Professional Documents
Culture Documents
2011 04 Examiner Report
2011 04 Examiner Report
2011 04 Examiner Report
Questions
1. Theatre
2. Exhibition centre
3. Farm access bridge
4. Hotel building
5. Town centre car park
6. Lifeboat station building
7. New link bridge between two offshore platforms
8. Office retrofit
Overview
The question was designed to challenge Calculations were mixed: candidates often
candidates' knowledge of structural framing struggle in this area and many need to develop
systems and for them to assess the most a better feel for simple analysis to check their
appropriate manner of spanning the theatre results. This is a skill that is vital for assessing
space without compromising the spatial the validity of software models and so must be
aspects of the basement. Many candidates a key part of the designer's armoury.
chose to span the short direction but often
without considering the design requirements Drawings were variable. Many candidates
fully. Transfer structures were either massive attempted split-level plans which is convenient
and eroded the headroom of the structure to from a time management point of view but can
the extent that it was no longer a viable space be very confusing when considering the lateral
or placed over-optimistic spans that failed to force-resisting structures. Some good scripts
accommodate the loads. Candidates offering showed drawings for both options in Part 1a,
longitudinally spanning structures generally which is not necessarily always the best use of
fared a lot better. time. Those scripts that relied on drawings for
Part 1a without a reasonable written
For longitudinal transfer trusses, it was explanation of load transfer and stability were
straightforward to use the rehearsal studio at risk of being marked down - the Examiners
depth, or the two-storey height office floors, or need to know that the candidate has
all of these, to install a Vierendeel girder. understood the requirements.
Vierendeel trusses were not generally well
done, and if they are to be used in the exam it It was pleasing to see that method statements
is recommended that candidates gain an for construction of the basement were on the
appreciation of approximate methods to size whole reasonable for the majority of scripts,
the sections. There were other possibilities: although addressing the longitudinal-spanning
Warren trusses are more economical to transfer structures was less well dealt with.
fabricate and construct, suffer less deflection
and (importantly in an examination condition) Question 2, Exhibition Centre
are easier for a candidate to design and submit
in their script. One aspect that could potentially The question required selection of a suitable
assist the candidate in deriving a long span framing method to surround the 6m x 12m
solution was that the height of the building was central hole in the upper floor. Columns could
not limited, meaning that an economic Warren be placed only around the perimeter, restricting
truss or trusses could be used for the transfer feasible solutions to portal frames or trusses.
structure in the long-span direction, at least on The subway constrained the positioning of
Gridline 2. However, this was by no means vertical supports at the edges of the building,
universally recognised and most candidates and the ground floor slab needed to span over
chose to span the shorter direction. the subway without imposing loads on the side
walls. The ground conditions varied widely
Vertical deflections were an issue with the 20 m between the two boreholes so different
span structures, with few candidates foundations were needed for each situation.
suggesting pre-cambering solution to deal with The letter was designed to test candidates’
the deadweight deflections. understanding of how a hole in the roof would
affect the wind and snow loading on the
For the provision of lateral stability, most structure, and required a proposal for framing
candidates opted for braced steel frame or around the hole.
reinforced concrete shear wall cores, and these
were dealt with generally satisfactorily. Some Many superstructure schemes proposed were
candidates offered combinations of concrete conventional but some unusual ones were
shear walls and sway frames; it should be suggested including masonry walls and
remembered that there is likely to be an external inclined members. Impractical
solutions included the use of hangers to
2
support the first floor, uneven or large column Question 3, Farm access bridge
spacings leading to uneconomic solutions, thick
and heavy slabs, and large reinforced concrete The bridge question was simple and
beams with impractically heavy reinforcement. straightforward, requiring the calculation of the
The roof covering was required to be concrete influence line for a train of loads. Numerous
tiles, which typically require a minimum roof solutions were feasible: multiple spans could
slope of 12 degrees, but some candidates have been used to overcome the depth
proposed flat roofs. restriction and would have reduced the
complexity of the imposed loading, but were
Candidates varied in their interpretation of the proposed by very few candidates. Many offered
ground conditions. Many assumed rock was single-span Warren or Vierendeel trusses, or
present at 6m depth in Borehole 1, although deep half-through plate girders. Some
this was not stated in the question, and only candidates struggled with the form of deck
one candidate suggested further ground superstructure, suggesting multiple types
investigation should be undertaken to confirm joined together (e.g., concrete box or voided
the conditions. Most schemes proposed deep slab connected to precast beams). More
beams or trusses to span 18m, but the unusual suggestions included the launching or
calculations of loads on these elements lifting and placing of RC box girders. Alternative
produced widely differing results with some solutions proposing only a change of material
candidates making it more difficult for (e.g. steel to concrete) are not sufficiently
themselves by overestimating loads. A distinct: the characteristic properties of each
diagonal grid was a viable option and would material must also be taken into account in
have reduced the spans. Most candidates suggesting spans and details. Stating that “all
proposed piled foundations. Consideration of construction will be monolithic” is not sufficient
the subway varied: some took pains to avoid to make the solution ‘robust’ without further
surcharging it but others barely took it into explanation, especially if the proposed solution
account. A few candidates proposed internal is in steel.
