Professional Documents
Culture Documents
Stabilizingfluid Deep Pile
Stabilizingfluid Deep Pile
net/publication/268591629
CITATIONS READS
3 1,383
4 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Zaw Zaw Aye on 03 October 2016.
Volume One
SPONSORED BY
The Geo-Institute of the American Society of Civil Engineers
EDITED BY
Michael W. O’Neill
Frank C. Townsend
Performance of Wet-Process Bored Piles Constructed with
Polymer-Based Slurry in Bangkok Subsoil
Abstract
Introduction
Medium to large diameter bored piles with length ranging from 24 m to 60 m have been
used as foundations of the various structures in Thailand for over 3 decades. Rotary
drilling technique coupled with wet process method using bentonite slurry as support
fluid is commonly applied to construct these piles. As bentonite slurry had proven
acceptable to make qualified bored piles in the past, most of them were constructed only
by using this mineral based slurry. Recently, polymer-based slurry has been
increasingly used in Bangkok as an alternative supporting fluid in bored pile drilling. In
the initial stage, the primary reason for using this alternative slurry was to minimize the
problems associated with using classic bentonite such as site pollution and the disposal
of excavated soils which are usually contaminated. Construction records and static pile
load test conducted on bored piles constructed with polymer-based slurry proved that
there is no adverse effect on stability of borehole during drilling as well as capacity of
the pile from using this alternative supporting fluid in Bangkok subsoil. Dry anionic
partially hydrolyzed polyacrylamide (PHPA) polymer powder premixed with fresh
water and a small percentage of bentonite was used in the construction of bored piles
presented in this paper.
143
DEEP FOUNDATIONS 2002
144
Medium to
Depth (m)
20 Stiff Clay Su= 50-14020- KPa
γ t = 17-21kN/m 3
Act
ual
Medium -
30 SPT-N= 20-40
Pie
Dense Sand 30
Hyd
(First Sand)
γ t = 20kN/m 3
zom
ros
etri
tatic
-
40 Hard Clay Su> 200 KPa
cD
40
γ t = 21KN/m 3
Line
raw
dow
50 Dense to Very -
nL
50
Dense Sand SPT-N= 50-100
ine
(Second Sand) γ t = 21KN/m 3
-
60 60
Figure 1. Typical soil profile of Bangkok plain with piezometric drawdown conditions.
In Bangkok, medium to large diameter (0.6 m to 1.8 m diameter) bored piles with depth
ranging from 24 m to over 60 m are constructed by wet process due to the prevailing
subsoil condition and limited application of dry process. Wet process method as its
DEEP FOUNDATIONS 2002
145
name implies makes the pile under wet condition by using drilling slurry. Temporary
casing of 14-15 m in length is also used as a support in soft clay layer. Drilling is
commonly commenced by dry process with auger applying rotary drilling action in the
soft clay layer and stiff clay layer. Before reaching to the first sand layer slurry is fed to
the borehole and drilling is continued with the bucket to the final depth. A cleaning
bucket is commonly used to clean the bottom of the borehole prior to reinforcement
cage installation. Tremie concreting is necessary for the piles installed under wet
process.
The primary function of drilling slurry is to prevent the borehole instability as deep-
seated bored piles are required to install through water bearing and caving soils.
Bentonite slurry was mainly used in the past as it adequately fulfilled the requirement.
Polymer-based slurry has become increasingly popular as an alternative supporting fluid
in recent years. The main reason for switching to use polymer-based slurry is to
minimize the problems associated with environmental issues caused by the use of
bentonite slurry.
In the initial stage of using polymer-based slurry, the major concerns were the
potential negative impact on stability of the borehole and the shaft friction capacity as
this alternative slurry was not yet accustomed to the bored piling industry in Bangkok.
