S-CURVE & REPORT PROGRESS

CHANGED OUT CATALYST FOR 212-V-1,2 & 3 HCC AREA, TURN AROUND 2020, PERTAMINA RU II DUMAI
DATE REPORT 4-Nov
TO DATE 20-Nov
REMAINING DAY 16 Days
PROGRESS WORK DURATION
Task Name WF
% PROG % WF PLAN 31-Oct 1-Nov 2-Nov 3-Nov 4-Nov 5-Nov 6-Nov 7-Nov 8-Nov 9-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov
SHUTDOWN WORKS
Shutdown
Conditioning Reactor (Depressurize & Cooling Down)
COC WORKS 100.00%
99.52% 100.00%100.00%100.00%
22.00%
212-V-2
Blinding Installation 2.86% 100.00% 2.86% 1.06% 12 12 96.19%
Top Manhole Opening 4.29% 100.00% 4.29% 1.06% 18 18

92.02% 92.98%
Remove Inlet Diffuser 0.36% 100.00% 0.36% 1.06% 3
Open Bubble Cap Manways 0.36% 100.00% 0.36% 1.06% 1.5 1.5 20.00%
90.00%
Dump Out Catalyst 5.71% 100.00% 5.71% 1.06% 16 16 16
Vacuum Out Remaining Catalyst & Ceramic Balls 0.48% 100.00% 0.48% 1.06% 4
Cleaning and turn Fresh air into vessel 2.86% 100.00% 2.86% 1.06% 12 12
87.02%
Inspection Internal Vessel 0.36% 3
Loading Ceramic Balls and Catalyst 4.29% 12 12 12 83.04% 18.00%

% Progress Cumulative
Reinstall Bubble Cap Manways 0.48% 80.00% 4
Final Cleaning and Inspection 0.48% 4
Reinstall Inlet Diffuser 0.36% 3
Box Up Top Cover and Elbow 2.86% 12 12 76.19%
Remove Blinding 1.43% 12
16.00%
Housekeeping 0.95% 4 4 72.44%
212-V-1 70.00% Planned : 26.43%
Blinding Installation 2.86% 100.00% 2.86% 1.06% 12 12
Top Manhole Opening 4.29% 100.00% 4.29% 1.06% 12 12 12 66.55% Actual : 47.26%
Remove Inlet Distributor 0.36% 100.00% 0.36% 1.06% 3 Ahd/ (-)Bhn : +20.83% % 14.00%
Open Bed #1 Bubble Cap Manways 0.36% 100.00% 0.36% 1.06% 3
Vacuum Out Cat. Trap at bed #1 0.48% 100.00% 0.48% 1.06% 4
Dump Out at bed #1 2.86% 100.00% 2.86% 1.06% 60.00% 12 12
Vacuum Out Remaining Catalyst & Ceramic Balls at Bed #1 0.48% 100.00% 0.48% 1.06% 4 57.50%
Open Bed #1 Support Grid Manways 0.48% 100.00% 0.48% 1.06% 2 2
Dismantle Quench Distributor 0.48% 100.00% 0.48% 1.06% 4 12.00%
Open Bed #2 Bubble Cap Manways 0.36% 100.00% 0.36% 1.06% 3
Dump Out at bed #2 2.86% 100.00% 2.86% 1.06% 12 12
50.00%
Vacuum Out Remaining Catalyst & Ceramic Balls at bed #2 0.48% 100.00% 0.48% 1.06% 4
Cleaning and turn Fresh air into vessel 2.86% 47.26% 12 12 47.62%
Inspection Internal Vessel 0.48% 4 10.00%
Loading Ceramic Balls and Catalyst at Bed #2 5.71% 16 16 16
Reinstall Bed #2 Bubble Cap Manways 0.48% 4
Reinstall Quench Distributor 4.29% 40.00%
40.95% 12 12 12
Reinstall Bed#1 Support Grid Manways 4.29% 18 18
Final Cleaning and Inspection Bed #1 0.48% 2 2 8.00%
Loading Ceramic Balls and Catalyst at Bed #1 2.86% 35.95% 8 8 8
34.52%
Reinstall Bed #1 Bubble cap manways 0.48% 4
Reinstall Inlet Diffuser 0.36% 3
Box Up Top Cover and Elbow 2.86% 30.00% 12 12
Remove Blinding 1.43% 12
Housekeeping 0.95% 27.07% 26.43% 4 4
6.00%

212-V-3
Blinding Installation 2.86% 100.00% 2.86% 1.06% 12 12
Top Manhole Opening 4.29% 100.00% 4.29% 1.06% 18 18
Remove Inlet Diffuser 0.36% 100.00% 0.36% 1.06%
20.00% 20.36% 3
Open Bubble Cap Manways 0.36% 100.00% 0.36% 1.06% 18.33% 3
4.00%

Dump Out Catalyst 5.71% 100.00% 5.71% 1.06% 16 16 16


Vacuum Out Remaining Catalyst & Ceramic Balls 0.48% 100.00% 0.48% 1.06% 14.82% 4
Cleaning and turn Fresh air into vessel 2.86% 12.19% 12 12
Inspection Internal Vessel 0.36% 10.00% 10.71% 1.5 1.5
Loading Ceramic Balls and Catalyst 4.29% 18 18 2.00%

Reinstall Bubble Cap Manways 0.48% 4


Final Cleaning and Inspection 0.48% 4
Reinstall Inlet Diffuser 0.36% 4.29% 1.5 1.5
Box Up Top Cover and Elbow 2.86% 12 12
Remove Blinding 1.43% 0.00% 12 0.00%
3

9
1

13

14

15

18

19

20
10

11

12

16

17

21
Housekeeping 0.95% 8
100% 36 54 34.5 29.5 68 68 54 56 83 76 49.5DAYS 31.5 57.5 33.5 42 8 27 28 4 0 0
47.26% 26.43% 36 90 124.5 154 222 290 344 400 483 559 608.5 640 697.5 731 773 781 808 836 840 840 840
ITEM CONCERN Progress PLAN PROGRESS
212-V-2 Last Today Cumm 4.29% 6.43% 4.11% 3.51% 8.10% 8.10% 6.43% 6.67% 9.88% 9.05% 5.89% 3.75% 6.85% 3.99% 5.00% 0.95% 3.21% 3.33% 0.48% 0.00% 0.00%
Blinding Installation 100% 4.29% 10.71% 14.82% 18.33% 26.43% 34.52% 40.95% 47.62% 57.50% 66.55% 72.44% 76.19% 83.04% 87.02% 92.02% 92.98% 96.19% 99.52% 100.00% 100.00% 100.00%
Top Manhole Opening 100% ACTUAL PROGRESS
Remove Inlet Diffuser 100% 12.19% 8.17% 6.71% 8.88% 20.19%
Open Bubble Cap Manways 100% 27.07% 20.19% 47.26% 12.19% 20.36% 27.07% 35.95% 47.26%
Dump Out Catalyst 100% DEVIASI
Vacuum Out Remaining Catalyst & Ceramic Balls 100% 7.90% 9.65% 12.25% 17.62% 20.83%
Cleaning and turn Fresh air into vessel 100% Prepare by Review By Approved By
212-V-1 PT Mipcon Prima Industri PT Patra Badak Arun Solusi PT Pertamina RU II
Blinding Installation 100%
Top Manhole Opening 100%
Remove Inlet Diffuser 100%