columns: this was a clear breach of the client’s
requirements. The site and soil conditions were ideal for bank
seats on top of bored cast in-situ piles so that
Many candidates seemed to be working to a the new road embankment would be subjected
set method in responding to the first part of the to minimal disturbance. This simple approach
question, which they had perhaps learned on a was preferred by only a few candidates. Some
preparation course. Candidates should use proposed deep pad foundations while others
such methods with caution – while helpful as a suggested piled foundations with a deep
guide, responding appropriately to the abutment or a pile cap at a much lower level,
requirements of the question is more important. requiring deep excavation over a large area.
Some candidates considered multiple spans
In writing the letter many candidates assumed but the 500mm thick concrete canal wall
that when the client “did not want a roof”, some offering 100kN/m vertical load bearing capacity
glazing was to be provided instead, which was was apparently deemed insufficient as a
not necessarily the intention. Glazing could support and new foundations were proposed in
have been offered as an option for the client to or very close to the restricted 3m zone at the
consider. The structural implications of the hole farm side or even through the newly-built road
were generally well-appreciated. For most embankment. Some candidates who took
candidates the technical solution was intermediate support from the canal walls did
straightforward but unfortunately the not appreciate it could carry only vertical loads.
presentation was disappointing and very few of
the letters would have been acceptable in In the letter, candidates were expected to
practice. address the reduced headroom caused by the
rise in water level. Mention of design fees,
Only a few candidates produced satisfactory extensions of time etc. could be relegated to a
calculations in sufficient quantity and detail. very brief sentence at the end. Some
Most were able to list the calculations that were candidates discussed the effect of rising water
needed, but many then failed to produce them. level on the canal wall (not part of the brief),
Key issues were sometimes ignored, such as while others proposed temporary closure of the
the deflection of the main beams or trusses. canal to deal with the problem.
Only a few candidates produced drawings with
sufficient details and data for estimates to be Only a few candidates provided appropriate
produced. Many candidates ran out of time calculations as required by the question.
when they reached section 2e, and only a very Consideration of non-vertical loads and the
few produced more than a bare minimum. The effect of longitudinal inclination of the deck
method statements generally ignored the superstructure was required in the substructure
temporary support needed for the slab over the calculations. Some candidates spent precious
existing subway when the concrete was time analysing and designing deck slabs which
poured. are mostly standard for bridges unless any
special circumstances arise. Some proposed
3
solutions might have caused instability to the designing the rejected scheme. Candidates
existing site configuration, but very few should bear in mind that if the non-preferred
managed to justify its integrity with calculations scheme has no positive attributes that can be
and most did not appreciate the necessity for noted, it is probably not a viable scheme in the
verification. first place and should not have been proposed.
A few candidates produced neat and Letters varied from good to awful. Candidates
appropriate drawings, with enough information are advised to consider the engineering
for pricing. Many candidates were happy to challenges presented by adding a 4.5m-deep
copy standard details from sample answers second and lower basement below the water
even though they were not relevant to the table and methodically address those
question, and thereby lost marks. challenges. Suggesting that the client finds
some other place for storage, or noting that the
Only a few candidates were able to proposal will cost more and must be
demonstrate their understanding of safe resubmitted for review, thereby delaying
construction over water. Traffic management completion, gains no marks.
on the existing road was ignored by most
candidates. Some proposed cast in-situ slabs In Section 2 many candidates did not properly
over the navigable canal without using address the transfer structure: suggestions
permanent formwork. included walls which were over a storey tall
without provision of door openings through the
Question 4, Hotel building wall at the corridor. Other solutions proposed
beams which were too shallow and would have
This question required the design of a 6-storey led to excessive deflections. Some designs of
hotel building with a basement and an inclined transfer beam did not include all the loads.
frontage. A 2-storey atrium was required at the Some candidates did not consider the
front of the building. concentrations of loads caused by the transfer
beams when laying out their foundation
Many candidates proposed the use of inclined schemes. Frequently, members which were
columns at the front of the building, and good designed were grossly oversized or grossly
candidates appreciated the resulting horizontal undersized.
