Professional Documents
Culture Documents
RM 103, Building 226 - 2320 Surge Area Drive (Off of SW Archer RD)
RM 103, Building 226 - 2320 Surge Area Drive (Off of SW Archer RD)
CEG6117
Advanced Deep Foundations
Design
Dr. McVay (email: mcm@ce.ufl.edu)
Lectures: https://lss.at.ufl.edu/
Syllabus:
Deep Foundations
Structural members made of steel, concrete,
and/or timber. They are expensive due to cost
of materials, and placement (driving, drilling,
etc.) vs. shallow foundations.
Pile Cap
P
Lateral Resistance
P
20<L<150’
Lateral Disp - y
Side Friction τ
Tip Resistance
Vertical Displ.
Layouts
Plumb or Vertical Battered
Water
Land
3D 3D
Standard Design
• Site Investigation
– Borings (Site Stratigraphy, Soil & Rock Properties along
with Variability), GeoStat
• Preliminary Design
– Multiple Foundation types (different pile types and
sizes, drilled shafts, etc.), FB-Deep, GeoStat, GRLWEAP,
FB-MultiPier
• Final Design – Consider all Service and Strengths
States, Future Influences(GeoStat & FB-MultiPier,
etc.)
NHI 2.2
Types of Piles
• There are four general types (based on material) of
piles available: 1) concrete; 2) steel; 3) wood; and 4)
composite (e.g. concrete filled steel pipe)
Rigs:
•Truck
•Crawler
•Crane
Methods of Construction
•Cased
•Dry Hole
•Wet (mineral or polyme
slurry)
6-17
TERMINOLOGY
6-6
LIGHT TRUCK-MOUNTED
H & T 635
48” Dia.; 35 ft.
6-12
Tools
Double-Flight
Soil Auger
6-35
Dry Method
WHEN USED
• Inplace Soil/rock will
keep the hole walls
from collapsing.
• Construction of the
shaft can be in relatively
dry conditions.
3-7
WET –VS- DRY?
4-9
1. Prestressed Concrete Piling, (furnished and installed)
**Size of Piling Cost per Lin. Foot Quantity Cost
$80
FDOT
18" (Driven Plumb or 1" Batter )
18" (Driven Battered) $90
24" (Driven Plumb or 1" Batter ) $105
24" (Driven Battered) $120
Bridge
30" (Driven Plumb or 1" Batter ) $150
30" (Driven Battered) $160
Embedded Data Collector (each) $1,300
Subtotal
Development
* When heavy mild steel reinforcing is used in the pile head add $250 to
the piling cost.
** When microsilica is used add $6/LF to the piling cost
Preliminary Cost
14" x 89 H Section $75
20" Pipe Pile $90
24" Pipe Pile $96
30" Pipe Pile $160
Structures Design
Dia. (on land, casing salvaged) Cost per Lin. Foot Quantity Cost
3 ft $290
4 ft $430
5 ft $510
Manual
6 ft $630
7 ft $750
Dia. (in water, casing salvaged) Cost per Lin. Foot Quantity Cost
3 ft $320
4 ft $500
5 ft $600
6 ft $690
7 ft $800
8 ft $1,100
Dia. (in water, permanent casing) Cost per Lin. Foot Quantity Cost
3 ft $460
4 ft $625
5 ft $750
6 ft $950
7 ft $1,100
8 ft $1,500
9 ft $1,800
NHI 6.14