COMPANY ------------

PROJECT AREA KALTENG

DATE DECEMBER 3, 2019

Dear sir,

We is very pleased to provide the following technical and cost proposal for Light Detection and
Ranging (LiDAR) use UAV data acquisition and processing with area cover approximately 500
hectares located in Kalteng.

Approximate location Area of


Interest for LiDAR survey

SCOPE OF WORK

We understand that you require the LiDAR and Aerial Photography to deliver accurate terrain
elevation model and terrain cover information to allow your technical personnel to manage
your properties more effectively. The following proposed scope of work addresses these
needs efficiently and using a combination of the most effective current drone surveying
technologies.

• Mobilize LIDAR Team to site location, and find the base coordinate.
• Acquire LIDAR data and Aerial Photography covering an area of 500 Ha. The vertical
accuracy of the data is to be 0.05 – 0.10 m (standard error at 1 sigma) on clear ground
and around 0.50 m on vegetation area. The horizontal accuracy of the data is to be
0.20 m
• Process the data to a spatially correct Digital Surface Model (DSM) of unclassified
LiDAR strikes. The unclassified LiDAR strikes (point cloud) will contain the ground and
non-ground elevation points.
• All data to be supplied in UTM coordinates using WGS84 GPS datum. Vertical datum
will be geoidal height generated from the EGM96 spheroid / geoid separation model
adjusted to whatever vertical datum is being used on the project.
• Classify the LiDAR to “ground” and “non-ground” elevation points into separate data
set files for delivery and for each project block area.
• Each project area will be tiled into 1 km x 1 km tiles for classification and edits.
• After the LiDAR point classification contouring will be generated for the ground
elevations and provided at a contour interval suitable for the type of project area terrain
relief. We suggest 1.0 m contours or other agreed specification for flat terrain.

WORK EXECUTION

The following is the process of capturing the Airborne Laser Scanning (LIDAR) data.

• We will supply dual frequency geodetic GPS to be established in the area. The base
stations will be manned and logging dual frequency data at 0.5 second epochs during
the period of data capture. The GPS data will be combined with the LiDAR data for
processing at the completion of each day flying. The LIDAR data will be processed on
site to a stage where it is checked for completeness before the survey team
demobilizes.
• LIDAR survey data will be acquired in UTM coordinates on the WGS84 GPS satellite
datum (ITRF 2000 Reference Frame) and will be adjusted to orthometric heights
applying a correction to every data point using the EGM96 geoids model with an
average point density of better than 70 - 90 point/m² (DSM) using a M8 Quanergy
airborne laser scanning unit. If a different survey datum is required for the LiDAR data,
we will transform the data based on transformation parameters supplied by the client.

• We will use Drone Matrice M600 Pro. The flying height for the data capture will be
approximately 70 - 110 meters above terrain level to get most effective point clouds.

CLIENT PROVIDES:

The client is responsible for the provision of the following.


• Supporting our team during acquisition data
• Client’s personnel in charge on site during data acquisition; for site preparation and
coordination with our GPS surveyor.
• Messing, accommodation and local transport for support of daily GPS surveyor during
LIDAR data acquisition.
• One (1) Benchmark control point GPS on the site.
PERSONNEL & EQUIPMENT

The survey team will consist of the following.

• Project Manager/Coordinator
• LIDAR operator
• LIDAR data processor
• GPS Surveyor

The following equipment will be utilized:


• Optech M8 Quanergy laser scanning system complete with the INS Inertial System
• Trimbel NetR9 GNSS receivers for ground control
• Metrice M600 Pro
DELIVERABLES:

The following will constitute the standard deliverables for the project.

• Digital terrain model (DTM) consisting of the


thinned LiDAR ground strikes, supplied in
space-delimited ASCII format.
• Digital surface model (DSM) consisting of all
LiDAR strikes, supplied in space delimited
ASCII format.
• Line map in scale 1:2500 containing 1 m
countours interval or other agreed
specification.
• Fature extraction (if client request Aerial Foto
also)
• Final Report

Note :

- More request data can be discussed


TIME SCHEDULE

Estimate time to finish project is 2 week, 1 week for acquisition and 1 week for processing
data.

COSTS

We would like to submit our budgeted financial proposal as below:

Lump Sum Price IDR 290.000.000

Note: - the price can change base on real area in ha.


- The price only acquisition data, not include Mob – demob,
accommodation, and cost during in site.

TERMS AND CONDITIONS

• This quotation is valid for 1 month from the proposal date.


• All price exclude VAT 10% taxes.
• All price in IDR
• We Freserve the right to schedule the data acquisition in a specified time frame.
• If weather or other conditions intervene, We reserves the right to reschedule the data
acquisition or demobilize from the project.
Page | 5
• Payments are due fourteen (14) days after receipt of invoice. Payment should be made
by electronic funds transfer (EFT) to the bank account nominated on the invoice, with
following schedule :
➢ down payment 30% of the contract price should be received 7 (seven) days
prior of order to mobilize from company to the contractor.
➢ 50% of the contract price after the completion of data acquisition.
➢ 20% of the contract price after the receipt of the acceptance of all final data
submission from the company.

We trust that this is the information you require. Should you have any questions regarding this
proposal, please do not hesitate to contact the undersigned.

Yours sincerely,

Angga D

Email : Laksono.anggadwi@gmail.com
H/P : 085643406455

Page | 6