BAR CHART

BAR CHART MECHANICAL, ELECTRICAL, & PLUMBING WORK


FEBRUARI 2021
NO ITEM KERJA SAT VOLUME DURASI KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22

PRELIMINARIES WORK
1 Membuat Gambar Kerja / Shop Drawing Instalasi lot 1 14 Hari
2 Mengajukan Approval Material dan Dokumen yang di perlukan lot 1 14 Hari
3 Membuat Dokumen Kontrak lot 1 14 Hari
4 Supervisi dan Koordinasi Lapangan lot 1 14 Hari

A BASEMENT FLOOR
I PLUMBING WORK
Instalasi Pipa Air Bersih
PPR Pipe PN-10 mtr 122 4 Hari
GIP Medium Class, DN 150 - 80 mm mtr 42 2 Hari
Instalasi Pipa SW, WW, KD, RW
PVC AW, Air Kotor (SW) mtr 56 2 Hari
PVC AW, Air Bekas (WW) mtr 50 2 Hari
PVC AW, Air Hujan (RW) mtr 10 2 Hari
Instalsai Pipa Air Bersih
PPR Pipe PN-10 mtr 305 9 Hari
R
II ELECTRICAL WORK E
Piping & Wiring untuk Instalasi Penerangan S
- Parkir and Public Area Ttk 50 6 Hari
C
- Kios Area Ttk 10 2 Hari
H
Pemasangan Tray
E
- Tray Cable Type Cage 300 S/D 100 x 100 S/D 50 mm mtr 99 1 Hari
III ELECTRONIC WORK
D
i FIRE ALARM U
Piping dan Wiring untuk Instalasi Fire Alarm L
- Basement Floor Ttk 28 5 Hari E
ii SOUND SYSTEM
Piping dan Wiring untuk Instalasi Sound System
S
- Basement Floor Ttk 12 3 Hari
A
Pemasangan Tray
M
- Tray Cable Type Cage 800 S/D 200 x 100 mm mtr 132 2 Hari
IV MVAC WORK
P
REFRIGERANT PIPE
A
Copper Tube, 1/4" + 5/8" C/W Insulation mtr 18 4 Hari I

L
A
H
A
N
PT. TRIKARSA BAHTERA ABADI 1 WEEKLY WORK PLAN
S
P
FEBRUARI 2021 A
NO ITEM KERJA SAT VOLUME DURASI KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22 I
DUCTING AND GRILEE AIR VENTILATION
EF - BS.1 L
DUCTING EXHAUST FAN mtr2 178 14 Hari A
EF - BS.2
H
DUCTING EXHAUST FAN mtr2 10 4 Hari
A
EF - BS.4
N
DUCTING EXHAUST FAN mtr2 2 4 Hari
EF - BS.7
DUCTING EXHAUST FAN mtr2 2 4 Hari S
EF - BS.9 I
DUCTING EXHAUST FAN mtr2 16 4 Hari A
EF - BS.12 P
DUCTING EXHAUST FAN mtr2 2 4 Hari
IF - BS.1
DUCTING INTAKE FAN mtr2 90 14 Hari
IF - BS.2
DUCTING INTAKE FAN mtr2 156 14 Hari

V FIRE FIGHTING WORK


Instalasi Black Steel Pipe Fire Fighting Hydrant mtr 6 2 Hari
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 350 14 Hari

B SEMI BASEMENT FLOOR


I PLUMBING WORK
Instalasi Pipa Air Bersih
PPR Pipe PN-10 mtr 223 7 Hari
LAHAN SIAP UNTUK PASANG SUPPORT
PPR Pipe PN-10 ( Toilet ) mtr 38 1 Hari
II MVAC WORK
REFRIGERANT PIPE
Copper Tube, 1/4" + 5/8" c/w insulation mtr 44 4 Hari
DUCTING AND GRILEE AIR VENTILATION
EF - SB.1
DUCTING EXHAUST FAN mtr 639 14 Hari

