L2 SCHEDULE FOR SUSHMA ENCLAVE -MACHILIPATNAM

Planned Actual
SI. No Description Days Start Finish Remark
1 Drawings 1 12-Feb-18 05-May-18
Dismantling 6 13-Feb-18 19-Feb-18 completed
2 Below Ground level
Earth work Cellar with dewatering 7 23-Apr-18 30-Apr-18 completed
Marking 1 01-May-18 01-May-18 completed
Footings Excavation 4 02-May-18 06-May-18 completed
3 PCC Laying for footings completed
Dressing 2 07-May-18 09-May-18 completed
PCC Laying for footings 3 10-May-18 13-May-18 completed
Reinforcement Cutting bending 15 14-May-18 29-May-18 completed
Marking for columns 2 15-May-18 17-May-18 completed
Column Placing and raft Casting 25 18-May-18 12-Jun-18 completed
Lift pit 7 19-May-18 26-May-18 completed
Pedestals 26 20-May-18 15-Jun-18 completed
Deshuttering 27 22-May-18 18-Jun-18 completed
RR Masonary work 15 25-May-18 09-Jun-18 completed
Back filling and compaction 7 10-Jun-18 17-Jun-18 completed
4 Plingth beams
PCC Laying for Plingth beams 2 18-Jun-18 20-Jun-18 completed
Reinforcement Cutting bending and
3 21-Jun-18 24-Jun-18
placing completed
RCC Laying 2 25-Jun-18 27-Jun-18 completed
Deshuttering 2 28-Jun-18 30-Jun-18 completed
Back filling 3 01-Jul-18 04-Jul-18 completed
Compaction 2 01-Jul-18 03-Jul-18 completed
PCC Laying 2 04-Jul-18 06-Jul-18 completed
5 Above Ground level -Ist slab
Starter marking 2 07-Jul-18 09-Jul-18 completed
Column reinforcement 2 10-Jul-18 12-Jul-18 completed
Column RCC casting 3 10-Jul-18 13-Jul-18 completed
Shuttering 15 14-Jul-18 29-Jul-18 completed
Rod binding 12 18-Jul-18 30-Jul-18 completed
Slab casting 1 30-Jul-18 31-Jul-18 completed
Brick work 15 15-Aug-18 30-Aug-18 completed
Plastering -Internal 15 20-Aug-18 04-Sep-18 completed
6 Above Ground level -II nd slab
Starter marking 2 01-Aug-18 03-Aug-18 completed
Column reinforcement 2 04-Aug-18 06-Aug-18 completed
Column RCC casting 3 04-Aug-18 07-Aug-18 completed
Shuttering 10 08-Aug-18 18-Aug-18 completed
Rod binding 10 12-Aug-18 22-Aug-18 completed
Slab casting 1 22-Aug-18 23-Aug-18 completed
Brick work 15 07-Sep-18 22-Sep-18 completed
Plastering -Internal 15 12-Sep-18 27-Sep-18
7 Above Ground level III rd slab
Starter marking 2 24-Aug-18 26-Aug-18 completed
Column reinforcement 2 27-Aug-18 29-Aug-18 completed
Column RCC casting 3 27-Aug-18 30-Aug-18 completed
SI. No Description Days Start Finish Remark
Rod binding 9 04-Sep-18 13-Sep-18 completed
Slab casting 1 13-Sep-18 14-Sep-18 10-Dec-18 completed
Brick work 15 29-Sep-18 14-Oct-18 25-Dec-18
Plastering -Internal 15 04-Oct-18 19-Oct-18 09-Jan-19
8 Above Ground level IV th slab
Starter marking 2 15-Sep-18 17-Sep-18 12-Dec-18 completed
Column reinforcement 2 18-Sep-18 20-Sep-18 14-Dec-18
Column RCC casting 3 18-Sep-18 21-Sep-18 17-Dec-18
Shuttering 9 22-Sep-18 01-Oct-18 26-Dec-18
Rod binding 9 26-Sep-18 05-Oct-18 04-Jan-19
Slab casting 1 05-Oct-18 06-Oct-18 05-Jan-19
Brick work 15 21-Oct-18 05-Nov-18 20-Jan-19
Plastering -Internal 15 26-Oct-18 10-Nov-18 04-Feb-19
9 Above Ground level V th slab
Starter marking 2 07-Oct-18 09-Oct-18 07-Jan-19
Column reinforcement 2 10-Oct-18 12-Oct-18 09-Jan-19
Column RCC casting 3 10-Oct-18 13-Oct-18 12-Jan-19
Shuttering 9 14-Oct-18 23-Oct-18 21-Jan-19
Rod binding 9 18-Oct-18 27-Oct-18 30-Jan-19
Slab casting 1 27-Oct-18 28-Oct-18 31-Jan-19
Brick work 15 12-Nov-18 27-Nov-18 15-Feb-19
Plastering -Internal 15 17-Nov-18 02-Dec-18 02-Mar-19
10 Above Ground level -Terrace
Starter marking 2 29-Oct-18 31-Oct-18 02-Feb-19
Column reinforcement 2 01-Nov-18 03-Nov-18 04-Feb-19
Column RCC casting 3 01-Nov-18 04-Nov-18 07-Feb-19
Shuttering 9 05-Nov-18 14-Nov-18 16-Feb-19
Rod binding 9 09-Nov-18 18-Nov-18 25-Feb-19
Slab casting 1 18-Nov-18 19-Nov-18 26-Feb-19
Rod binding 9 22-Nov-18 01-Dec-18 07-Mar-19
Slab casting 1 01-Dec-18 02-Dec-18 08-Mar-19
Brick work 15 17-Dec-18 01-Jan-19 23-Mar-19
Plastering -Internal 15 22-Dec-18 06-Jan-19 07-Apr-19
11 Out side Plastering
West side -Elevation 20 06-Jan-19 26-Jan-19 27-Apr-19
East side 15 27-Jan-19 11-Feb-19 12-May-19
North side 10 12-Feb-19 22-Feb-19 07-May-19
South side 10 23-Feb-19 05-Mar-19 22-May-19
12 Handing over to Interior 19-Sep-18