Project RCC RU-VI Balongan: Milestone Preparation For TA

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

WBS

LEVEL WBS CODE WBS DESCRIPTION

1. U2004 Project RCC RU-VI Balongan


2. U2004.1 Milestone
2. U2004.2 Preparation for TA
3. U2004.2.1 PROJECT MANAGEMENT
3. U2004.2.2 ENGINEERING WORK
4U2004.2.2.1 Process Engineering
5. PFD Mark up
5. P & ID Mark up
4U2004.2.2.2 Piping Engineering
5. Develop 3D Piping Isometric
5. Extract Isometric Drawing
5. Extract Material Take Off
5. Material Requisition for Piping
4U2004.2.2.3 Mechanical Engineering
5. Material Requisition for
5. Material Requisition for
5. Material Requisition for
5. Material Requisition for
5. Material Requisition for
4U2004.2.2.4 Electrical Engineering
5. Survey For Electrical Work
5. Mapping Cable Rack / Cable Tray Replacement
5. Material Take Off for Cable Rack / Cable Tray
5. Material Take Off for Receptacle, JB etc
5. Material Take Off for Lighting
4U2004.2.2.5 Instrumentation Engineering
5. Survey for Instrument Work
5. Hook Up Darwing for Control Valve replacement
5. Material Requisition For Control Valve
5. Material Take Off for Hook Up
5. Material requisition for Hook Up material
4U2004.2.2.6 Civil Engineering
5. Survey for Heavy Lift Haul Route
5. Survey for Heavy Lift Crane Foundation
5. Specification for Road and Pavement
5. Design & Calculation of Heavy Lift Haul Road
5. Design & Calculation of Heavy Lift Foundation
5. Specifiation for Steel Structure
5. Specification for Concrete Work
5. Design & Calculation of Steel Structure
5. Requisition for Heavy Lift Road
5. Requisition for Heavy Lift Crane Foundation
5. Requisition for Steel Structure
3. U2004.2.3 PROCUREMENT
WBS
LEVEL WBS CODE WBS DESCRIPTION
4U2004.2.3.1 Tag Item
5. Slide Valve (repair)
5. Expansion Below Joint (repair)
5. Slide Valve (New)
5. Expansion Below Joint (New)
5.
5.
5.
5.
4U2004.2.3.2 Bulk Item
5. Civil (Piling) Material)
5. Piping Material
5. Electrical Material
5. Instrument Material
4U2004.2.3.3 Subcontracting
5. Civil Work
5. Mechanical Work
5. Piping Work
5. Electrical Work
5. Instrument Work
3. U2004.2.4 CONSTRUCTION
4U2004.2.4.1 Temporary Facility

4U2004.2.4.2 Civil

4U2004.2.4.3 Steel Structure

3. U2004.2.5 INSTALLATION
4U2004.2.5.1 Mechanical

4U2004.2.5.2 Piping

4U2004.2.5.3 Electrical

2. U2004.3 T.A (Turn Around)


3. U2004.3.1 Mechanical
4U2004.3.1.1 Reactor
WBS
LEVEL WBS CODE WBS DESCRIPTION

4U2004.3.1.2

4U2004.3.1.3

4.

4.

4.

3. U2004.2.2. Piping
4U2004.2.2.1

4U2004.2.2.2

3. U2004.2.3 Civil / Steel Structure


4U.2004.2.3.1

4U2004.2.3.2

3. U2004.2.4 Electrical
4U.2004.2.4.1

4U2004.2.4.2

3. U2004.2.5 Instrument
4U.2004.2.5.1

4U2004.2.5.2
Project Revitalisasi RCC RU-VI Balongan 100%

Site Preparation
Turn Around