LAHAN SIAP UNTUK PASANG SUPPORT


EF - SB.3
DUCTING EXHAUST FAN mtr 5 1 Hari
EF - SB.5
DUCTING EXHAUST FAN mtr 1 1 Hari
EF - SB.6
DUCTING EXHAUST FAN mtr 12 2 Hari
EF - SB.7
DUCTING EXHAUST FAN mtr 74 7 Hari
EF - SB.8
DUCTING EXHAUST FAN mtr 1 1 Hari
EF - SB.11
DUCTING EXHAUST FAN mtr 11 1 Hari
EF - SB.12
DUCTING EXHAUST FAN mtr 47 4 Hari

PT. TRIKARSA BAHTERA ABADI 2 WEEKLY WORK PLAN


ASANG SUPPORT
FEBRUARI 2021
NO ITEM KERJA SAT VOLUME DURASI KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22

IF-SB.1
DUCTING INTAKE FAN mtr 195 14 Hari
IF-SB.2
DUCTING INTAKE FAN mtr 322 14 Hari
IF-SB.3
DUCTING INTAKE FAN mtr 61 6 Hari

III FIRE FIGHTING WORK


Instalasi Black Steel Pipe Fire Fighting Hydrant mtr 278 14 Hari
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 560 15 Hari
IV ELECTRONIC WORK
i FIRE ALARM
Piping dan Wiring untuk Instalasi Fire Alarm
- Semi Basement Floor Ttk 26 1 Hari
ii SOUND SYSTEM RESCHEDULE SAMPAI SKIMCOAT
Piping dan Wiring untuk Instalasi Sound System
- Semi Basement Floor Ttk 26 1 Hari

C GROUND FLOOR
I MVAC WORK
REFRIGERANT PIPE

RESCHEDULE COMERCIAL AREA


Copper Tube, c/w insulation ( PODIUM AREA ) mtr 146 10 Hari
DUCTING AND GRILEE AIR CONDITIONING
TOKO AREA
DUCTING AIR CONDITIONING mtr2 94 14 Hari
PODIUM AREA
IU/OU - G.3
DUCTING INDOOR / OUTDOOR UNIT mtr2 8 6 Hari
IU - G.4A
DUCTING INDOOR UNIT mtr2 14 6 Hari
IU - G.4B
DUCTING INDOOR UNIT mtr2 18 6 Hari
IU - G.4C
DUCTING INDOOR UNIT mtr2 16 6 Hari
IU - G.4D
DUCTING INDOOR UNIT mtr2 14 6 Hari
IU - G.4E
DUCTING INDOOR UNIT mtr2 14 6 Hari

D LANTAI 2
I MVAC WORK
REFRIGERANT PIPE
Type 1 - BR ( 12 Unit )
Copper Tube, c/w insulation mtr 45 4 Hari
Type 2 - BR ( 2 Unit )
Copper Tube, c/w insulation mtr 40 4 Hari
PODIUM AREA
RESCHEDULE COMERCIAL AREA
Copper Tube, c/w insulation mtr 129 10 Hari

PT. TRIKARSA BAHTERA ABADI 3 WEEKLY WORK PLAN


FEBRUARI 2021
NO ITEM KERJA SAT VOLUME DURASI KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22

E LANTAI 3
I PLUMBING WORK
Instalasi Pipa Air Bersih
PPR Pipe PN-10 mtr 44 2 Hari
Instalasi Pipa Air Bersih Unit Apartment Toilet
PPR Pipe PN-10 mtr 237 4 Hari

II FIRE FIGHTING WORK


Instalasi Black Steel Pipe Fire Fighting Hydrant mtr 3 1 Hari
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 206 10 Hari

III ELECTRICAL WORK


Wiring untuk Instalasi Penerangan
- Toko 1 Ttk 8 1 Hari
- Toko 3 Ttk 8 1 Hari
- Toko 5 Ttk 10 1 Hari
RESCHEDULE COMERCIAL AREA
- Toko 6 Ttk 10 1 Hari
- Toko 9 Ttk 8 1 Hari
- Toko 10 Ttk 9 1 Hari

