TECH- 2 Technical Proposal for General Consultant for

Chennai Metro Rail Phase-2 Project - Corridor 4

FORM TECH-2

CONSULTANT’S ORGANIZATION AND EXPERIENCE


Brief Description of the Consultant’s Organisation
RITES Ltd Consultancy Firm incorporated in India as a Public Limited Company during 1974 and listed at NSE and
BSE.
Nippon Koei India Nippon Koei India Pvt. Ltd. (NK India), formed in 2008, is an ISO 9001:2015 & ISO 14001:2015 certified
Pvt. Ltd. company and is a wholly owned subsidiary of Nippon Koei Co., Ltd. of Japan (Nippon Koei).
Nippon Koei Co. Nippon Koei Co., Ltd. (NK) is Japan’s No.1 International Engineering Consultant, established 1946, is an
Ltd. ISO 9001:2015 & ISO 14001:2015 certified company. During 70 years, Nippon Koei has worked on over
5,500 multi-disciplinary infrastructure projects in 160 countries all over the world.
Arup India Pvt Ltd. Arup established a wholly owned subsidiary, Arup India Private Limited, in January 2008 to provide our
Indian and global clients the full array of multi-disciplinary services of the Firm.
Ove Arup & Partner
International Ltd.
Outline of the Recent Experience of the Consultant – Relevant to the Assignment
RITES Ltd a. Name of General Consultancy Services for Bangalore Metro Rail Project Phase-I.
Assignment & Key Name of Key Experts involved:
Experts 1. Sh. S Balakrishna, Dy PD

2. Sh. DRK Reddy, Project Manager (NS)

3. Sh. Mahesh Kumar, Project Manager (EW)

4. Sh. Ramesh Pinjani, Project Manager

5. Sh. A.K. Singh, Project Manager

6. Sh. Rajagopalan, Chief Finance

7. Sh. Pradeep Deogire, Chief Architect Expert

8. Sh. K Ramakrshina, Chief Resident Engineer

9. Sh. KVVR Murty, Chief Resident Engineer

10. Sh. Sameer Basha, Chief Structural Engineer

11. Sh. L.D. Prabhakar, Contract Expert

12. Sh. R Bala Subramanium, Senior Resident Engineer

13. Sh. US Virat, Senior Resident Engineer

14. Sh. Virender Sharma, Senior Resident Engineer

15. Sh. CHM Raju, Senior Resident Engineer

16. Sh. Shannu Ganeshan, Resident Engineer

17. Sh. DK Sharma, Resident Engineer

Page 1 of 4
TECH- 2 Technical Proposal for General Consultant for
Chennai Metro Rail Phase-2 Project - Corridor 4

18. Sh. Puskhar Narayanan, Resident Engineer

19. Sh. Ravinder Dutta, Resident Engineer

20. Sh. Jitendedra Jha, Resident Engineer

b. Duration of 01.08.2007 to 31.03.2016


Assignment

c. Contract Amount INR 2,548,973,717


(Total)

d. Amount paid to INR 343,73,86,162


Consultant :

e. Role/Involvement Lead partner in JV of RITES, India; Oriental Consultant Co. Ltd.(OCCL),


Japan; Parsons Brinkerhoff International, Inc. (PBI), USA and SYSTRA,
France

Nippon Koei India a. Name of


Pvt. Ltd. Assignment & Key
Experts

b. Duration of
Assignment

c. Contract Amount N.A.


(Total)

d. Amount paid to
Consultant

e. Role/Involvement

Nippon Koei Co. a. Name of Ho Chi Minh City Urban Railway (MRT) Construction Project Ben Thanh - Suoi
Ltd. Assignment & Key Tien Section (Line 1)
Experts Name of Key Experts involved:
Hiroshi Izawa : Project Director (Management); Stuart John Littlewood : Project
Director(Engineering); Derek Marsden : Chief Program Manager; D. Chamock :
Chief Safety Expert; S.Higashinakagawa : Chief Environment Expert; Y.Minami
: Chief Sociologist; A. Hosomi : Chief Transportation Plg./Public Relations
Expert; S. Matsumura : Chief Urban Planning Expert; M.Okamura : Chief Urban
Institution Expert; H. Hotta : Chief Property Dev. Expert; T.Aikawa : Chief Train
Operation Expert; M. Iwasaki : Finance Expert; R.A. Borthwock : Chief Contract
Expert; Chiris Kwan Chi Tong : Chief Specification Expert; Iwan CK Chiu :
Chief Quality Assurance Manager; Ryan Luong : Chief Manual Expert;
H.Omura : Chief Cost Control Manager; Chief Training Expert: H.Matsumoto;
T.Sugiyama : Project Manager Underground; Roger W. Rothenburger :
Construction Manager Underground; S. Nakamura : Chief Cut&Cover Expert;
K.Kobayashi : Tunnel Manager; T.Shirai : Chief Geotechnical Expert;

Page 2 of 4
TECH- 2 Technical Proposal for General Consultant for
Chennai Metro Rail Phase-2 Project - Corridor 4

F.Mitsuhata : Chief Survey/Alignment Expert; H.Nishizawa : Chief Station


Structure Expert; T.Iwamoto : Chief Station Layout Expert; Y.Kamata : Chief
M&E Engineer; D.Chi Leung Chan: Chief Elec. Eng. Expert; J. Kwok Hong Tam
: Chief Station Utility Expert; Po Biu Lee : Chief AC/Vent&Utility Expert
b. Duration of Jan/2008 to Ongoing
Assignment

c. Contract Amount INR 6,12,30,03,794/- (1 JPY = 0.6941 INR as on 10.09.2020)


(Total)

d. Amount paid to INR 3,68,23,97,956/-


Consultant

e. Role/Involvement Lead partner in JV of Nippon Koei Co., Ltd.; Japan Railway Technical Services;
PB Japan Co., Ltd.; JR East Japan Consultants Company; Japan
Transportation Consultants, Inc; Tonichi Engineering Consultants, Inc;
Transport Engineering Design Incorporated-South Joint Stock Company and
Transport Investment and Construction Consultant Joint Stock Company
Arup India Pvt Ltd. a. Name of
Assignment & Key
Experts

b. Duration of
Assignment

c. Contract Amount
(Total)

d. Amount paid to
Consultant

e. Role/Involvement

Ove Arup & Partner a. Name of


International Ltd. Assignment & Key
Experts

b. Duration of
Assignment

c. Contract Amount
(Total)

d. Amount paid to
Consultant

e. Role/Involvement

Page 3 of 4