Bar Chart Mechanical, Electrical, & Plumbing Work
Bar Chart Mechanical, Electrical, & Plumbing Work
PRELIMINARIES WORK
1 Membuat Gambar Kerja / Shop Drawing Instalasi lot 1 14 Hari
2 Mengajukan Approval Material dan Dokumen yang di perlukan lot 1 14 Hari
3 Membuat Dokumen Kontrak lot 1 14 Hari
4 Supervisi dan Koordinasi Lapangan lot 1 14 Hari
A BASEMENT FLOOR
I PLUMBING WORK
Instalasi Pipa Air Bersih
PPR Pipe PN-10 mtr 122 4 Hari
GIP Medium Class, DN 150 - 80 mm mtr 42 2 Hari
Instalasi Pipa SW, WW, KD, RW
PVC AW, Air Kotor (SW) mtr 56 2 Hari
PVC AW, Air Bekas (WW) mtr 50 2 Hari
PVC AW, Air Hujan (RW) mtr 10 2 Hari
Instalsai Pipa Air Bersih
PPR Pipe PN-10 mtr 305 9 Hari
R
II ELECTRICAL WORK E
Piping & Wiring untuk Instalasi Penerangan S
- Parkir and Public Area Ttk 50 6 Hari
C
- Kios Area Ttk 10 2 Hari
H
Pemasangan Tray
E
- Tray Cable Type Cage 300 S/D 100 x 100 S/D 50 mm mtr 99 1 Hari
III ELECTRONIC WORK
D
i FIRE ALARM U
Piping dan Wiring untuk Instalasi Fire Alarm L
- Basement Floor Ttk 28 5 Hari E
ii SOUND SYSTEM
Piping dan Wiring untuk Instalasi Sound System
S
- Basement Floor Ttk 12 3 Hari
A
Pemasangan Tray
M
- Tray Cable Type Cage 800 S/D 200 x 100 mm mtr 132 2 Hari
IV MVAC WORK
P
REFRIGERANT PIPE
A
Copper Tube, 1/4" + 5/8" C/W Insulation mtr 18 4 Hari I
L
A
H
A
N
PT. TRIKARSA BAHTERA ABADI 1 WEEKLY WORK PLAN
S
P
FEBRUARI 2021 A
NO ITEM KERJA SAT VOLUME DURASI KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22 I
DUCTING AND GRILEE AIR VENTILATION
EF - BS.1 L
DUCTING EXHAUST FAN mtr2 178 14 Hari A
EF - BS.2
H
DUCTING EXHAUST FAN mtr2 10 4 Hari
A
EF - BS.4
N
DUCTING EXHAUST FAN mtr2 2 4 Hari
EF - BS.7
DUCTING EXHAUST FAN mtr2 2 4 Hari S
EF - BS.9 I
DUCTING EXHAUST FAN mtr2 16 4 Hari A
EF - BS.12 P
DUCTING EXHAUST FAN mtr2 2 4 Hari
IF - BS.1
DUCTING INTAKE FAN mtr2 90 14 Hari
IF - BS.2
DUCTING INTAKE FAN mtr2 156 14 Hari
IF-SB.1
DUCTING INTAKE FAN mtr 195 14 Hari
IF-SB.2
DUCTING INTAKE FAN mtr 322 14 Hari
IF-SB.3
DUCTING INTAKE FAN mtr 61 6 Hari
C GROUND FLOOR
I MVAC WORK
REFRIGERANT PIPE
D LANTAI 2
I MVAC WORK
REFRIGERANT PIPE
Type 1 - BR ( 12 Unit )
Copper Tube, c/w insulation mtr 45 4 Hari
Type 2 - BR ( 2 Unit )
Copper Tube, c/w insulation mtr 40 4 Hari
PODIUM AREA
RESCHEDULE COMERCIAL AREA
Copper Tube, c/w insulation mtr 129 10 Hari
E LANTAI 3
I PLUMBING WORK
Instalasi Pipa Air Bersih
PPR Pipe PN-10 mtr 44 2 Hari
Instalasi Pipa Air Bersih Unit Apartment Toilet
PPR Pipe PN-10 mtr 237 4 Hari
F LANTAI 4
I PLUMBING WORK
Instalasi Pipa Air Bersih Unit Apartment Toilet
PPR Pipe PN-10 mtr 404 11 Hari `
II FIRE FIGHTING WORK
Instalasi Black Steel Pipe Fire Fighting Hydrant mtr 4 1 Hari `
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 161 8 Hari `
III ELECTRICAL WORK
Piping dan Wiring untuk Instalasi Penerangan
- Toko 5 Ttk 25 2 Hari RESCHEDULE SAMPAI AREA TOKO SIAP
G LANTAI 5
I PLUMBING WORK
Instalasi Pipa Air Bersih Corridor
PPR Pipe PN-10, DN 15 mm mtr 5 1 Hari
Instalasi Pipa Air Bersih Unit Apartment Toilet
PPR Pipe PN-10, DN 20 - 15 mm mtr 209 4 Hari
Instalasi Pipa SW,WW,KD,RW
PVC AW, Air Kotor ( SW ) mtr 63 2 Hari
PVC AW, Air Bekas (WW) mtr 156 6 Hari
PVC Class D,Vent (VT) mtr 215 8 Hari
PVC AW, Air Hujan (RW) mtr 76 3 Hari
II FIRE FIGHTING WORK
Instalasi Black Steel Pipe Fire Fighting Hydrant mtr 10 1 Hari `
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 360 8 Hari `
H LANTAI 6
I PLUMBING WORK
Instalasi Pipa Air Bersih Corridor
