Tugas Model Diskrit
Tugas Model Diskrit
NPM : 16.14.1.0044
QUIZ MODEL DISKRIT
Phase Machine B
A-Phase B-Phase C-Phase
Clock Time Bound Events/ Conditional Events
Activity
Ended
8 Arrival Of Job 1 -
st
7 Arrival Of Job 2 1 Operation On Job 2 (B) -> End at Time 6
3 Arrival Of Job 3 2nd Operation On Job 3 (B) -> End at Time 8
5 Arrival Of Job 4 3rd Operation On Job 4 (B) -> End at Time 12
Phase Machine C
A-Phase B-Phase C-Phase
Clock Time Bound Events/ Conditional Events
Activity
Ended
8 Arrival Of Job 1 1st Operation On Job 1 (C) -> End at Time 8
7 Arrival Of Job 2 2nd Operation On Job 2 (C) -> End at Time 11
3 Arrival Of Job 3 -
5 Arrival Of Job 4 -
Phase Machine D
A-Phase B-Phase C-Phase
Clock Time Bound Events/ Conditional Events
Activity
Ended
8 Arrival Of Job 1 1st Operation On Job 1 (D) -> End at Time 8
7 Arrival Of Job 2 2nd Operation On Job 2 (D) -> End at Time 12
3 Arrival Of Job 3 3rd Operation On Job 3 (D) -> End at Time 9
5 Arrival Of Job 4 4th Operation On Job 4 (D) -> End at Time 5
Phase Machine E
A-Phase B-Phase C-Phase
Clock Time Bound Events/ Conditional Events
Activity
Ended
8 Arrival Of Job 1 1st Operation On Job 1 (E) -> End at Time 9
7 Arrival Of Job 2 -
nd
3 Arrival Of Job 3 2 Operation On Job 3 (E) -> End at Time 9
5 Arrival Of Job 4 3rd Operation On Job 4 (E) -> End at Time 9
NAMA : KURNIA MARTIN
NPM : 16.14.1.0044
TUGAS MODEL DISKRIT
2. Menentukan Timing Chart
Timing Chart Saat t = 8
Machine Time in Hours
1234567891012345678910
A 8 J1/01 6
B -
C 8 J1/01 8
D 8 J1/01 8
E 8 J1/01 9
Saat t = 7
Waktu Operasi A = Waktu job selesai – Waktu job datang
=9–7
=2
Saat t = 3
Waktu Operasi A = Waktu job selesai – Waktu job datang
=6–3
=3
Saat t = 5
Waktu Operasi A = Waktu job selesai – Waktu job datang
= 11 – 5
=6
4. Utilitas Mesin
Utilitas Mesin = Waktu Kerja Komulatif
Total Waktu Observasi
= 128
12
= 11,5