tension force component arising in the floors
from the inclined member and designed for it. The quality of drawings was often poor and not
Candidates are recommended to include enough plans and sections were given.
annotated sketches to show the intended Candidates were often attempting to place all
layout of the proposed schemes and the load their framing plans on a single drawing, but
paths. Some proposed designs ignored the when a foundation plan, a ground level plan, a
client’s brief, especially with respect to the first level (transfer level) plan, a typical upper
transfer beam at the front of the building, which level plan and a roof plan are needed, it is
typically supported the transverse transfer impossible to show them all on a single
beam, where maximum light into the building drawing and address all of the key elements of
was required. Schemes were not sufficiently each level. Examiners are willing to review
distinct in many cases. Only a few candidates multiple levels on a single plan, but can award
recognized that using the stairwells for lateral marks only for elements shown. On this
support places a significant offset between the building it would require at least two, if not
centre of the wind loads and the centre of three, plans rather than a single one to show
rigidity in the transverse direction, and could the required “structural elements and critical
explain the implications. details for estimating”.
For the basement design it was expected that A few candidates gained high marks for
lateral earth and water pressures would be selecting the appropriate critical details: marks
taken into account. It was expected that, for were lost for drawing non-critical (typical)
large-span structural elements, such as a details instead.
transfer beam, the deflection will be checked
and that an adjustment made to the allowable Method statements were insufficiently detailed.
span-depth ratio in cases where the span The statement should make reference to the
exceeds 10m. temporary works needed for the construction of
a basements and large-span structure, and
When choosing their preferred scheme to be should include mention of the environmental
designed in Section 2, some candidates could and safety aspects of the project. The
find only positive points for the scheme they programme should reflect the points mentioned
preferred to design, and only negative things to in the method statement. It should cover the
say about the scheme they would prefer not to construction of the whole building, and not just
design. This is very transparent to the the completion of the structural frame. The
Examiners, and it leads to the suspicion that likelihood of buoyancy during construction was
the real reason for selecting one scheme over frequently ignored.
the other is that the candidate is incapable of
4
Question 5 Town centre car park
Viable schemes included steel or concrete
The question required a town centre car park frames, or load-bearing masonry. Some
on a steeply-sloping site, near to the sea, with solutions offered were entirely of concrete with
a shop unit included in the structure. No levels reinforced walls: these solutions, although
for the car park were given except for the shop viable, were considered to be uneconomical.
level and the entrance level. Candidates Viable foundation options included a raft, pad
needed to consider how cars would circulate in or strip footings, or small-diameter piles.
the car park, so ramp and column locations Candidates who offered large-diameter piles
should have been considered. Some had failed to recognise the small size of the
candidates ignored the usability of the car park building and the site constraints.
and did not include ramps and split levels.
In order to fit the building on to the site,
The car park was located next to a busy high retaining walls were required to support the site
street and was between two existing buildings. boundary. There was sufficient space for a
It was therefore necessary to consider how temporary slope behind the proposed building
damage to the existing buildings could be footprint and an in-situ retaining wall, allowing
avoided in designing the retaining structures conventional foundations to be constructed for
and foundations: this was satisfactorily the building. Alternatively, where the solution
undertaken by only a few candidates. The adopted was contiguous or secant piling or
transfer of loads was not adequately described sheet piling, these could have been made part
in many scripts, and particularly how the out-of- of the permanent works. Within the lifeboat
balance earth pressures could be taken to the housing there was a requirement for an
foundations. Several candidates simply overhead crane, but this was not addressed by
presented an identical grid layout for the two many candidates.
alternative options with the only difference
being a change of material from in-situ The letter required candidates to suggest ideas
concrete to steel: this is not sufficiently distinct for adding floor area. The obvious solution was
unless the different properties of the materials to use the roof space above the amenities and
are taken into account to modify layouts workshop. Most candidates gave this advice
appropriately. although many failed to address how access
would be achieved. Marks were available for
Only a few letters were satisfactory, and many the quality of writing, but unfortunately few
did not address the important structural issues, gained them: letters were often little more than
such as the transfer of loads where notes. While redesign costs and additional time
appropriate, and the requirement to change the can be mentioned, these are secondary and
slab level from the original design. Few are not expected to form the dominant part of a
candidates adequately considered the modified structural engineer’s letter.
