JSA For Evaporation Pond

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 7

Temporary Construction Facility TCF1

Contract No: 660004138

JSA for Evaporation Pond

S# JOB STEPS/LIST OF Potential HAZARDS HAZARDS CONTROL RESPONSIBLE


ACTIVITIES PARTY
1 Site Preparation o Unsafe work place might o Certified work permit issuer and receiver will conduct
pose danger joint site inspection, find out the hazards and build
proper precautions for it.
o Work permit procedure o Isolate the job area, install barricades and warning sings.
violation o Use proper and good condition hand tools.
o Obtain daily excavation checklist before commencing Permit Receiver
the job.
o Keep the job site clean Site Engineer
o All equipment shall be inspected and verified.

2 o Excavation o Falling into excavation and o Barricade the excavation area and install warning signs
traffic hazard and traffic/blinking lights on the edges of excavation to o Structure
prevent falling of vehicles, personnel and others at Engineer
night. o Site Engineer
o Permit
o Use pully and buckets to take out the spoils from the Receiver
o Spoils and mud. excavation when the excavation exceeds 4 feet.
Temporary Construction Facility TCF1
Contract No: 660004138

o Keep the spoils at least 2 feet away from the edges of


the excavation…

o Hazardous atmosphere and o Conduct gas tests each day (more frequent, if required)
materials. for the existence of Flammable, combustibles and Toxic
gases and also for the oxy deficiency before the work
shift starts.
.

o Access and aggress o If excavation is deeper than 4 feet, provide proper


ladder extending 1m high from the edges of the
excavation. o Permit
o If the excavation wider than 25 feet, provide Egress receiver
route on each 25 feet distance. o Site Engineer
o All the ladder components should be free of defect
o Cave-in / Excavation o Competent person shall inspect the excavation on daily
collapse. basis and after rain, heavy wind, storm and spills from
outside or inside before the job starts.
o When the excavation reaches 1.2 m or 4 feet deep,
install firm shoring system as per soil classification.
o Don’t allow heavy equipment/machinery within 10’ feet
of the edges of excavation
o The shoring system should be firm and jacks/braces
supported.
Temporary Construction Facility TCF1
Contract No: 660004138

o The shoring system/planks/plyboards shall extend at


o Underground utilities least 1’ feet high than the edges.
o Update the shoring (push it down) after each 1’ feet
increase in the dept.
o Remove the spills/water from the excavation before
starting work
o Check for underground utilities/hazards after every one
feet (1’) or (30cm) depression.
o Daily pre excavation checklist shall be maintained
o Use the tools mentioned on the pre-excavation checklist
only.
o Never use hand tools with metal handles it can cause
shock and heavy vibration.
o Read the pre-excavation checklist for more details.

o Take care for the nearby structures and if need give


proper support to avoid any damage.
o If power-operated nearby structures exist, barricade and
isolate it.
Temporary Construction Facility TCF1
Contract No: 660004138

3 Subgrade Preparation o Water used for compaction of fill material shall be


(compaction) o Cave in reasonably free of salts, oil, acid, alkalis, organic matter, o Permit
o Personal injury or other deleterious substances. receiver
o Pinch point o Compaction shall be done and the compaction test for o Site Engineer
soil integrity is to be carried.
All the compaction shall be done as per SAES-M-100.

Preparation for HDPE o No unauthorized personal should walk on the sheet it


4 Geomembrane o Unauthorized entry will be damaged use specific shoes o Permit
o Place sand bags to prevent wind and damage before receiver
o Adverse weather high winds and after installation o Site Engineer

PPES & Equipment o Defective PPE’s o All personal should use appropriate PPES. o Permit
5 Inspection o Untrained personal o Applicator should have cotton liners, painting glasses receiver
o Uninspected Tools and face shield dust mask Dust Mask (N95), and disposable o Site Engineer
equipment coveralls
o All the operator and applicator should be Aramco
certified
o All equipment should be third party inspected and
supervisor must be Aramco approved.
Fusion welding, fillet o Fire hazard o Fire extinguisher shall be placed to suppress the fire
6 welding for liners o Trip hazard o Supervisor should assign one competent person as o Permit
Temporary Construction Facility TCF1
Contract No: 660004138

o Struck by hazard attendant. receiver


o Electric shock and burns o Supervisor shall be available at work location o Site Engineer
o Noise Hazard o Only certified operator is allowed to operate the
seaming machine
o Personal shall wear proper PPE to avoid burns and
electric shock all equipment shall be checked prior to
use.
o Ear protection shall be worn or reduce damping,
vibration.

o Geomembrane
7 Machine Handling o Proper storage area o Contractor shall have proper storage area for material o Permit
o Adequate material placement receiver
o Material shall be placed and installed as per SDS. o Site Engineer
placement
o Adverse weather o Use sand bags to avoid to the damage of membrane
during extreme weather
Temporary Construction Facility TCF1
Contract No: 660004138

8
o House Keeping o Slip and Trip Hazards o Wearing of all mandatory PPE is required to all workers
even during housekeeping.
o Remove all unwanted materials from the work area and
return all tools to site store.
o All tools unused shall be return to store for safe keeping o Permit
receiver
o Site Engineer
o HSE Officer
9
o Emergency Response o Inadequate Emergency o Inform to Azmeel Emergency contacts numbers in case o HSE
Response of emergency Manager
o Ensure that all the staff understands the action required
o Permit
during emergency situation.
o Ensure availability of the first aiders, ambulanced with receiver
driver and first aid kit as per SA requirement o Site Engineer
o HSE Officer

Activity: JSA for Evaporation Pond


Approval Name Date Signatures

SAPMT Safety
Temporary Construction Facility TCF1
Contract No: 660004138

JSA Azmeel Staff Name Date Signatures

Project Manager Engineer Muhammad Fatayar

HSE Manager Muhammad Tariq

Safety Officer Hafiz Muhammad Sherdil Khan