F LANTAI 4
I PLUMBING WORK
Instalasi Pipa Air Bersih Unit Apartment Toilet
PPR Pipe PN-10 mtr 404 11 Hari `
II FIRE FIGHTING WORK
Instalasi Black Steel Pipe Fire Fighting Hydrant mtr 4 1 Hari `
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 161 8 Hari `
III ELECTRICAL WORK
Piping dan Wiring untuk Instalasi Penerangan
- Toko 5 Ttk 25 2 Hari RESCHEDULE SAMPAI AREA TOKO SIAP

G LANTAI 5
I PLUMBING WORK
Instalasi Pipa Air Bersih Corridor
PPR Pipe PN-10, DN 15 mm mtr 5 1 Hari
Instalasi Pipa Air Bersih Unit Apartment Toilet
PPR Pipe PN-10, DN 20 - 15 mm mtr 209 4 Hari
Instalasi Pipa SW,WW,KD,RW
PVC AW, Air Kotor ( SW ) mtr 63 2 Hari
PVC AW, Air Bekas (WW) mtr 156 6 Hari
PVC Class D,Vent (VT) mtr 215 8 Hari
PVC AW, Air Hujan (RW) mtr 76 3 Hari
II FIRE FIGHTING WORK
Instalasi Black Steel Pipe Fire Fighting Hydrant mtr 10 1 Hari `
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 360 8 Hari `

H LANTAI 6
I PLUMBING WORK
Instalasi Pipa Air Bersih Corridor
PPR Pipe PN-10, DN 15 mm mtr 5 1 Hari

PT. TRIKARSA BAHTERA ABADI 4 WEEKLY WORK PLAN


FEBRUARI 2021
NO ITEM KERJA SAT VOLUME DURASI KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22

Instalasi Pipa Air Bersih Unit Apartment Toilet


PPR Pipe PN-10, DN 20 - 15 mm mtr 209 4 Hari
Instalasi Pipa SW,WW,KD,RW
PVC AW, Air Kotor ( SW ) mtr 63 2 Hari
PVC AW, Air Bekas (WW) mtr 156 6 Hari
PVC Class D,Vent (VT) mtr 214 8 Hari
PVC AW, Air Hujan (RW) mtr 55 2 Hari
II FIRE FIGHTING WORK
Instalasi Black Steel Pipe Fire Fighting Hydrant mtr 10 1 Hari `
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 206 10 Hari

I LANTAI 7
I PLUMBING WORK
Instalasi Pipa SW,WW,KD,RW
PVC AW, Air Kotor ( SW ) mtr 125 1 Hari
PVC AW, Air Bekas (WW) mtr 312 3 Hari
PVC Class D,Vent (VT) mtr 428 4 Hari
PVC AW, Air Hujan (RW) mtr 38 1 Hari
II FIRE FIGHTING WORK
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 206 10 Hari

J LANTAI 8
I PLUMBING WORK
Instalasi Pipa SW,WW,KD,RW
PVC AW, Air Kotor ( SW ) mtr 125 1 Hari
PVC AW, Air Bekas (WW) mtr 312 3 Hari
PVC Class D,Vent (VT) mtr 428 4 Hari
PVC AW, Air Hujan (RW) mtr 38 1 Hari
II FIRE FIGHTING WORK
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 206 10 Hari

K LANTAI 9
I FIRE FIGHTING WORK
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 206 10 Hari

L LANTAI 10
I FIRE FIGHTING WORK
Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline dan Cabang mtr 206 10 Hari

M LANTAI 11
I ELECTRICAL WORK
Piping & Wiring untuk instalasi penerangan
- Unit Apartment 1 - BR ( 19 Unit ) Ttk 57 6 Hari
- Unit Apartment 2 - BR ( 11 Unit ) Ttk 50 5 hari
II ELECTRONIC WORK
i FIRE ALARM
Piping & Wiring Instalasi Fire Alarm
- Corridor Fire Alarm Installation Ttk 12 2 Hari
- Unit Apartment Fire Alarm Installation Ttk 36 12 Hari