Trial boreholes conducted in the initial stage of introducing polymer-based slurry
revealed that borehole is well stablized if the right dosage is used. Dry anionic partially
hydrolyzed polyacrylamide (PHPA) polymer powder premixed with fresh water and a
small percentage of bentonite is mainly used for long bored piles in Bangkok. First, a
small dosage of bentonite powder is premixed with fresh water prior to polymer powder
introduction. The predetermined dosage of dry polymer is then added and mixed with
the betonite slurry. Premixed polymer-based slurry is stored in the steel tanks before
supplying to the bored pile drilling. The reason for adding bentonite for long bored piles
is to minimize the fluid loss which was observed from the trial boreholes drilled only
with pure polymer slurry. Depending on the thickness of sand layers present at site and
the length of pile, addition of bentonite may not be necessary. Close monitoring was
made by sonic caliper measurement (KODEN drilling monitoring equipment) to check
the stability of the borehole. The results of the sonic caliper measurement proved that
borehole can be well stabilized with the use of polymer-based slurry at total
construction time prior to concreting even over 24 hours. According to the cross-hole
sonic logging or sonic coring tests conducted on bored piles, there is no evidence that
degraded concrete remains along the pile shaft due to the use of polymer-base slurry.
Load tests were carried out to confirm the capacity of bored piles constructed
with the alternative drilling slurry. As most of the test piles constructed with polymer-
based slurry gave smaller settlement values, particularly at maximum test load than
those obtained from piles constructed with bentonite slurry, confidence in using
polymer-based slurry was raised among the designers and the contractors.
Shaft capacity degradation of wet-process bored piles may be attributed to three main
factors : reduction of effective stress at borehole interface, properties of slurry and
DEEP FOUNDATIONS 2002
146
Following empirical formula are normally adopted to estimate the ultimate skin friction
capacity of bored piles.
Total stress approach is used to calculate the shaft friction capacity of clay
layers.
fs = α.Cu
where, α = adhesion factor
Cu = undrained shear strength
Static pile load test on eleven test piles constructed by wet process with
polymer-based slurry are presented in this paper. Out of these, three piles were
instrumented with vibrating wire strain gauges and mechanical extensometers at
interface of different soil layers. All test piles except TP-8 were tested to minimum 2.5
times of pre-defined design load, which is commonly estimated in the preliminary
design stage.
Slurry Properties and Construction Records of Test Piles. Table 1 shows the
properties of polymer-based slurry and construction records of test piles. It is to be
noted that all these test piles were constructed by the same contractor. Hence it is
assumed that influence of other variables such as equipment as well as construction
procedure used in drilling, slurry mixing and quality control measures applied for all
piles would be minimized in evaluation of the load test results.
Prediction vs Performance of Test Piles. As none of the test piles except TP-5 was
tested to failure load, no attempt is made to determine the capacity of the piles from the
failure load criteria for further assessment. Instead the performance of test piles is
evaluated from load-settlement characteristics as described below.
As large quantities of tested-to-failure instrumented load test results of bored
piles constructed with bentonite slurry in Bangkok are available, load-settlement
behavior of this pile type can be accurately predicted using back-analyzed data. Load-
settlement behavior of all test piles constructed with polymer-based slurry presented in
this paper were predicted by taking the parameters obtained from back-analyzed data of
bentonite bored piles.
Predicted load-settlement curves are compared with those of actual test results as
shown in Figure 2 to 12. It is to be noted that the term “gross settlement” indicated in
the graphs represents the total pile head movement at applied load. The objective of
these comparisons is to assess from the actual load test results, whether or not use of
polymer-based slurry in bored pile construction affects the capacity of bored piles.
The summary of predicted and measured load-settlement data is presented in
Table 2. At the design load, measured pile head movement of most of the piles are
within 5 mm as can be seen in the table. It is also evident that movement measured from
the field load test is smaller than that of prediction for most of the test piles, and is more
clear at the applied load ranging from 1.5 to 3 times of pre-defined design load. This
finding pointed out that better capacity of bored pile constructed in Bangkok can be
achieved with use of polymer-based slurry. The pattern of the load-settlement curves
obtained from the filed tests suggested that majority of the applied load is resisted by
the shaft friction. Therefore, it is reasonable to conclude that overall shaft frictional
resistance of bored pile is improved with the use of polymer-based slurry.
