CASE STUDY:

The activities of a project and the other related information are given in table below:

Activity Optimistic Time Normal Time Pessimistic Time


1--2 30 44 54
1--3 8 12 16
2--3 1 2 3
2--4 2 3 5
3--4 8 10 12
4--5 14 22 25

1. Contract a PERT diagram


2. Determine the probability of a project in less than 60 days.