PT. TRIKARSA BAHTERA ABADI 5 WEEKLY WORK PLAN


FEBRUARI 2021
NO ITEM KERJA SAT VOLUME DURASI KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22

III FIRE FIGHTING WORK


Instalasi Black Steel Pipe Fire Fighting Sprinkler Mainline mtr 206 10 Hari

N LANTAI 12
I ELECTRICAL WORK
Piping & Wiring untuk Instalasi Penerangan
- Corridor Apartment Ttk 59 5 Hari
- Unit Apartment 1 - BR ( 19 Unit ) Ttk 57 6 Hari
- Unit Apartment 2 - BR ( 11 Unit ) Ttk 50 5 hari
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 200 x 100 mm Mtr 67 2 Hari
II ELECTRONIC WORK
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 100 x 100 mm Mtr 72 2 Hari

O LANTAI 13
I ELECTRICAL WORK
Piping & Wiring untuk Instalasi Penerangan
- Corridor Apartment Ttk 59 5 Hari
- Unit Apartment 1 - BR ( 19 Unit ) Ttk 57 6 Hari
- Unit Apartment 2 - BR ( 11 Unit ) Ttk 50 5 hari
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 200 x 100 mm Mtr 67 2 Hari
II ELECTRONIC WORK
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 100 x 100 mm Mtr 72 2 Hari

P LANTAI 14
I ELECTRICAL WORK
Piping & Wiring untuk Instalasi Penerangan
- Corridor Apartment Ttk 59 5 Hari
- Unit Apartment 1 - BR ( 19 Unit ) Ttk 57 6 Hari
- Unit Apartment 2 - BR ( 11 Unit ) Ttk 50 5 hari
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 200 x 100 mm Mtr 67 2 Hari
II ELECTRONIC WORK
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 100 x 100 mm Mtr 72 2 Hari

Q LANTAI 15
I ELECTRICAL WORK
Piping & Wiring untuk Instalasi Penerangan
- Corridor Apartment Ttk 59 5 Hari
- Unit Apartment 1 - BR ( 19 Unit ) Ttk 57 6 Hari
- Unit Apartment 2 - BR ( 11 Unit ) Ttk 50 5 hari
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 200 x 100 mm Mtr 67 2 Hari
II ELECTRONIC WORK
Pemasangan Tray

PT. TRIKARSA BAHTERA ABADI 6 WEEKLY WORK PLAN


FEBRUARI 2021
NO ITEM KERJA SAT VOLUME DURASI KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22

- Tray Cable Type Cage 400 S/D 100 x 100 mm Mtr 72 2 Hari

R LANTAI 16
I ELECTRICAL WORK
Piping & Wiring untuk Instalasi Penerangan
- Corridor Apartment Ttk 36 3 Hari
- Unit Apartment 1 - BR ( 19 Unit ) Ttk 114 10 Hari
- Unit Apartment 2 - BR ( 11 Unit ) Ttk 90 9 Hari
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 200 x 100 mm Mtr 67 2 Hari
II ELECTRONIC WORK
Pemasangan Tray
- Tray Cable Type Cage 400 S/D 100 x 100 mm Mtr 72 2 Hari

VERTICAL LADDER
Electrical
Ladder Cable 1000 S/D 500 x 100 mm Mtr 14 1 Hari
Electronic
Ladder Cable 1000 x 100 mm Mtr 9 1 Hari

VERTICAL PIPE
LANTAI 2 S/D LANTAI 13
Hydrant & Sprinkler
- Hydrant Riser Mtr 107 7 Hari
- Sprinkler Riser Mtr 61 5 Hari

PT. TRIKARSA BAHTERA ABADI

Dibuat oleh : Diketahui oleh :

Koko Nurprianto ( )

PT. TRIKARSA BAHTERA ABADI 7 WEEKLY WORK PLAN