Nama: Pinkyvi Tiffany Widajanto NIM: 2201920530 Personal Assignment 2
Nama: Pinkyvi Tiffany Widajanto NIM: 2201920530 Personal Assignment 2
NIM: 2201920530
Personal Assignment 2
A. Resource Scheduling
You have prepared the following schedule for a project in which the key resources is a tractor. There are
three tractors available to the project. Activities A and D require one tractor to complete while activities B,
C, E, and F require two tractors.
Develop a resource constrained schedule in the loading char that follows. Use the parallel method and
heuristics given. Be sure to update each period as the computer would do. Record the early start (ES), the
late finish (LF) and slack (SL) for the new schedule.
A 1 4 0 5 1 1 1 1 1
B 2 5 0 5 0 2 2 2 2 2
C 2 4 5 9 0 X 2 2 2 2
D 1 5 5 8 2 1 1 1 1 1
E 2 3 9 11 0 X X X X 2 2 2
F 2 2 12 14 0 X X 2 2
Resources Scheduled 3 3 3 3 2 3 3 3 3 3 2 2 2 2
Resources Available 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Use the information contained below to compress one time unit per move using the least cost method.
Reduce the schedule until you reach the crash point of the network. For each move identify waht activity(s)
was crashed, the adjusted total cost, and explain your choice if you have to choose between activities that
cost the same.
If the indirect cost for each duration are $1,500 for 17 weeks, $1,450 for 16 weeks, $1,400 for 15 weeks,
$1,350 for 14 week, $1,300 for 13 weeks, $1,250 for 12 weeks, $1,200 for 11 weeks, adn $1,150 for 10
weeks, what is the optimum cost-time schedule for the project? What is the cost?
Normal Time = 17
Total Direct Cost = 2000
CP= A+B+D+H+I
Time = 15
CP = A+B+D+H+I
Activities Changed = H
Time = 14
CP = A+B+D+H+I
A+B+F+G+I
Activities Changed = H
CP = A+B+D+H+I
A+B+F+G+I
Activities Changed = B
Time = 12
CP = A+B+D+H+I
A+B+F+G+I
Activities Changed = I