SOAL LATIHAN

Project ID: CSP


Project Name: Conveyor System Project
Planned Start: 07-Mar-20
Calendar: 7 days - 9h
Unit of time Days
Duration Format Days

BUDGETED
Activity ID Activity Name RESOURCES Successor
UNIT
ENGINEERING DEPARTEMENT
DESIGN
E020 System Design 45 ATM ENG 80 E030
E040 Prepare Drawing For Conveyors 20 DESIGN ENGINEER 60 E050
REVIEW
E030 Review and Approve Design 15 PROGRAM MANAGER 30 E040
E050 Review and Approve Drawing For Conveyors 5 PROGRAM MANAGER 15 P070
PURCHASING DEPARTEMENT
PREPARATION
P070 Prepare and Solicit Bids for Conveyor 10 ATM ENG 30 P080
P080 Review Bids For Conveyors 2 PROGRAM MANAGER 4 P090
P090 Award Contract 1 ACCOUNTTING 2 P100
FABRICATION
P100 Fabricate and Deliver Conveyor 25 VENDOR 0 IS120, IS130, IS140, IS150
INFORMATION SYSTEM DEPARTEMENT
PREPARATION
IS130 Site Preparetion 15 FIELD ENG3 45 IS150
IS140 Operation Manual 35 PROGRAM MANAGER 180 IS230
INSTALLATION
IS120 Start Conveyor Installation 0
IS150 Install Conveyor 211 10 FIELD ENG 1 28 IS160, IS170, IS180, IS210
IS160 Install Conveyor 212 45 FIELD ENG 1 100 IS190
IS170 Field Piping 50 FIELD ENG2 100 IS220
IS180 Field Wiring 50 FIELD ENG2 150 IS220
IS190 Install Conveyor 213 10 FIELD ENG 1 30 IS200
IS200 Install Conveyor 214 20 FIELD ENG 1 90 IS220
IS210 Field Painting 20 FIELD ENG2 60 IS220
IS220 Star-up and Debug System 20 ATM ENG 40 IS230
IS230 Conveyor System Complete 0

RESOURCES DATA:
Resource ID Resource Name Resource Type Price / Unit
ATM ENG ATM ENG Labor Rp. 200
DES ENG DESIGN ENGINEER Labor Rp. 200
ACCS ACCOUNTTING Labor Rp. 200
VENDOR VENDOR Nonlabor 0
PRG MGR PROGRAM MANAGER Labor Rp. 250
FIELD ENG1 FIELD ENG 1 Labor Rp. 200
FIELD ENG2 FIELD ENG2 Labor Rp. 200
FIELD ENG3 FIELD ENG3 Labor Rp. 200

WBS
WBS CODE WBS NAME
1 ENGINEERING DEPARTEMENT
1.1 DESIGN
1.2 REVIEW
2 PURCHASING DEPARTEMENT
2.1 PREPARATION
2.2 FABRICATION
3 INFORMATION SYSTEM DEPARTEMENT
3.1 PREPARATION
3.2 INSTALLATION