping capability; due to the insulating effect of double bottom
dropped objects that may damage or weaken mooring (thermos-bottle effect), coupled with the residual
systems, etc. All these should be considered in the water in cargo tanks, can offer very favorable
relevant risk analysis. conditions for anaerobic bacteria to proliferate and
activate accelerated surface corrosion [9][10],
6 M. WANG, P. MCNEELY, C. SERRATELLA OTC 13997
A potential result of structural cracks at the cargo tank analysis together with application of risk analysis to perform
bottom of a DH vessel is crude oil leakage into the double similar cost benefit analysis for HSE related risks. The basic
bottom spaces, which may lead to fire and/or explosions premise is as follows:
given an ignition source. Factor G accounts for only the • The requirements associated with factors in Category 1
cost of ventilation operations. The potential cost due to (Factors A and B) together with the functional
the fire and/or explosion can be estimated here as a requirements and regulatory requirements are considered
consequence of the cargo tank bottom cracks. This impact as mandatory (Factor C). For instance, if a FPSO is
can be factored into a risk assessment, as described later functionally required to have a dis-connectable
in this paper. The potential threat to personnel who mooring/riser system, a DH configuration should be used
conduct inspection, maintenance, and repair in double because once it is dis-connected it is considered as a
bottom spaces is considered in Factor K. vessel, not a platform.
• The effects of all factors in Category 2 can be reasonably
K. Risks to the operation, inspection, maintenance, and estimated either based on design information or past
repair personnel. These include the following factors: experience of the operating company.
• Access to the cargo and ballast tanks, as discussed in • Use of risk analysis techniques to estimate effects of the
Factor G. In general, access to the double bottom factors in Category 3.
spaces of a DH FPSO is an additional effort and risk,
compared to a same sized DS-SB hull. Slips, trips, This step-by-step manner approach can be described in the
and falls may cause dangers to the inspection, flow chart given in Figure 2.
maintenance, and repair personnel.
• The threat to health and safety of the personnel doing
Inspection, maintenance, and repair in double bottom Step 1: Does the yes
spaces. This should be considered even the double FPSO have factors DH
bottom is fully cleaned and ventilated. falling in Category 1 configuration
• Operations of tank cleaning associated with Factor E.
In case significant mud deposits in cargo tanks,
manual cleaning of those cargo tanks for a DS-SB No
hull may be required, which can also pose some risks
to health and safety of personnel who carry out Step 2: Identify other Yes
such tasks. factors and categorize
• The additional difficulties in hot work to repair them
bottom of a DS-SB hull can also pose certain level of
risk to the personnel on duty. Refer to Factor G for
the risk associated with this item. Step 6:
• The possibility for piracy and sabotage associated Step 3: Step 4: Does the
with the risks described in Factors H and I. Calculate Calculate DS-SB
total cost the total cost more?
It should be noted that the above listed factors are for generic of all the risk cost of
FPSOs. Each project may have some particular factors to be factors in all the
considered. These special factors may come from particular Category 2 factors in
production requirements (special feature of crude oil, gas, or for DS-SB Category 3 No
other products), special features of field metocean conditions, and DH for DS-SB
output and offload/transportation of cargo, production process, & DH
etc. Designers should identify the factors based on the actual
situations within the field and its associated requirements. The
manner in which the factors are categorized and the factors DS-SB
themselves given in this section should be used as an outline Step 5: Sum up the total
cost in Steps 3 & 4 for configuration
of the types of issues which should be considered in such
decision. DS-SB & DH,
respectively
Methodology
As shown above, there are so many factors that affect Figure 2. Hull Configuration Selection Approach
selection of hull configuration, some easily quantifiable, some
not. To accommodate all of these, a hybrid approach is
developed for the decision-making. This approach is a
combination of qualitative and quantitative cost benefit
OTC 13997 A RATIONAL APPROACH TO FPSO HULL CONFIGURATION SELECTION 7
Some details of each step given in the flow chart for the association with probability of occurrence of assumed events.
approach are described below. Different from the calculation of costs in step 3, risk analysis
method should be used in calculation of costs in this step. A
Step 1: Although IMO and many countries have required DH brief description of such risk analysis methodology is given in
configuration for tankers, no existing international regulation Appendix A.
strictly requires DH configuration for conventional FPSO that
is permanently moored at the site. However, if the FPSO is Step 5: After completing the cost calculation for each of the
judged as a “sailing vessel” the DH requirements may be individual factors in Categories 2 and 3, the costs for each hull
applicable. Definition of “sailing vessel” is not so clear and configuration (DH and DS-SB) should be summed to get the
frequently attracts some interesting debates. In the first case total cost for all the factors considered.
(the first bullet) of Factor A, DH requirement is usually
applicable. In addition, some states may place such Step 6: Comparison of the costs and decision-making. The
requirements for FPSO in the near future. The MMS has been approach developed in this paper is a cost based decision
working on such issues. Waiver of DH requirements from rule making approach, which accounts for both CAPEX and OPEX
requirements of some classification societies may require and covers both certain and potential costs. In theory, the
some kind of applications. Designers should take necessary configuration that costs less should be the one to be selected.
actions based on the actual situation of the project.