waterproofing requirements necessary for the
change in use. Calculations were expected for all key
elements including a typical column and floor
While some candidates provided satisfactory beam, the foundations, the retaining walls, the
designs, calculations were particularly poor in crane rail, the roof structure, and the bracing or
some cases for the foundations, with a few other means of providing lateral stability.
candidates under-designing the foundations by Calculations for simple members were
a factor of 2 while others provided over-sized expected to be comprehensive and should
foundations. include bending, shear and deflection checks
as appropriate. Retaining wall designs should
The drawings tended to reflect shortcomings include bearing capacity, sliding and stability
indicated by Part 1(a), and few candidates checks as well as design of the wall elements.
were comfortable with the different foundation Many candidates did not address the crane
levels. Method statements reflected the beam design in any way. Calculations were
variation in understanding or lack of it regarding often provided in too much detail but for only a
the problems presented by the adjacent few key elements, omitting important ones, or
buildings and the road. Pleasingly, suggested showed a lack of basic skills in sizing up
programme times were generally realistic. members.
Question 6 Lifeboat station building Drawings were expected for foundations, the
first floor, sections and typical elevations.
The question required the design of a two- Generally candidates attempted to show these,
storey lifeboat station on a corner plot of a but the standard of drafting was often very poor
sloping site. This was a small development of and comprised only freehand sketches with few
almost domestic scale, but many candidates notes or dimensions. Drawings must be neatly
did not appreciate this and proposed solutions presented and show adequate details and
that were grossly over-engineered. The member sizes for estimating, and will be
Examiners were looking for solutions that were marked against this standard.
both economical as well as functional.
5
The proposed programme was expected to be by candidates who neglected the specified
9-12 months subject to weather conditions and bridge support requirements.
the extent of off-site fabrication. Candidates
offered programmes from 6 to 18 months. The letter asked the candidates to look at the
implications of adding a large laydown platform
Method statements were often very brief on top of the south end of the bridge.
indicating that candidates had a lack of Extensive modifications to the bridge geometry
appreciation of construction techniques or had were generally unnecessary. Most candidates
begun to run out of time. identified the consequential increases in dead,
imposed and wind loads and the increased
Aspects to include were: reactions at the south in-place bridge supports.
Most candidates also recognised that the
realistic construction programme location of the laydown platform would affect
taking account of weather and sea the lift weight and centre of gravity, and would
conditions together with Health & probably interfere with the south lift rigging.
Safety and statutory procedures. Candidates are encouraged to produce simple
verification of ground conditions sketches to illustrate the problems and their
particularly with a sloping site, structural resolution.
installation and modification of
services, and protection and Candidates were expected to present sufficient
monitoring of the existing retaining calculations to establish the form and sizing of
wall; the principal structural elements and
traffic management and temporary connections, including the permanent supports
works; and lift points. Insufficient attention was given
construction sequence of installation to the sizing of the main structural elements. In
of key elements, any need for many instances dead and wind loads were
fabrication shop inspections before poorly derived. Candidates are reminded that
site delivery, and any lack-of-fit the magnitude of these loadings will govern the
issues. member sizing of the main structural elements,
and these loadings should be determined in a
Question 7, New link bridge between two rational and clearly-understandable manner.
offshore platforms Candidates are encouraged to reconcile their
initial dead load estimate with a final designed
Candidates were required to design a new weight to confirm their calculations remain
bridge linking an existing utilities platform with a valid. Candidates must also allocate sufficient
new living quarters platform. The bridge had to time to consider design of the supports for the
conform to specified dimensional requirements in-place and temporary conditions.
of a 65m span with a mismatch in the height of
the steelwork provided on the two supporting For an offshore link bridge, the critical details
platforms: this can occur because of the more required were the in-place support
stringent requirements for new platforms, which arrangements to tolerate the relative platform
are subject to 10,000-year abnormal wave displacements, the lift points and member
criteria and/or subsidence experienced by connection details where access is limited
some platforms during their service life. A (especially valid for bridges with a triangular
further crucial aspect of the brief was the cross section). Candidates are reminded of the
accommodation of in-line and lateral relative importance of good quality sketches, drawn to
platform movements such as could be caused scale, to clarify their design submissions and to
by wave loading on the supporting platforms. identify the detailing necessary to maintain a
viable arrangement. Single line diagrams are
Candidates generally selected either modified not as useful, as joint eccentricities are not
Warren or Pratt truss solutions using apparent and sensible design proportions
rectangular or triangular forms. Other solutions cannot be verified by simple visual checks.
offered included plated (box girder) or portal Candidates must endeavour to prepare
frame (vierendeel truss) arrangements, drawings consistent with the calculations
although portal frames for this span would be presented in part 2(c).
