AMERICAN INTERNATIONAL UNIVERSITY - BANGLADESH (AIUB)

Faculty of Business Administration

Project Report Summary

Submitted By:
NAME ID

Md Ashikur Rahman 17-34435-1


Arittra Biswas 17-35781-3

Submitted to: Sadia Rahman


Hosting BPL Tournament
Introduction:
Bangabandhu Premier League is an association formed by well-known softball cricketers who
are playing cricket for years. The passion for cricket and community leadership brought fine
people together to form and established this association in a very short term. BPL will be
organizing softball cricket tournaments and league games in Twenty 20 format between twelve
leading teams who were playing cricket professionally for more than three years in other
organized leagues. BPL is committed to provide a platform for all like minded people to enjoy
cricket and socialize with each other and create a family atmosphere. We know this will get
better and bigger in coming years and will attract more teams and supporters from our
community.

Activities Demonstration:
1.    Board Meeting: For the very beginning, must create a board meeting with our organizing
team. All decision will be taken in this meeting.
2.     Allocation of matched: After registration, all team will be shuffle for and match. The
schedule time should be allotted as well as the venue.
3.    Visas: For the foreign players must have visa for participation the competition.
4.    Media and promotion: This is very important because it is the heart of  a cricket match
without camera and all this equipment it will be like a myth. All the spectators get exited with
when they hear commentary and this will be good for game and organization.
5.    Broadcasting right: This is very important, without permission it is not possible to
broadcast any match.
6.    Prize money: This is very important part of the game. The winner must be awarded. The
prize can be in term of cash or trophy.
7.    Venues: The place where the match will be held must be selected. It can be within the
organization or outside the organization, so it has to be decided where the match will be played.
8.    Umpires: Umpires shall be hired from outside the organization so that fair decision can be
made.
9.    Warm-up matches: Practice time for each team will be scheduled so that each team get
time to prepare themselves for the game. 
10. Group stage: This is our first stage for the tournament. In this stage all team will play among
them and earn point. All 16 teams play against each other in the 1st round. Total of 120 matches
in the 1st roundPoint will be given according to their winning matches and there performance.
Point will help them to participate knockout stage. Standing 1,4,6,8,10,12,14 & 16 will be called
GROUP A.
Standing 2,3,5,7,9,11,13,15 will be Called GROUP B.  
11. Knockout stage: In this stage those who can gain well point in the first stage. In the 2nd
round 16 teams will be divided into two groups based on the 1st round standing. At this point
teams will play once with other in the same group
12. Statistics: A team will be playing 22 games before the playoff.
Including both groups matches total of 56 matches played in the 2nd round.
Top EIGHT teams will be selected for the playoff. League matches will award 3 points to the
winning team.Knock out matches will award 1 point to the winning team
The activities of the BPL Tournament:
Activities Activity Immediate Expected Time
Name Predecessor (Days)
Board Meeting A - 7
Allocation of matches B A 5
Visas C B 6
Media and promotion D - 2
Broadcasting rights E D 4
Prize money F A 3
Venues G B 7
Umpires H C,G,F 4
Warm-up matches I F 5
Group stage J I 17
Knockout stage K E 5
Statistics L H,J,K 2

Network Diagram: (CPM)

0 7 7 12 12 18

A B C
0 7 16 21 22 28

19 23
7 10 12 19

F G H
0 0 32 34
28 32 34 34
7 10 21 28
start L
end
0 0 32 34
10 15 15 32 34 34

I J
10 15 15 32

0 2 2 6 6 11

D E K
21 23 23 27 27 32
Possible paths:
1. A-B-C-H-L = 7+5+6+4+2= 24
2. A-B-G-H-L = 7+5+7+4+2=25
3. A-F-H-L = 7+3+4+2=16
4. A-F-I-J-L = 7+3+5+17+2=34
5. D-E-K-L = 2+4+5+2= 13

Critical path: A-F-I-J-L


Expected project duration: 34 days

Slack time:
A=0 G=9
B=9 H=9
C=10 I=0
D=21 J=0
E=21 K=21
F=0 L=0
Gantt Chart:
Star 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36
t
A
D
B
C
F
I
J
G
H
E
K
L