Greenhat Company applies factory overhead based on machine hours. The company had the
following budget for its operation in 2009, which was at 80 percent level of theoretical capacity:
Standard machine hours (MH) ........ 20,000
Variable factory overhead .......... $72,000
Total factory overhead rate per MH ....... $12.60
Greenhat budgeted its operation for 2010 at 90 percent of theoretical capacity. The standard
calls for 2 machine hours per unit manufactured. During 2010 Greenhat used 23,000 machine-
hours to manufacture 11,300 units. The company incurred $12,000 more factory overhead cost
than the flexible-budget amount for the units manufactured, of which $5,000 was due to fixed
factory overhead.

Required
1. What is the budgeted fixed factory overhead at an 80 percent level of operation? At a 100
percent level of operation?
2. What was the standard variable factory overhead rate and the standard fixed factory
overhead rate in 2010? (Assume no change in the variable overhead rate.)
3. What is the total factory overhead flexible-budget amount for 2010? (Assume no cost change
from 2009.)
4. Compute the following four overhead variances for the Greenhat Company:
a. Variable overhead spending variance.
b. Variable overhead efficiency variance.
c. Fixed overhead spending variance.
d. Production-volume variance.
5. Compute the following two overhead variances for the Greenhat Company:
a. Total flexible-budget variance.
b. Production-volume variance.

ANSWER
https://solvedquest.com/greenhat-company-applies-factory-overhead-based-on-machine-hours/

Reach out to freelance2040@yahoo.com for enquiry.


Powered by TCPDF (www.tcpdf.org)

You might also like