Professional Documents
Culture Documents
NTF - Addendum To SP-1126
NTF - Addendum To SP-1126
NTF - Addendum To SP-1126
APPENDIX -5
Bahja Rima MSV/RGS Standardization
June 2019
PAGE 3 OF 17
PROJECT DESIGN BASIS
Bahja Rima MSV/RGS Standardization APPENDIX -5
PAGE 4 OF 17
PROJECT DESIGN BASIS
APPENDIX -5
Bahja Rima MSV/RGS Standardization
Contents
1. Objective ................................................................................................................................ 4
2. Background............................................................................................................................ 4
3. Way Forward ......................................................................................................................... 5
PAGE 5 OF 17
Page 3 of 6
PROJECT DESIGN BASIS
APPENDIX -5
Bahja Rima MSV/RGS Standardization
1. Objective
This Note to File is prepared to supplement the current revision (Rev.04) of SP-1126
(Drain Systems Specification) on Relief/ Drain Pits continuous purge requirement.
Objective of this note to file is to document the consideration and conditions to use the
concrete Relief and Drain Pits without continuous purging for maintenance draining
and emergency relief only.
2. Background
As per section 2.3.2 of SP-1126, for remote facilities with small inventory in not very
toxic service, a simple drain system with a pit for the final inventories with a vent to
safe location for vapor disposal and a facility for emptying the pit by vacuum truck
would be sufficient. These kind of pits are designed for atmospheric conditions and
may pose a deflagration risk. Moreover, such pits are not usually provided with
continuous purge as required by DEP 80.45.10.10-Gen. (Clause 5.7.6.4) as per the
following.
The continuous purge requirement for Relief/ Drain Pits is highlighted in many projects,
which, results in raising variances with similar justification. To prevent repetitive
variances it was agreed (By Process Function) to have an approved interim Note to
File (NTF) until the next update of SP-1126.
PAGE 6 OF 17
Page 4 of 6
PROJECT DESIGN BASIS
APPENDIX -5
Bahja Rima MSV/RGS Standardization
3. Way Forward
This NTF is approved by Process CFDH and issued to clarify design rules for Relief /
Drain Pits at remote locations with respect to the requirement of continuous purge to
mitigate deflagration risk as per the following.
Concrete Relief and Drain Pits can be used without continuous purging for
maintenance and emergency relief only, provided all the following conditions shall be
met:
1. The pits shall be kept hydrocarbon free when not in use by removing flammable
material immediately after draining/relief by vacuum truck and purged after use
with inert fluid. Project Plant Operating Manual (POM) shall include this
requirement.
2. The pits shall not be used for services where continuous presence of
hydrocarbon / Very Toxic- Acute fluids is likely or considered as Zone 0 as per
the Hazardous Area Classification.
5. The drain / vent stack to be designed for highest gas blowby / liquid rate from
upstream assuming inadvertent draining under pressure as per SP-1126
(2.3.2.2). The vent shall be large enough to ensure that the maximum pressure
in the pit is significantly less than the weight of the lid (To be confirmed during
DD stage).
6. -1190.
Page 5 of 6
PAGE 7 OF 17
PROJECT DESIGN BASIS
APPENDIX -5
Bahja Rima MSV/RGS Standardization
Facilities having a flare system shall use Drain Vessel rated to minimum 700
kPa(g) with continuous purge. Drain Pit shall not be used in facilities provided with
flare systems.
If any of the existing drain or relief vessel is designed for less than 700 kPa(g) and
connected to an open vent, continuous purge is not required provided the above
conditions are followed.
Continuous purge is required if the drain vessel is connected to a flare system as
by definition fuel gas system is available for flare system. For designs not following
the requirement of continuous purge, an ALARP demonstration is required
followed by a formal variance request.
PAGE 8 OF 17
Page 6 of 6