SPT-N (Blows/ft)
1 0 50 100
0 0
Soft to
Applied Load (kN)
Medium
10 Clay 10 0 2000 4000 6000 8000 10000 12000
0
Gross Settlement (mm)
Stiff to Very
20 Stiff Clay 20 -5
-10
Depth (m.)
Medium to
30 Very Dense 30 -15
Sand Measurement
Hard clay
-20
40 40 Prediction
Medium to -25
Very Dense
50
-30
50 Sand
Very Dense
Sand
60 60
SPT-N (Blows/ft)
1 Applied Load (kN)
0 50 100
0 0 0 2000 4000 6000 8000 10000 12000
Soft Clay
0
10 10
Loose Sand
-10
20 20
Stiff Clay -20
30 30 -30
Dense to Very
Dense Sand
-40
40 Hard Clay 40 Measurement
-50 Prediction
Dense to
Very 50
50
Dense Sand -60
60
60
Stiff Clay
20
-10
Depth (m.)
Hard Clay 20
60
60
Figure 4. Load Settlement curves of TP-3 (Dia. 1.20 x 51 m) : Prediction vs. Measurement.
STP-N (Blows/ft)
Stiff Clay
20
Dense
-15
30 Sand
Depth (m.)
Measurement
40 Prediction
Hard Clay
-25
50 Very
Dense
Sand
60 -35
Hard Clay
70
STP-N (Blows/ft)
0 50 100 Applied Load (kN)
0 0 0 5000 10000 15000 20000 25000 30000 35000
Very Soft to 0
10 Soft clay
20
Stiff to Very -50
20
Stiff Clay
-75
Depth(m.)
30
Measurement
30
-100 Prediction
V. Dense Sand
Hard Clay -125
40 40
Medium
Dense to -150
Very Dense
50 50
Sand
Hard clay
60 60
SPT-N (Blow/ft)
Stiff Clay
-5
20
-10
Dense Sand
Depth (m.)
30 -15
V. Stiff Clay
-20
40 Measurement
Dense Sand -25 Prediction
50 -30
-35
Very Dense
60 Sand
70
SPT-N (Blows/ft)
Soft to -5
10 Med. Clay
-10
Stiff Clay
Depth ( m.)
15
-15
Measurement
20 Hard Clay -20 Prediction
-25
25
Very -30
Dense Sand
30 -35
35
STP-N (Blows/ft)
-40
Stiff Clay
30
Measurement
-60
Dense to
Prediction
40 Very -80
Dense Sand
50 -100
60
STP-N (Blows/ft)
0 50 100 Applied Load (kN)
0 0
0 1000 2000 3000 4000 5000 6000 7000
Soft to 5
Medium Clay 0
Gross Settlement (mm)
10 10
15 -5
Stiff to Very
20
Depth (m.)
Stiff Clay 20
25 -10
Medium to Measurement
30 30
Dense Sand Prediction
-15
35
40 Hard Clay
40
Dense to -20
V. Dense Sand 45
50
50
Figure 10. Load-Settlement Curves of TP-9 (Dia. 0.80x43 m) : Prediction vs. Measurement
SPT-N (Blows/ft)
0 50 100
Applied Load (kN)
0
0 500 1000 1500 2000 2500 3000
5
Very Soft 0
Gross Settlement (mm)
to Soft Clay
-2
10
-4
Stiff to Very
Depth (m.)