unsuitable because of the extreme bending
moments at the beam/column connections. In the method statement it was unnecessary to
Candidates are reminded that two distinct and include aspects of the bridge construction and
viable solutions are required, and that the loadout as these did not form part of the
structural behaviour of both solutions must be question, and some candidates devoted
properly explained using words and diagrams. valuable time to these subjects with no gain in
In justifying their preferred solution, good marks. An important procedure to be
candidates gave due regard to the in-place and incorporated would be continuing weather
temporary conditions (loadout, transportation, forecasting and monitoring, weather being the
lift and set-down), recognising that all these principal constraint on commencement of the
conditions influence the framing and member sailaway and lift operations. An understanding
sizing of offshore structures. Marks were lost of offshore installation is necessary as bridges
6
of this span have to be lifted by a Heavy Lift were also on the thin side with candidates often
Vessel, engaged on a primary installation not recognising that building renovation can be
guidance system, rotated into a set down a time- consuming task.
position before being finally positioned by fine
guides to achieve the required installation
tolerances. Candidates are encouraged to
produce simple sketches to illustrate all
significant issues during bridge installation,
especially the bridge guidance system and
location on to the in-place supports. These
operations have a significant bearing on all
offshore structural solutions and may be the
dominant design condition for the main frame
members.
7
Associate-Membership Examination 2011
Questions
Overview
Question 2. Sculpture Platform and Visitor
Associate 2011 Centre.
Membership
Examination A visitor centre was required for the 2012 London
Total Candidates 32 Olympic Games. The building was also required to
Overall pass-rate 62.5% support a monumental sculpture. The visitor centre
was to be in the shape of an equal sided pentagon
in plan. The roof had to be designed to support the
This year the Associate Membership Examination sculpture which was placed centrally. The sculpture
was attempted by 32 candidates, a similar number included an integral rigid plinth which imposed a
to last year. Twenty candidates (62.5%) passed the vertical load, a lateral wind force and an overturning
examination, a slight decrease for the pass rate moment on the roof structure. To keep the visitor
from last year. The Examiners, though, are centre as open as possible, only one internal
encouraged by the fact that a similar percentage of column was allowed, and this had to fit inside a
candidates pass this examination each time. It is 500mm internal diameter circular casing. A clear
also felt that the majority of candidates seem well- headroom of 4m and a services zone of 0.5m were
prepared and understand what they have to provide required. Also the bottom of the sculpture base
in order to pass. The Denis Matthews prize was plinth was required to be no more than 7.5m above
recommended for this year to the candidate who ground, so that the sculpture itself did not extend
passed with the highest aggregate of marks for beyond the 40m height limit.
Sections one and two.
Question 3. Watertight Tanks
For the 2011 Associate Membership Examination,
candidates were required to answer one from a A pair of watertight tanks were required, constructed
choice of four questions. It was notable that the in reinforced concrete. The tanks were part of a
majority of candidates (27 from 32) favoured drainage system in which water flowed along a
question 1, the student accommodation block. channel into the selected tank and out again at the
Below are set out the key features of each question, far end. One or other of the tanks could be selected
together with general feedback on the various using a pair of gates. It was possible that, during
sections. maintenance, one tank could be completely emptied
while the other tank remained full. A large paved
Question 1. Student Accommodation Block area surrounded the inlet channel and tanks to
provide access for maintenance plant and
This question called for the design of a new 4-storey equipment.
block situated on an open campus site, providing
student accommodation comprising student Question 4. Viewing Tower
bedrooms, store rooms, study/dining room and
common areas. Each floor required 30 bedrooms The question required the design of a viewing tower
and 2 store rooms. Each bedroom and store room to overlook an exposed coastal site. The tower was
was to have an overall plan area of 6m long by 4m to have an observation area located at a height of
wide. For access a 2m-wide corridor was required. 12m, accessed by a spiral staircase. A roof was
No columns were permitted within any bedroom, the required over the observation area. The sides of the
study/dining room nor the common areas. The observation area were to be constructed with the
overall height of the building was not to exceed minimum of obstructions. The staircase was to be
16m, while each floor was to have a clear floor-to- provided with a weatherproof envelope to protect
ceiling height of 2.6m. A 150mm raised floor void the users.
was required for services. The external cladding to
the building was to be of cavity wall construction,
while the roof was to have plain clay tiles on battens
with insulation, supported by timber rafters.
8
Feedback
Section 1a
Section 1b
Section 2c
Section 2d
Section 2e