Project Titel : Water Transmission Scheme from Madinat Zayed to Liwa and

Qusahwira LOT B

Contract No. : N-12192.1

Clint : Abu Dhabi Transmission and Dispatch Company (TRANSCO)

Consultant : BILFINGER-TEBODIN Middle East

Contractor : Societe Egyptienne D’Entreprises (SEDE)

Document Title : Design Calculation Sheet For Restrained Pipe Length


(C) construction Condition VI.A & VI.B
Part (C.1) Horizontal Bends

Doc. No. : N12192.1-B-C-P-ECTO-00

Societe Egyptienne D’Entreprises (SEDE)

02 18.02.2021 M. Sleeam A. ANIS SEDE Approval

01 02.11.2020 M. Sleeam A. ANIS SEDE Approval

00 05.10.2020 M. Sleeam A. ANIS SEDE Approval


Rev. Date: ORIG. BY Ckd. BY SUB. BY Description/ Issued For