15 -6
Stiff Clay
Measurement
20 -8 Prediction
35
Figure 11. Load-Settlement curves of TP-10 (Dia. 0.60x26 m) : Prediction vs. Measurement
152 DEEP FOUNDATIONS 2002
SPT-N (Blow/ft)
0 50 100
0
Applied Load (kN)
5
Soft Clay 0 500 1000 1500 2000 2500
0
15 -5
Stiff Clay
20 -10 Measurement
25
Prediction
-15
Dense Sand
30
-20
35 Hard Clay
40
Figure 12. Load-Settlement curves of TP-11 (Dia. 0.60x24 m) : Prediction vs. Measurement
TP-1 0.80 x 49 3300 9900 5.50 12.70 17.50 3.90 9.80 14.95
TP-2 0.80 x 50 3300 9900 6.50 16.52 24.20 5.20 14.74 21.05
TP-3 1.20 x 51 7200 18000 6.62 17.50 29.80 4.61 14.19 19.76
TP-4 1.80 x 62 11000 33000 5.62 14.07 20.55 4.00 9.88 12.96
TP-5 1.50 x 54 12000 32000 9.31 26.29 127.10 8.60 12.79 23.03
TP-6 1.00 x 51 4500 11250 5.50 13.91 19.80 2.49 7.10 9.15
TP-7 1.00 x 30 2600 6500 3.50 10.65 20.80 1.67 3.96 5.38
TP-8 0.80 x 41 3300 9900 5.72 15.90 30.20 2.75 8.05 11.60
TP-9 0.80 x 43 3300 6600 6.20 15.10 - 4.52 11.20 -
TP-10 0.60 x 26 1000 2500 2.56 6.35 9.50 1.61 3.76 4.55
TP-11 0.60 x 24 800 2000 2.59 7.84 14.30 1.09 3.19 4.22
Instrumented Pile Load Test. Shaft frictional resistance of polymer-based bored piles
in sand layers were of major interest to the authors as it is considered that drilling slurry
has less influence on clay layers according to the previous studies on bentonite bored
piles.
Three instrumented pile load tests were available at the time of this paper
preparation. Vibrating wire strain gauges (VWSG) and mechanical extensometers (ME)
were installed at the major soil boundaries for all 3 piles. It is to be noted that the lowest
level of strain gauges and extensometer of test piles TP-1, TP-2 and TP-3 are located at
1.5, 1.0 and 1.0 m above the relevant pile tip level respectively.
DEEP FOUNDATIONS 2002 153
Load distribution curves along the test pile shaft at various applied load are
shown in Figure 13 to 15. The values of unit skin friction developed by the maximum
test load at the different soil layers along the shaft of test piles in comparison with those
of ultimate unit skin friction calculated using the formula shown in the earlier section
are also illustrated in these figures.
Stiff to
20
Very Stiff
20 20.0 20
Clay
Depth (m.)
Medium Dense
30 to V.Dense 30 30.0 30
Sand
Figure 13. Load distribution curves and unit skin friction of TP-1 (Dia. 0.80x49 m).
10 10 10 10
Loose Sand
Depth (m.)
20 Stiff to Very 20 20 20
Stiff Clay
30 Dense to Very 30 30 30
Dense Sand
Hard Clay
40 40 40 40
Dense to Very
Dense Sand
50 50 50 50
Mobilized at 9900 kN
Qult (calculated)
60 60 60 60
Figure 14. Load distribution curves and unit skin friction of TP-2 (Dia. 0.80x50 m).
DEEP FOUNDATIONS 2002
154
10 10
10 10
Stiff Clay
20 20
Depth (m.)
V. Stiff to 20 20
Hard clay
Dense Sand
30 30 30
30
Hard Clay
40 Dense to 40 40
40
Very Dense
Sand
50 50 50 50
Mobilized at 18000 kN
Qult (calculated)
60 60 60 60
Figure 15. Load distribution curves and unit skin friction of TP-3 (Dia. 1.20x51 m).
shaft diameter, the shaft frictions of upper soil layers (soft clay and stiff to very stiff
clay) were fully mobilized and it is likely that medium dense sand (first sand) layer
almost reached to ultimate shaft friction resistance. However, it is most likely that very
dense sand (second sand) was not fully developed to the ultimate stage. The same
behavior is observed for test piles TP-2 and TP-3.
Shaft friction factors β of the first and second sand layer of TP-1, TP-2 and TP-3
are back calculated from the load transfer values of relevant layers obtained from the
VWSG data. However, the back-calculated β factors (named as pseudo-β for purpose of
convenient reference in this paper) particularly for the second sand layer are the values
at applied maximum test loads and not at ultimate test loads. In other words, it is likely
that the back-calculated β factors for the second sand layer are the values at partially
mobilized shaft friction of this layer. The back-calculation of β value is mainly aimed to
get an idea on the magnitude of β factors for polymer-based bored piles from the
currently available data in comparison with the design values commonly used for
bentonite bored piles constructed in Bangkok.
