Professional Documents
Culture Documents
JSA For Evaporation Pond
JSA For Evaporation Pond
JSA For Evaporation Pond
2 o Excavation o Falling into excavation and o Barricade the excavation area and install warning signs
traffic hazard and traffic/blinking lights on the edges of excavation to o Structure
prevent falling of vehicles, personnel and others at Engineer
night. o Site Engineer
o Permit
o Use pully and buckets to take out the spoils from the Receiver
o Spoils and mud. excavation when the excavation exceeds 4 feet.
Temporary Construction Facility TCF1
Contract No: 660004138
o Hazardous atmosphere and o Conduct gas tests each day (more frequent, if required)
materials. for the existence of Flammable, combustibles and Toxic
gases and also for the oxy deficiency before the work
shift starts.
.
PPES & Equipment o Defective PPE’s o All personal should use appropriate PPES. o Permit
5 Inspection o Untrained personal o Applicator should have cotton liners, painting glasses receiver
o Uninspected Tools and face shield dust mask Dust Mask (N95), and disposable o Site Engineer
equipment coveralls
o All the operator and applicator should be Aramco
certified
o All equipment should be third party inspected and
supervisor must be Aramco approved.
Fusion welding, fillet o Fire hazard o Fire extinguisher shall be placed to suppress the fire
6 welding for liners o Trip hazard o Supervisor should assign one competent person as o Permit
Temporary Construction Facility TCF1
Contract No: 660004138
o Geomembrane
7 Machine Handling o Proper storage area o Contractor shall have proper storage area for material o Permit
o Adequate material placement receiver
o Material shall be placed and installed as per SDS. o Site Engineer
placement
o Adverse weather o Use sand bags to avoid to the damage of membrane
during extreme weather
Temporary Construction Facility TCF1
Contract No: 660004138
8
o House Keeping o Slip and Trip Hazards o Wearing of all mandatory PPE is required to all workers
even during housekeeping.
o Remove all unwanted materials from the work area and
return all tools to site store.
o All tools unused shall be return to store for safe keeping o Permit
receiver
o Site Engineer
o HSE Officer
9
o Emergency Response o Inadequate Emergency o Inform to Azmeel Emergency contacts numbers in case o HSE
Response of emergency Manager
o Ensure that all the staff understands the action required
o Permit
during emergency situation.
o Ensure availability of the first aiders, ambulanced with receiver
driver and first aid kit as per SA requirement o Site Engineer
o HSE Officer
SAPMT Safety
Temporary Construction Facility TCF1
Contract No: 660004138