A difficult situation is when the costs for the two
Step 2: In identification of factors, the frame laid out in the configurations are very close to each other. If this happens,
“Factors Affecting Hull Configuration Selection Decision consultation with project operation team should be made to
Making” section can be used. Caution should be paid to consider preference of operation team. Other factors should
completeness of all the major factors and avoiding duplicated also be considered such as proximity of the site to
account of effects of the factors. In some cases, many factors environmentally sensitive areas or political risk associated
are involved in one issue. Each of these factors addresses a with an oil spill. The owner and/or operator’s past practice
different aspect of the issue. Let’s take the maintenance of should also be taken into consideration in dealing with such
double bottom as an example. The cost of the maintenance situations, including the crew and associated parties’
itself (e.g., material, ventilation, labor, etc.) should be familiarity with a hull configuration (particularly for
calculated in Factor G, but the cost associated with the operation, inspection, maintenance, repair), and effect of
potential personnel risks associated with the maintenance is the human element on probabilities of an accident
calculated in Factor K. The risk due to the potential explosion during operations.
or fire in double bottom space may also be related to the
maintenance, but it should be calculated in Factor J. Basically, Hull Configurations of the Existing and the near
calculation of the effects of each factor should not have Future FPSOs and Relevant Experience
overlap in terms of cost. This principle is applicable to all the As mentioned in the introduction, all of the three hull
factors listed in Categories 2 and 3. configurations, SH, DH, and DS-SB, has been used as FPSOs.
Some information on hull configurations used in past or
Step 3: Calculation of costs associated with the factors listed considered for the near future is summarized here to provide
in Category 2 is somewhat straightforward. The cost should some useful reference for the reader.
cover both CAPEX and OPEX for each factor, i.e., cost of
equipment, structures, construction, labors, etc. that are Table 1 shows the number of each configuration of part of the
invested during the life of the FPSO and the cost of operations new build FPSO/FSO fleet in operation, based on the Aker’s
associated with these factors. A subtle part of such cost is the date base (published once a year in Offshore magazine) that
costs due to interruption or reduction of FPSO production that covers a total of 24 FPSOs/FSOs. The data is based on early
is a direct result of the operations associated with these 2000 figures. Authors acknowledge that this is a small and
factors. For instance, if the maintenance and repair for a DS- incomplete date base and will keep expand it. The difficulty in
SB hull requires reducing production by 20% of normal including all the FPSOs/FSOs is that many date bases do not
production rate for 2 days annually. An additional annual cost specify hull inner configuration.
for this DS-SB of 0.4 times daily production value should be
included in the total cost of the SB-DS configuration. Table 1 indicates that as of early 2000;
Calculation of cost in this category should be based on the • SH is the least popular choice.
design data, existing date bases, past design and/or operational • DH configuration is still dominant
experience. The information provided in the last section may • DS-SB is an important choice of hull configuration.
also be used as reference.
Table 1 also shows that location where a FPSO is permanently
Step 4: This step is to calculate the costs associated with the moored has significant influence on hull configuration
factors grouped in Category 3. A feature of these costs is their selection. The data indicates that areas of heavy marine traffic
8 M. WANG, P. MCNEELY, C. SERRATELLA OTC 13997
would tend to suggest that a DS-SB FPSO is a prudent choice. Since year 2000, there have been at least 11 FPSOs with their
In areas where both mooring failure and side collision hull configuration confirmed. The hull configuration and
problems were prevalent, the use of the DH configuration associated information on these FPSOs are given in Table 2. A
would seem logical. It should also be noted that these areas are comparison of the information given in Tables 1 and 2
featured with harsh weather, which may be the strongest may reveal some information on the trend of hull
reason for the use of the DH configuration rather than any configuration choice.
other non-natural hazards.
It can be seen from Table 2 that DS-SB hull becomes a
New-build FPSOs/FSOs World Wide (up to early 2000) dominant hull configuration in these new-build FPSOs/FSOs.
Total SH DH DS-SB However, it should also be noted that all these vessels, except
No. Of FPSOs/FSOs 24 2 13 9 for the Terra Nova FPSO, are to be moored in benign
Percentage of total 100% 8.3% 54.2% 37.5% environmental conditions. Because of limitation to access
New-build FPSOs/FSOs North Sea and Canada latest information, this is not a complete list of the new-build
No. of FPSOs/FSOs 14 0 11 3 FPSOs/FSOs. There are several FPSOs under design, which
may change the ratio of the number of DH over DS-SB
Percentage of total 100% 0% 78.6% 21.4%
FPSOs, but doubt it will change the general trend. A safe
New-build FPSOs/FSOs in the Rest of the Areas
conclusion can be that both DH and SB-DS configurations
No. of FPSOs/FSOs 10 2 2 6
have been widely adopted in new-build FPSOs.