Figure 17 shows the values of pseudo-β of polymer-based slurry piles obtained
from 3 instrumented pile load tests plotted on the graph of β values derived from the
full-scale static pile load tests of bentonite bored piles in Bangkok subsoil from the
previous research works (Submaneewong, 1999). Submaneewong (1999) recommended
the design line of β factors for bentonite bored piles in the first and second sand as
indicated in Figure 17. It is evident that pseudo-β for the first sand layer of all 3 test
piles constructed under polymer-based slurry are significantly higher than those of
design values. The pseudo-β values of the second sand layer are also slightly higher
than those of design line. It is most likely that β values of second sand layers would be
higher than pseudo-β values indicated in Figure 17 if the piles were tested to higher
loads or to failure, since shaft friction at this layer might not have been fully mobilized
at applied maximum test load as described in above paragraphs. These findings
suggested that polymer-based slurry bored piles produced better shaft friction resistance
in sand layers than that of bentonite bored piles. Further research is needed to determine
the β values of the first and second sand layers at fully mobilized shaft friction
resistance.
200
Soft clay
Stiff to very stiff clay
Medium dense sand
Stiff to very stiff clay Very dense sand
150
Unit Skin Friction (kN/m 2)
0
0 4 8 12 16 20 24
Figure 16. Unit skin friction versus pile head movement of different soil layers (TP-1).
156 DEEP FOUNDATIONS 2002
1 .0
Submaneewong (1999) : Bored Piles (Tip in 2nd Sand)
Submaneewong (1999) : Bored Piles (Tip in 2nd Hard Clay)
Chiewcharnsilp (1988)
0 .8
Polymer Bored Pile TP-1 (1st Sand)
Polymer Bored Pile TP-2 (1st Sand)
Polymer Bored Pile TP-3 (1st Sand)
0 .6 Polymer Bored Pile TP-1 (2nd Sand)
β (Ks tan δ)
0 .2
0 .0
28 .0 30 .0 32 .0 34 .0 36 .0 38 .0
Conclusions
Acknowledgement
The authors wish to express their appreciation to the project directors and engineers of
SEAFCO Co., Ltd. for providing the bored pile construction records. Thanks are also
DEEP FOUNDATIONS 2002 157
extended to EDE Co., Ltd. for providing the load test data. The authors also wish to
thank Miss. Siriphen Chaiyapak (former office engineer, SEAFCO Co., Ltd.) and Mr.
Artorn Kantawateera (trainee student, Khonkaen University) for their assistance in
preparing this paper.
References
Harayama H. (1990). “Load settlement analysis for bored piles using hyperbolic transfer
functions,” Soil and Foundations, Vol. 30, No. 1, Japanese Society of Soil Mechanics
and Foundation Engineering, 55-64.
Nutalaya, P. (1981). “Subsidence Studies of the Bangkok Plain,” AIT Research Report,
Asian Institute of Technology, Bangkok, Thailand.
Reese L. C., (1978). “Design and Construction of Drilled Shafts,” Twelfth Terzaghi
Lecture, Proc. ASCE, Vol. 104, No. GT1, 1978, 95-116.
Thasnanipan N., Ganeshan B. and Anwar M.A. (1998). “Effect of construction time
and bentonite viscosity on shaft capacity of bored piles,” Third International
Geotechnical Seminar on Deep Foundation on Bored and Auger Piles, Ghent, Belgium,
19-21 October 1998, Balkema, Rotterdam, 171-177.
Thasnanipan N., Tanseng P. and Anwar M. A. (1998). “Large diameter bored piles in
multi-layered soils of Bangkok,” Third International Geotechnical Seminar on Deep
Foundation on Bored and Auger Piles, Ghent, Belgium, 19-21 October 1998, Balkema,
Rotterdam, 511-518.