AS PER BOQ
Sl. No. ITEM DESCRIPTION
UNIT RATE Qty AMOUNT
General Excavation by mechanical means in all types of soil including dense soil,
disintegrated/ weathered/ soft rock including necessary manual excavation for dressing
the edges & levelling, all leads and lifts. Rate to include disposing the excess earth and
spreading in layers to the required levels within the site wherever specified, carting away
1.01
outside the site to the designated areas identified by the local authorities, removal of
slurry generated while excavation and keeping the area free of water, excavating loose
pockets and compacting the same. Note:Authorised working space shall be considered
as per IS 1200 (Provision of slopes if required for execution shall not be paid separately).
Supply and filling in foundations and the area whereever specified with approved good
quality filling materials in plinths, area development etc. wherever specified in layers of
not exceeding 150 mm thick including breaking clods,storing,transportation ,double
handling, watering, compacting each layer with vibratory compactor and at
1.05 unaccessible places with wooden/steel rammers to achieve 95% proctor density at
optimum moisture content, all leads and lifts, bailing/ pumping out of water to keep site
dry while backfilling; cost shall include conveyance of all materials, labour, machinery
etc. complete as directed.The rate to includes loading,unloading, hire and fuel charges
for tools and plants and other incidental charges etc., complete.
a With excavated earth stored and available at site Cum 264.00 7.60 2,006.40
AS PER BOQ
Sl. No. ITEM DESCRIPTION
UNIT RATE Qty AMOUNT
Providing and laying in position 200mm thick soling with excavated/available laterite
rock The cost includes preparation of Base,breaking of available laterite to required
1.06 size,packing with hand broken Laterite /metal/ Rubble and smaller pebbles for void Sqm 386.00 50.67 19,558.62
filling, moorum for binding and Mechanical vibratory compaction as directed by the
Engineer-in-charge including watering,packing, compaction etc.
Providing Anti termite treatment in accordance with stipulations laid down by IS 6313 -
part II by approved agency with min of 10 years of guarantee including the cost of
2.00 chemical,precautionary measures etc.complete along retaining walls only for a width of Sqm 65.00 59.09 3,840.85
one meter or as specified by consultants ( agency shall be approved by
consultants/project managers) Plinth area will be considered for the measurement .
Providing, batching, mixing, transporting through transit mixers, pumping and laying
controlled Reinforced Cement Concrete of specified grade at all levels and heights
specified below using ordinary Portland cement of grade 53 from approved
manufacturer, river sand, 20mm and down size coarse aggregates, necessary
admixtures approved by Consultants (elkem and Conplast SP 430SRV from Fosroc or -
equivalent), including all leads and lifts, pumping using line pump or boom placer,
vibrating/ compaction, scaffolding wherever necessary, curing as directed, excluding
cost of shuttering and reinforcement works.
2.05.01 Columns -
M25 Grade -
Providing, fabricating and erecting form work at all levels and places wherever
needed/specified as per drawing including striking with 12mm Plastic coated, marine
resistant waterproof ply/Smooth finished MS plates with adjustable steel props of
acceptable Staging and with sufficient bracing as approved by consultant. Cost to
include designing of proper form work and staging system to suit the
requirements,Submission of design calculations a nd shop drawings for approval,sealing
the joints with heavy duty brown self adhesive tape, aligning to line and levels including
M.S. Ties, PVC Spacer, Providing openings/ cutouts/ pockets, applying deshuttering
chemical, Deshuttering as approved by the consultant etc., complete at all levels,
double/tripple heights and profiles
1) plywood shuttering shall be considered for all vertical elements,beam sides and
soffit,corewalls,stairs,ramps,tanks,RCCpedestals Etc.,
2) M.S. plates shall be considered for Footings,slabs,chejjas only.
3.01 Columns (With Plywood)
a) Foundation to Plinth Sqm 585.00 14.76 8,634.60
b) Plinth to First Floor Sqm 585.00 29.27 17,122.95
c) AboveRoof Cum 585.00 5.71 3,340.35
3.08 RCC Brackets/Fins/Ledges at all levels ( with Plywood) Sqm 860.00 3.83 3,293.80
3.10 Plinth Beams (With Plywood) Sqm 640.00 30.32 19,404.80
Sub total Form Works 113,761.27
4.00 Finishing Works
1 Blockwork - 200mm Sqm 1,107.00 99.00 109,593.00
2 Internal Plastering Sqm 565.00 103.59 58,528.35
3 External Plastering Sqm 655.00 133.68 87,560.40
4 Chajja Plastering Sqm 665.00 4.68 3,112.20
5 Emulsion - Internal Painting Sqm 455.00 103.59 47,133.45
6 Apex- External Painting Sqm 445.00 133.68 59,487.60
7 Granite Flooring Sqm 2,400.00 50.67 121,608.00
Sub total Finishing 487,023.00