Percentage of total 100% 20% 20% 60%
An interesting common feature for the QHD32 FPSO and the
Table 1 Statistics of Hull Configuration of New-build Terra Nova FPSO is that both are equipped dis-connectable
FPSOs mooring system and both subject to ice environment during
winter times. This is very the conditions considered favorable
Statutory regulation is another factor whose influence is also to a DH configuration when considering Factor A above.
obvious. When looking at the heavily regulated areas of the
world (North Sea and Canada), overwhelming majorities of References
the FPSOs/FSOs are DH or at least DS-SB hulled. In areas
where local regulations tend to be less severe or non-existent, 1. IMO, Code on Intact Stability for all Types of Ships
use of the DS-SB configuration prevails. Coincidentally but Covered by IMO Instrument, IMO Resolution A. 749(18),
also logically, the areas with harsh weather are those where London, November 1993.
the local regulations are more complete and more severe. 2. IMO, MARPOL 73/78, Consolidated Edition, 1997.
3. Inter-Governmental Maritime Consultative Organization,
In general, the worldwide fleet appears more likely to utilize International Convention on Load Lines, 1966.
the DH configuration when required by regulation and in 4. IMO, Code for the Construction and Equipment of Mobile
harsh weather environments. Of course, the other factors that Offshore Drilling Units, 1989.
are described in this paper must also influence the decision of 5. Committee on Oil Pollution Act of 1990, Double-Hull
hull configuration selection. Tanker Legislation, an Assessment of the Oil Pollution
Act of 1990, National Academy Press, Washington, D.C.,
Hull Configuration of the FPSO after 2000 1998.
Project Owner or Vessel Hull 6. Shashikumar, N., “Ownership and Operation of Oil
Operator Type Location Config. Tankers in the Post-OPA 90 – An Analysis of Costs,
Sahna Chevron FPSO Angola DS-SB Profits and Complication”, A Sunny Report (found in
Girasoll Elf FPSO Angola DS-SB www.rigos.com/sunny1.html), 1996.
Amenam Elf FSO Angola DS-SB 7. National Research Council, “Effect of Double-Hull
Erha Exxon FPSO Nigeria DS-SB Requirements on Oil Spill Prevention”, National
Kizomba Exxon FPSO Angola DS-SB Academy Press, Washington, D.C., 1996, pp36-37.
Bonga Shell FPSO Nigeria DS-SB 8. Pendexter, L.A. and Diettrich, Diana, “Design
EA Shell FPSO Nigeria DS-SB Considerations for Corrosion Control of Double Hull
Belanak Conoco FPSO Indonesia DS-SB Tankers”, NACE Corrosion93, paper No. 550, 1993.
Agbami Texaco FPSO Nigeria DS-SB 9. OCIMF, “Factors Influencing Accelerated Corrosion of
Cargo Oil Tanks, September, 1997.
QHD32 Texaco FPSO China DH
10. ABS, “Microbial Generated Corrosion of Tank Plating in
Terra Petro- FPSO Canada DH
Crude Oil Carriers”, ABS Safenet Advisory Oct. 1997,
Nova Canada
http://www.abs-ns.com/news/letters/snaoct97.htm.
Table 2 Hull Configuration of the New-build FPSOs after
year 2000
OTC 13997 A RATIONAL APPROACH TO FPSO HULL CONFIGURATION SELECTION 9
Hull Form
Risk Scenarios
1 3 4 6 7 8
Explosive Cargo Tank
Collision Tank Access Corrosion Piracy/Sabotage
Mixture in Tanks Operations
2 5
Mooring Failure Cracking
2A 2B 3A 3B 3C 6A 6B 7A 7B
Grounding Infield Cargo Ballast/ Slips, Trips Cargo Ballast/ Overpressure Over Fill
Collision Tanks Voids & Falls Tanks Void Tank Tank
1A 1B 1C 1D 1E 1F
Passing Attendant/ Offloading Fishing Infield Helicopter
Vessel Supply Vessel Vessel Vessel
to be in the area (see scenario Table 3) can cause a collision of Comparative Risk Assessment Conclusions:
sufficient energy to result in a cargo spill. Also factoring into Finally, Category 3 HSE risk costs for each hull configuration
this ranking is the arrangement of the cargo in the wing tanks and are compared. The range of costs associated with each hull
the probability of vessels being in a particular area near configuration is then used by the team in comparing the relative
the FPSO. risk merits and benefits of each configuration. The comparative
information generated in this study can then be used in
Grounding probability is estimated based on several factors and conjunction with other information such as provided in the
accounts for prevailing winds at the site, proximity to land Category 1 and 2 Factor categories, to assist in the decision
masses and structures, etc. The estimates used in the risk study making process identified in the main section of this paper for a
account for prevailing winds following a storm event of logical selection of the FPSO hull configuration.
sufficient magnitude as to cause mooring failure as well as the
prevailing currents and winds and thus drift directions towards
nearby land masses and structures capable of causing bottom
damage. Likelihood of recovery is also factored into the
probability calculations.