PPR Pipe PN-10, DN 15 mm mtr 5 1 Hari
I LANTAI 7
I PLUMBING WORK
Instalasi Pipa SW,WW,KD,RW
PVC AW, Air Kotor ( SW ) mtr 125 1 Hari
PVC AW, Air Bekas (WW) mtr 312 3 Hari
PVC Class D,Vent (VT) mtr 428 4 Hari
PVC AW, Air Hujan (RW) mtr 38 1 Hari
II FIRE FIGHTING WORK
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 206 10 Hari
J LANTAI 8
I PLUMBING WORK
Instalasi Pipa SW,WW,KD,RW
PVC AW, Air Kotor ( SW ) mtr 125 1 Hari
PVC AW, Air Bekas (WW) mtr 312 3 Hari
PVC Class D,Vent (VT) mtr 428 4 Hari
PVC AW, Air Hujan (RW) mtr 38 1 Hari
II FIRE FIGHTING WORK
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 206 10 Hari
K LANTAI 9
I FIRE FIGHTING WORK
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 206 10 Hari
L LANTAI 10
I FIRE FIGHTING WORK
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 206 10 Hari
M LANTAI 11
I ELECTRICAL WORK
Piping & Wiring untuk instalasi penerangan
- Unit Apartment 1 - BR ( 19 Unit ) Ttk 57 6 Hari
- Unit Apartment 2 - BR ( 11 Unit ) Ttk 50 5 hari
II ELECTRONIC WORK
i FIRE ALARM
Piping & Wiring Instalasi Fire Alarm
- Corridor Fire Alarm Installation Ttk 12 2 Hari
- Unit Apartment Fire Alarm Installation Ttk 36 12 Hari
N LANTAI 12
I ELECTRICAL WORK
Piping & Wiring untuk Instalasi Penerangan
- Corridor Apartment Ttk 59 5 Hari
- Unit Apartment 1 - BR ( 19 Unit ) Ttk 57 6 Hari
- Unit Apartment 2 - BR ( 11 Unit ) Ttk 50 5 hari
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 200 x 100 mm Mtr 67 2 Hari
II ELECTRONIC WORK
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 100 x 100 mm Mtr 72 2 Hari
O LANTAI 13
I ELECTRICAL WORK
Piping & Wiring untuk Instalasi Penerangan
- Corridor Apartment Ttk 59 5 Hari
- Unit Apartment 1 - BR ( 19 Unit ) Ttk 57 6 Hari
- Unit Apartment 2 - BR ( 11 Unit ) Ttk 50 5 hari
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 200 x 100 mm Mtr 67 2 Hari
II ELECTRONIC WORK
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 100 x 100 mm Mtr 72 2 Hari
P LANTAI 14
I ELECTRICAL WORK
Piping & Wiring untuk Instalasi Penerangan
- Corridor Apartment Ttk 59 5 Hari
- Unit Apartment 1 - BR ( 19 Unit ) Ttk 57 6 Hari
- Unit Apartment 2 - BR ( 11 Unit ) Ttk 50 5 hari
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 200 x 100 mm Mtr 67 2 Hari
II ELECTRONIC WORK
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 100 x 100 mm Mtr 72 2 Hari
Q LANTAI 15
I ELECTRICAL WORK
Piping & Wiring untuk Instalasi Penerangan
- Corridor Apartment Ttk 59 5 Hari
- Unit Apartment 1 - BR ( 19 Unit ) Ttk 57 6 Hari
- Unit Apartment 2 - BR ( 11 Unit ) Ttk 50 5 hari
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 200 x 100 mm Mtr 67 2 Hari
II ELECTRONIC WORK
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 100 x 100 mm Mtr 72 2 Hari
R LANTAI 16
I ELECTRICAL WORK
Piping & Wiring untuk Instalasi Penerangan
- Corridor Apartment Ttk 36 3 Hari
- Unit Apartment 1 - BR ( 19 Unit ) Ttk 114 10 Hari
- Unit Apartment 2 - BR ( 11 Unit ) Ttk 90 9 Hari
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 200 x 100 mm Mtr 67 2 Hari
II ELECTRONIC WORK
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 100 x 100 mm Mtr 72 2 Hari
VERTICAL LADDER
Electrical
Ladder Cable 1000 S/D 500 x 100 mm Mtr 14 1 Hari
Electronic
Ladder Cable 1000 x 100 mm Mtr 9 1 Hari
VERTICAL PIPE
LANTAI 2 S/D LANTAI 13
Hydrant & Sprinkler
- Hydrant Riser Mtr 107 7 Hari
- Sprinkler Riser Mtr 61 5 Hari
Koko Nurprianto ( )